越南输煤系统安装作业指导书英文B版English
TableofContent
1CompilationBasisandReferredStandard3
2ProjectReviewandConstructionScope4
2.1ProjectReview4
2.2ConstructionScope13
3ConstructionPersonnelandTheirQualification14
4ConstructionMachine,ToolandSafetyProtectionArticle14
4.1ConstructionMachineandTool14
4.2SafetyProtectionArticle16
5ConstructionConditionandPreparation16
6ConstructionProcedure,MethodandRequirement18
6.1ConstructionProcedureFlowChart18
6.2ConstructionMethodandRequirement19
7QualityControlandAcceptance32
8Safe,CivilizedConstructionandEnvironmentManagement37
Table8-1RiskControlProgramofOccupationalHealthandSafety(RCP)39
RiskControlProgramofOccupationalHealthandSafety(RCP)39
Table8-2EnvironmentalFactorandControlMeasure42
EnvironmentalFactorAndControlMeasure42
9ConstructionProgressPlan43
1.CompilationBasisandReferredStandard
1.1Thecodeoferectionandacceptanceofelectricpowerconstruction,pipingsection(DL5031-94)
1.2Codeforradiographictestofpipe,ASMEB31
1.3Manufacturer’sdrawingandinstallationinstructionsforequipmentincoalhandlingsystem
1.4NO.1coalyardandbucker-wheelstackerandre-claimerF4281S-M0201
1.5NO.2coalyardandbucker-wheelstackerandre-claimerF4281S-M0202
1.6ArrangementdrawingofT1transfertowerF4281S-M0301
1.7ArrangementdrawingofT2transfertowerF4281S-M0302
1.8ArrangementdrawingofT3transfertowerF4281S-M0303
1.10ArrangementdrawingofT4transfertowerF4281S-M0304
1.11ArrangementdrawingofT5transfertowerF4281S-M0305
1.12ArrangementdrawingofT6transfertowerF4281S-M0306
1.13InstallationdrawingofmaintenanceequipmentF4281S-M0307
1.14ArrangementdrawingofC2beltconveyorF4281S-M0401
1.15ArrangementdrawingofC3beltconveyorF4281S-M0402
1.16ArrangementdrawingofC4beltconveyorF4281S-M0403
1.17ArrangementdrawingofC5ABbeltconveyorF4281S-M0404
1.18ArrangementdrawingofC6ABbeltconveyorF4281S-M0405
1.19ArrangementdrawingofC7ABbeltconveyorF4281S-M0406
1.20Installationdrawingofelectricdriventwo-sideploughunloaderF4281S-M0501
1.21InstallationdrawingofwaterwiperF4281S-M0502
1.22Arrangementdrawingofsampler(as-firedcoal)F4281S-M0503
1.23ArrangementdrawingofbeltscaleandcheckchainF4281S-M0504
1.24ArrangementdrawingofbulldozerhouseandrepairworkshopF4281S-M0505
1.25InstallationdrawingofequipmentandpipeinsluicepumphouseF4281S-M0506
1.26Flowdiagramofcoalhandlingsystemincludingwashdown,water-sprayingandblow-downsystemF4281S-M0601
1.27Arrangementdrawingofwashdownandblow-downpipeintransfertowerandtrestleF4281S-M0602
1.28ArrangementdrawingofspraypipeincoalyardF4281S-M0603
1.29Arrangementdrawingofcoalbunkerwashpipe,drainagecanalanddrainagepipeF4281S-M0604
1.30CoalchutewithliningboardF4281S-M0701
1.31HangerframeofcoalchuteF4281S-M0702
1.32InspectiondoorF4281S-M0703
1.33Installationdrawingofstackerandre-claimerF4281S-M0704
2ProjectReviewandConstructionScope
2.1ProjectReview
ThisprojectinvolvesinstallationworksofcoalhandlingsystemofDuyenHai1ThermalPowerPlantProject.Thecoalwillbeanthracite(Cam6A,HonGai-CamPha)fromnorthVietnam.Theannualconsumptionofcoalwillbe318800ton.Thecoalwillbetransportedtocoalunloadingwharfofplantbymeansofseaandtransportation.Beltconveyorwillbeusedforcoalconveyingfromwharftocoalbunkerbay.
