302HVACSYSTEMTESTINGBALANCINGANDPERFORMANCEVERIFICATION
AABCSpecificationsforTestingandBalancingHVACSystems
TheAssociatedAirBalanceCouncil(AABC)TotalSystemBalancing–
SpecificationsforHVACTesting,BalancingandPerformanceVerification
TOTALSYSTEMBALANCEINCLUDES--ThefollowingchapterreferencesaretakenfromtheAABC2002NationalStandardforTotalSystemBalance:
1.FanSystems:
Supply/Return/Relief/Exhaust(Chapter10)
2.ConstantandVariableAirSystems(Chapter8)
3.DualDuctSystemsandHighPressureSystems(Chapter9)
4.Multi-ZoneSystems(Chapter7)
5.LaboratoriesandPositivelyPressurizedAreas(Chapter16)
6.HydronicSystems(Chapter11)
7.SoundTesting(Chapter18)
8.VibrationTesting(Chapter19)
9.DuctLeakageTesting(Chapter5)
10.CoolingTowerTesting(Chapter13)
11.SmokeControlTesting(Chapter20)
12.Commissioning(Chapter21)
13.TemperatureControlSystem(Chapter12)
SELECTIONOFTHETESTANDBALANCEAGENCY
TheTestandBalanceAgencyshallbeselectedfromthelist
ofpre-qualified,pre-approvedCertifiedTestandBalanceAgencies
below:
Thesespecifiedagencieshaveaproventrackrecordofproperly
testandbalanceandstandingbehindtheirwork:
AMERICANAIRBALANCECO.,INC.
MainOffice
4721E.HunterAve.
Anaheim,CA92807
(714)693-3700
LOSANGELESAIRBALANCECOMPANY,INC.
1848W.11thSt.,UnitN
Upland,CA91786
(909)931-1114
PENNAIRCONTROL,INC.
MainOffice
5941LakeshoreDrive
Cypress,CA90630
(714)220-9091
WINAIRE,INC.
MainOffice
15641ChemicalLane,Suite#A
HuntingtonBeach,CA92649
(714)901-2747
TheTestandBalanceAgenciesnamedcomplywiththeuniversallyacceptedNationalStandardssetforthbyTheAssociatedAirBalanceCouncilwhichweredevelopedtohelptheengineerachievedesignintent.
SystemBalanceshallbeperformedbytheseagencieswhoarenotaffiliatedwithanymechanicalcontractor,architect,orengineerOnlytimelysubmittals(within90daysofawardofcontract)namingoneofthesepre-approvedTestandBalanceAgencieswillreceiveapproval.
ThenameoftheselectedTestandBalanceAgency,plusthenameand
registrationnumberofthecertifiedTestandBalanceEngineer,shallbe
submittedtotheMechanicalEngineerbytheGeneralContractorforapprovalwithinthirty(90)daysaftertheawardofthecontract.
Ifacompleteandqualifyingsubmittalspecifyingoneofthepre-approved
TestandBalanceAgenciesnamedaboveisnotreceivedwithinthespecifiedtime,theMechanicalEngineershallselecttheTestandBalanceAgencyfromthepre-approvedlistofqualifiedTestandBalanceAgenciesabove.
Inaddition,noworkbytheMechanicalContractorshallcommenceuntiloneoftheTestandBalanceAgenciesnamedabovehassignedoffontheshopdrawings;itisunderstood,thatmanyfunctionsofTestandBalance,includingpre-constructionmeetings,ductleakagetestingandinspectionofinstallationrequireearlyinvolvementintheprojectinasupportfunctiontotheMechanicalEngineer.
WORKOFOTHERTRADES
TheGeneralContractorwillprovidetheTestandBalanceAgencywith:
1.Withinthirty(90)daysafterselection:
a.Constructiondrawings
b.Equipmentspecifications
c.Writtencontract
d.Equipmentsubmittals
2.Asissuedorreceived:
a.Changeorders
b.Equipmentmanufacturer’ssubmittaldata
c.MechanicalContractor’sshopdrawings
d.Temperaturecontroldrawings
e.Projectschedule
f.Reasonabletime
g.Completelyoperablesystem
3.Beforetestingandbalancingisstarted,theMechanicalContractorshalladjustbeltsandsheaves,alignallparts,oilandgreasebearingsinaccordancewithmanufacturer’sinstructions,cleanexteriorsurfacesofcoiltubesandfins,flushinteriorofoiltubesuntilcleanandcheckmixingdamperoperationtoinsurefreeoperationandactivationbythecorrectthermostat.
4.TheMechanicalContractorshallberesponsibleforcertifying,inwriting,thatthesystem,asscheduledforbalancing,isoperationalandcomplete.Completenessshallincludenotonlythephysicalinstallation,buttheMechanicalContractor’scertificationthattheprimemovers,fans,pumps,refrigerationmachines,boilers,etc.areinstalledingoodworkingorder,andthatthefullloadperformancehasbeenpreliminarilytestedunderthecertificationoftheMechanicalContractor.Beforeanytestingandbalancingisstarted,acompletereportshallbesenttotheTestandBalanceAgency.
5.TheMechanicalContractorshallberesponsibleformakingallmodificationstorectifydiscrepanciesreportedbytheBalancingContractorasindicatingnon-compliancewiththecontractdocuments.
