Improving Cost Estimates of Construction Projects Using.docx
- 文档编号:9885799
- 上传时间:2023-02-07
- 格式:DOCX
- 页数:14
- 大小:26.60KB
Improving Cost Estimates of Construction Projects Using.docx
《Improving Cost Estimates of Construction Projects Using.docx》由会员分享,可在线阅读,更多相关《Improving Cost Estimates of Construction Projects Using.docx(14页珍藏版)》请在冰豆网上搜索。
ImprovingCostEstimatesofConstructionProjectsUsing
ImprovingCostEstimatesofConstructionProjectsUsing
PhasedCostFactors
LiLiu1andKaiZhu2
Abstract:
Centraltocost-basedcompetitionisthecapabilityto
accuratelypredictthecostofdeliveringaproject.Mostliteratureoncost
estimationfocusesonspecificestimationmethodsasgenerictechniquesandlittleattentionhasbeenpaidtotheuniquerequirementsateachprojectstage.Thisnoteattemptstoidentifythecriticalfactorsforeffectiveestimationatvariousstagesoftypicalconstructionprojects.Drawingfromorganizationcontroltheoryandcostestimatingliterature,thisnotedevelopsatheoreticalframeworkthatidentifiesthecriticalfactorsforeffectivecostestimationduringeachprojectphaseofaconventionalconstructionproject.Theunderlyinglogicisthatasacostestimatingeffortprogresses,bothtaskprogrammabilityandoutputmeasurabilityimprove.Asaresult,controleffortwillshiftfrominput-orientedcontroltoacombinationofoutputandbehaviorcontrol.
DOI:
10.1061(ASCE)0733-9364(2007)133:
1(91)
CEDatabasesubjectheadings:
Costcontrol;Estimation;Constructioncosts;Projectmanagement.
Introduction
Mostconstructioncontractsarefixedpricecontractswithincentives
forcostsavingandearlycompletionaswellaspenaltiesforcostoverrunanddelays.Centraltocost-basedcompetitionisthecapabilitytoaccuratelypredictthecostofdeliveringaproject.Overestimatedcostcouldresultinmisjudgmentforthefeasibilityofaprojectorlossofacontracttocompetitors.Ontheotherhand,thecontractorcouldincursignificantlossesfromunderestimatedcost.AssuccinctlystatedbyHicks(1992),“withoutanaccuratecostestimate,nothingshortofanactofGodcanbedonetopreventaloss,regardlessofmanagementcompetence,financestrengthofthecontractor.”
Typically,estimationofprojecteffortneedstobemadeatvariousstagesofaproject.Attheconceptualstage,aballparkfigureisneededtoascertainwhetherthefeasibilityoftheprojectshouldbeinvestigated.Lateratthebiddingandconstructionstages,fairlyreliableestimatesareneededfortenderingandbudgetcontrolpurposes.Duetodifferencesatdifferentprojectstagesinestimationobjectivesandintheavailabilityofinformationrequiredforusingvariousestimationmethods,effectiveestimationatdifferentprojectstagesislikelytodependondifferentsetsoffactorsateachstage.Forexample,clearscopedefinitionandspecificationofaprojectcouldhavemoresignificanteffectonthelevelofestimateaccuracyintheearlystagethaninthelaterstages.
Althoughanyestimatingtechniquemayhaveinherenterrorsresultingfromtheestimationprocess(Morrison1984),externalfactorsstillhavesignificantinfluenceontheaccuracyofestimation(AkintoyeandFitzgerald2000).Itisthereforeimportanttoidentifycriticalfactorsforeffectiveestimationateachprojectstage.Mostcostestimationstudiesfocusonspecificestimationmethodsasgenerictechniquesandlittleattentionhasbeenpaidtotheuniquerequirementsateachprojectstage.Thisstudyattemptstoidentifythecriticalfactorsforeffectiveestimationatvariousstagesoftypicalconstructionprojects.
Thisnotestartswithareviewofcurrentcostestimationliteratureonconstructionprojects.Emphasisisonaccuracylevel,criticalfactors,andcharacteristicsofdifferentstages.Then,drawingfromorganizationalcontroltheory,aframeworkforgroupingcriticalfactorsatdifferentprojectstagesisproposed.Finally,conclusionsaredrawnandimplicationsforfurtherresearcharediscussed.
PriorResearch
Accuratepredictionofconstructioncostsisheavilydependentupontheavailabilityofqualityhistoricalcostdataandthelevelofprofessionalexpertiseamongotherthings.Thelimitedinformationavailableatanearlystageofaconstructionprojectmaymeanthatthequantitysurveyormustmakeassumptionsaboutthedesigndetailsofaproject,whichmaynoteventuateasthedesign,planning,andconstructionevolve.
Oneofthecriticalindicatorsofeffectiveestimationistheaccuracylevel.Reviewofstudiesoncostestimationaccuracyforconstructionprojectsdatingbacktothe1970sindicatesthattheestimationaccuracylevelforconstructionprojectshardlychangedoverthepast4decadesandremainsataround10%level(McCaffer1976;FlanaganandNorman1983;Morrison1984;
Cheong1991;GunnerandSkitmore1999;LingandBoo2001).