Themainauxiliaryequipmentinclude:
stackerandre-claimer,tiltedrollerscreen,coalcrusher,materialregulator,power-drivenploughunloader,electricwaterwiper,hopperwallvibrator,coalyardsprayer,trestleflusher,coalchute(hopper)andliningplate.Theoverviewofsubsystemofcoalhandlingsystemisasfollows:
2.1.1Coalstorageyard
Twoparalleledthrough-typebucket-wheelstackerandre-claimerlinearcoalyardisdesignedforthisproject.Andalsodrycoalshedofspacesteeltrussstructureisdesigned.
Onebucketwheelstackerandre-claimerisarrangedforeachcoalyard,with4coalbulldozers(TY-220)and1wheelloaderasauxiliaryequipmentforcoalstackingandconveying.Thebucketwheelstackerandre-claimeranditsmainparametersareasfollows:
Description
Manufacturer
QTY
Type
Basicparameters
Buckerwheelstackerandre-claimer
ChangchunGeneratingEquipmentGroup
2
DQ1200/25
00.40
1.Ratedoutput:
stacking2500t/h,reclaiming1200t/h
2.Maximumoutput:
stacking3000t/h,reclaiming1440t/h,shuntvolume1300/1200t/h
3.Stackingheightofcoalstorageyard:
13.5maboverail,1.5munderrail.
4.Powersupplymode:
cabledrum,6600V,frequency50Hz
5.Travelingrange:
about204m,turningradius40m
6.Installedtotalpower:
430kW,maximumloadpower420kW
7.Equipmentweight:
490t,portal32t,cantileverbeltconveyor:
22.4t,runninggear32.4t,trippercar45.5t,balanceweight87t
2.1.2CoalScreeningandCrushingsystem
(1)Overviewofcoalcrushingsystem:
thereisonecoalcrushingroominthisplant,wheretworinghammercoalcrusher(800t/h)willbeinstalled.Coalcrusherandelectricmotorisconnectedbyhydrauliccouplertoreducestartingcurrent.Independentfoundationandspringisolationpedestalareadoptedforcoalcrusher.Twosetsoftiltedrollerscreen(1200t/h)willbeinstalledincoalcrusherroom,andtheinletofscreenisequippedwithswitchingbaffle,sofuelcoalcanbepassedtoC6A/Bbeltconveyorthroughbypassifnecessary.
(2)Mainequipmentincoalcrushingsystem
Maintypesandparametersofcoalcrusher
S/N
Description
Specification
Unit
QTY
Manufacturer
1
Coalcrusheranditsaccessories,includingrotor,enginebody,coupleranditsshield,etc.
KRC12enginebody
set
2
ShenyangElectricPowerMachineryGeneralFactory,CEEC
2
Electricmotoranditspedestal
YKK5001-8
set
2
XiangtanelectricmotorstockCo.,ltd
3
Hydrauliccoupler(withtemperaturerisingalarmdevice)
YOX1000
set
2
GuangzhouHydraulicTransmissionEquipmentCo.,Ltd
4
High-pressureoilpipe,quickcoupling,etc.
KRC12(includecable)
set
1
ShenyangElectricPowerMachineryGeneralFactory,CEEC
5
Vibrationandbearingtemperaturerisingmonitor(includealltransducersand20mofaudiosignalcable)
KRC12(includecable)
set
2
JiangyinQuanshengautomationinstrumentCo.,Ltd
6
Anchorbolt(includeboltforenginebodyandmotorpedestal,thelengthofboltmustbedeterminedbyconsultingwithdesigninstitute.