6.TheHVACControlsContractorshall,atnoadditionalcost,
providethree(3)setsorcopiesofallnecessaryprograms,software,cablesandspecialtytoolstotheTestandBalanceAgencytooperateandcalibrateallsystems.Further,theControlsContractorshallcoordinatewiththeTestandBalanceAgencyasnecessarytoaccomplishfullyoperationalandproperlybalancedsystems.
TESTINGANDBALANCING
1.Withinthirty(30)daysafterreceiptofthetestingandbalancingcontract,plans,specificationsandcompleteequipmentsubmittals,theTestandBalanceAgencyshallsubmitanagendadescribing
thefollowing:
a.Fieldobservationreports
b.AnoverviewofsystemTestandBalanceprocedures:
1.DemonstratingcompleteunderstandingofthedesignintentbytheTestandBalanceAgency.
2.IdentifyingpotentialproblemsforperformingTotalSystemBalanceandsuggestingpossiblechangestoallowthemosteffectiveTotalSystemBalance.
c.AABCNationalProjectPerformanceGuaranty.
d.AABCCertificationofTestandBalanceEngineers
andTechnicians.
e.InstrumentcalibrationcertificatesofeachinstrumentthatmaybeusedalongwithspecificIDnumbers(i.e.,serialnumbers.)
SCOPEOFWORK
OngoingInspection
1.TheTestandBalanceAgencyshallvisitthejobsiteduringtheearlystagesoffabricationtoinspectductInstallation.AreportshallbesubmittedtotheMechanicalEngineerlistinganydeficienciesfoundandmakingrecommendationsforworktobeperformedordevicestobeaddedtoallowforproperbalancing.
TotalSystemBalance
1.Eachpieceofequipmentandtheentiresystemshallbeadjustedtoinsureproperfunctionofallcontrols,properdistributionofair,maintenanceoftemperatures,eliminationofdraftsandvibrationandleftinfirstclassoperatingcondition.
2.TheairsystemshallbeadjustedtoobtaintheairvolumesspecifiedbytheMechanicalEngineer,butreadjustedifrequiredtoobtaindesigntemperatureineachroom.TheMechanicalContractorshallmakedrivechanges,installadditionaldampers,vanes,grillebaffles,etc.,asmayberequiredonthejob.
3.Wherevertheuseofmulti-louvers(insupply,exhaust,orreturnairgrilles)createsobjectionablenoise,two
(2)inchthick,six(6)lb.fiberglassboardshallbeinstalledinthegrilleopening,slottedfortheproperairquantity.ThisshallbeaccomplishedbytheMechanicalContractor.
4.Balancethesupplyandreturnairsystems(withthechillersoperating)byfirstarrivingatthefantotalairquantity,readingairvelocitiesatcoolingcoilsat55degreesF,returnairandoutsideairopenings;andaducttraverse.ThefanRPMshallbeadjustedforthespecifiedairquantitiesallowingforthemaximumof2%forductleakage.Thequantityofairtoeachoutletshallnotbelessthanthatshownonthedrawingsandnotgreaterthan10%ofthatamount.Ifsoinstructedbythemechanicalengineer,furtherbalancingoftemperaturesshallbemadeandindicatedbyathermometerorbytemperaturerecorder.
5.PerformPitotTubeTraverseofallsupply,returnandexhaustsystems.
a.Exceptasspecificallyindicatedherein,PitotTubeTraverseshallbetakeninbranchductstoassurespecifiedflowtoallzones.Pitottubes,associatedinstruments,traversingandtestingtechniquesshallconformtotheASHRAEHandbookofFundamentals.
b.Testholesshallbeinastraightduct,asfaraspossibledownstreamfromtheelbows,bends,take-offsandotherturbulencegeneratingdevices,tooptimizereliabilityofflowmeasurements.
6.Furnishtypewrittendataforallsupplyfanstabulating:
a.QuantityofairinCFMateachairoutletorinlet.
b.Dryandwetbulbtemperaturesateachthermostattothenearest1/10of1degree.
c.Outdoordryandwetbulbtemperatures,winddirectionandvelocity,andbarometricpressureatthetimetestsareconducted.
d.RPMoffanorblower.
e.RPMofmotor.
f.Ampereinputofeachmotor(onereadingoneachlegifthree(3)phase).
g.NoloadAmperageandbrakehorsepowercalculationsonallmotors1/2horsepowerorlarger.
h.Staticpressureinincheswatergaugeatinletoffanorblower.
i.DuctTraversedata.
7.FurnishtypewrittendatafortheCoilstabulating:
a.Enteringandleavingwatertemperature.
b.QuantityofairinCFM.
c.FacevelocityinFPM.
d.Dryandwetbulbairtemperatureenteringandleavingcoil.
e.CapacityofcoilinBTUH.
f.QuantityofwatercirculatedthroughcoilinGPM.
8.FurnishtypewrittendatafortheChillerstabulating:
a.Suctionandcondensingtemperatureandpressures.
b.Ampereinputofmotorsunderfullload(oneforeachphaseleg).
c.Temperaturesofenteringandleavingchilledandcondenserwater.
d.CapacityofmachineinBTUH.
e.QuantityofchilledandcondenserwatercirculatedthroughmachineinGPM.
9.FurnishtypewrittendataforthePumpstabulating:
a.QuantityofwatercirculatinginGPM.
b.SuctionanddischargepressureinPSIG.
c.Ampereinpu
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 302 HVAC SYSTEM TESTING BALANCING AND PERFORMANCE VERIFICATION
链接地址:https://www.bdocx.com/doc/9558014.html