Awiderangeoffactorsinfluencingcostestimationhasbeenidentifiedbyextantliteratureincludinggovernmentregulation,planchanges,qualityofthecontractormanagementteam,priorityonconstructiondeadlines,completenessandtimelinesofprojectinformation(Koehnetal.1978),biddingsituations,projectcharacteristics,
experienceonsimilartypeofproject,theestimatingprocess(ShashandAl-Khaldi1992),andtheexperienceoftheestimators(LoweandSkitmore1994;Al-HarbiandJohnston1994).
Toimprovetheeffectivenessofmanagingtheestimationprocess,someresearchersattemptedtoclassifythelargenumberofcostfactorsintocategoriesoffactorswithsimilarattributes(Akintoye2000;TrostandOberlender2003).Here,weregroupthecostfactorsidentifiedbyliteratureintoninecategories:
Projectinformation,teamexperience,costinformation,estimationprocess,teamalignment,estimationdesign,expectedaccuracy,reviewandacceptanceofestimateandidiosyncraticfactorsthatarebeyondthecontroloftheprojectteam.Thiscategorizationwillbeusedindevelopingtheframeworkforidentifyingfactorsinfluencingestimationaccuracy.
OrganizationalControlTheory
Inthisstudy,organizationalcontroltheoryisadoptedasthetheoreticalbasisforconstructingastage-by-stageestimationframework.Controlisconceptualizedinthisnoteasinfluencesexertedbyanorganizationusingvariousmechanismsthathelpaligntheactionsofitsemployeeswiththeinterestsoftheorganization(Tannenbaum1967).Organizationalcontroltheoryidentifiesthreetypesormodesofcontrolthatcanbedirectedatachievingthebehaviornecessarytosecuredesiredperformance.
Behaviorcontrolseekstosecureaspecifiedtypeofbehaviorinthebeliefthatthebehaviordeliverstherightresults.Behaviorcontrolsareproceduresthatlaydownasequenceofoperationsthatmustbefollowed.Costestimationmethodsexemplifythisformofcontrol.
Outputcontrolspecifiesthescheduleofoutputsdesired.Theassumptionisthatpeople,whoknowwhattheirtargetsare,adoptappropriatebehaviorstoachievethem.Forexample,specifyingexpectedestimationaccuracyisaformofoutputcontrol.Anotherexampleofoutputcontrolistolinkperformance(output)topromotion.
Inputcontrolregulatestheinputintothetransformationprocesses.
Inthecaseofcostestimation,inputincludeshistoricalestimation,designinformation,experienceoftheestimators,andmaterialprice.Thismaybeachievedthroughmechanismssuchasselectingtherightpeople,improvingdataquality,andintegratingdesignwithcostestimation.Inputcontrolmayalsobeimplementedbydevelopingrelevantknowledge,skills,andvaluesinexistingorganizationalmembers.
FigpresentsOuchi’scontrolframework(Ouchi1979)whichsubsequentlyformsthebasisformanyempiricalstudiesusingcontroltheory.Taskprogrammabilityisdefinedasthedegreetowhichappropriatebehaviorscanbespecifiedinadvance(Eisenhardt1985)andoutputmeasurabilityisdefinedasthedegreetowhichoutputcanbereliablyandaccuratelymeasured(Ouchi1979).Theframeworkshowsthatwhentaskprogrammabilityishigh,itispossibletospecifybehaviorsnecessarytoachievedesiredresults—behaviorcontrolisappropriate.Whenoutputmeasurabilityishigh,thenoutputcontrolcanbeemployedtoachievethedesiredresults.Whentaskprogrammabilityandoutputmeasurabilityarebothlow,then,inputcontrolistheappropriatecontrol
modetodeliverhighperformance.
Incostestimationprocess,theinfluencefactorscouldbegroupedintoinput,behavioral,andoutputcontroltypes.Then,throughapplicationofthecontrolframeworkasshowninFig.1,weproposeaframeworkthathelpsimprovecostestimatesateachoftheprojectphases.
TheFramework
Inthefollowing,thekeyinput,output,andprocessfactorsforcostestimationateachstageareidentifiedforconstructionprojectsundertheconventionalprocurementsystems.Wearguethatthelevelsoftaskprogrammabilityandoutputmeasurabilityincreaseasaprojectprogresses.Therefore,thelocusofcontrollingestimationtaskatdifferentstagesshouldbedependentontheleveloftaskprogrammabilityandoutputmeasurability.Then,thekeyinput,output,andbehavioralfactorsthatcouldbecontrolledforestimatingtaskateachprojectstageareidentified.
ProjectPhasesandControlModes
Theconventionalprocurementsystemanddesign-buildaretwowidelyadoptedprocurementsystemsintheconstructionindustry,accountingforabove80%ofconstructionprojectsintheUnitedKingdomin1998(Masterman2002).Othersystemsincludemanagement-orientedsystemanddiscretionarysystem.Althoughthetypicalprojectphasesandactivitiesforeachphasearedifferentdependingonthetypeofprocurementsystem,theinformationavailabilityincreasesasaprojectprogresses.Similarly,themanagementobjectivesthatdriveforcostestimationatdifferentprojectphasesalsofollowasimilarpatternasaprojectprogresses.Informationavailabilityandmanagementobjectivesaretwocriticalfactorsthatinfluencethelevelsoftaskprogrammability
andoutcomemeasurabilitywhich,inturn,determinetheeffectivenessofdifferen
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- Improving Cost Estimates of Construction Projects Using
链接地址:https://www.bdocx.com/doc/9885799.html