KRC12electricmotor
set
2
ShenyangElectricPowerMachineryGeneralFactory,CEEC
Equipmenttypeandparametersofrollerscreen
S/N
Description
Specification
Unit
QTY
Manufacturer
1
Rollerscreenbodyanditsaccessories
BGSP15
2
ShenyangElectricPowerMachineryGeneralFactory,CEEC
2
Motor-reductiongearassembly
Z68
10
SIEMENS
3
Motor-reductiongearassembly
Z48
20
SIEMENS
4
Reveringdeviceforbypass
BGSP15×20
2
ShenyangElectricPowerMachineryGeneralFactory,CEEC
5
Electric-hydraulicthruster(canbehand-actuated)
DYTP700-50
0/100
2
ZhejiangXiangshanelectricpushrodplant
2.1.3CoalHandlingSystem
(1)Coalhandlingequipment,suchasactuatingdevice,belt,carrierroller,tensiondevice,redirectionsupport,etc.aresuppliedbyHunanHengyangTransportMachineryCo.,Ltd.
(2)BeltconveyorofcoalyardstoragesystemincludesC2beltconveyor,C3A/Bbeltconveyor,andC4beltconveyor,ofwhichC2beltconveyorandC3A/Bbeltconveyorareofsamespecificationwiththatofcoalunloadingsystem.C4beltconveyorisofsamespecificationwiththatofcoalloadingsystem.C3BbeltconveyorandC4beltconveyorareequippedwiththree-waypower-drivenbaffle,sothatcoalfromC3BandC4beltconveyorcanbeunloadedonC5A/Bconveyor.
(3)BeltconveyorofcoalloadingsystemincludesC5A/Bbeltconveyor,C6A/BbeltconveyorandC7A/Bbeltconveyor,allofwhicharedesignedastwinchannel.C6A/Bbeltconveyorisequippedwiththree-waypower-drivenbafflesothatcoalfromC6A/BconveyorcanbeunloadedonC7A/Bbeltconveyorandforconnectingbeltconveyorwithcoalbunkerbay.Electric-driventwo-sideploughtripperisadoptedincoalbunkerbayforunloadingcoaltorawcoalhopper.
(4)Informationofbeltconveyor
Typeofbeltconveyor
Unit
C2
C3AB
C4
C5AB
C6AB
C7AB
DrumCenterdistance
m
91
333.5
97
144.35
177.65
186.8
Beltwidth
mm
1600
1600
1600
1200
1200
1200
capacity
t/h
2500
2500
2500
1200
1200
1200
BeltSpeed
m/s
3
3
3
2.8
2.8
2.8
Beltinclination
0º-8°
0º
0º-4°
4º-10°-16°
8°-16°
0º
Conveyingmaterial
coal
coal
coal
coal
coal
coal
Coaldensity
t/m³
0.9-1
0.9-1
0.9-1
0.9-1
0.9-1
0.9-1
Liftingheight
m
5.2
0
5.317
31.8
36
0
Ratedpower
Kw
185(400V)
2*220
185
220
250
110
TypeofTake-up
Vertical
Hydraulic
Take-upDolly
Vertical
Vertical
Vertical
2.1.4Controlmodeofcoalhandlingsystem
Programcontrolisadoptedforcoalhandlingsystem,whichwillbeincorporatedintocentralcontrolnetworkofauxiliaryplant.Itcanachievecentralizedmonitoring,managementandautomaticsequencecontrol.Inconsiderationofequipmentoverhaulingandemergencyhandling,emergencyswitchshallbesetneartheequipment.
Coalhandlingauxiliaryequipment
(1)Metering,sampling,metaldetectorandmagneticseparatordevice:
Installfiredcoalsamplingdeviceatoutletsectionofcoalcrusherroom,andinstallelectronicbeltweigher(meteringofas-firedcoalandcyclingchainweightverificationdeviceattheconveyorbetweenrawcoalbunkerandcoalcrusherroom.Fourstagesofelectromagneticironseparatorarearrangedinthisproje