线路施工工艺
TransmissionLine
ConstructionWorkmanship
TABLEOFCONTENTS
1GENERALOFTHETRANSMISSIONLINE
2FOUNDATIONWORK
2.1FLOWCHARTTOTHEFOUNDATIONWORKMANSHIP
2.2LINECHECK-SURVEY
2.3FOUNDATIONLAY-OUT
2.4FOUNDATIONEXCAVATION
2.5REQUIREMENTSOFTHEMATERIALS
2.6FORMWORKING
2.7CONCRETEPOURING
2.8CURINGANDBACKFILLING
2.9GROUNDINGINSTALLATION
2.10CAUTIONSFORSAFETYPURPOSE
3ERECTIONWORK
3.1FLOWCHARTTOTHEERECTIONWORKMANSHIP
3.2PREPARATIONBEFORECONSTRUCTION
3.3TOWERLEGSERECTION
3.4GINPOLEERECTION
3.5TOWERPARTSSUSPENDING
3.6GINPOLEDEMOLISH,BOLTSFIXINGANDSITE
CLEARING
3.7SAFETYCAUTIONS
4STRINGINGWORK
4.1FLOWCHARTTOTHESERINGINGWORK
4.2GENERAL
4.3PREPARATIONBEFORESTRINGING
4.4CONDUCTORPAYOUT
4.5SAG
4.6ACCESSORIESINSTALL
4.7OPGWSUSPENDING
1GENERALOFTHETRANSMISSIONLINE
1.1138kVLeyte-BoholtransmissionlinestartsfromOrmocSubstationand
endsinMaasinSubstation,thereisanewcreationof113.86kmlineconsistingof
313newtowers/poles.
1.2DirectionoftheLineandFoundationSeries:
MAASINS/SForward
C
B
D
A
ORMOCS/SBackward
2FOUNDATIONWORK
2.1FLOWCHARTTOTHEFOUNDATIONWORMANSHIP
Pre-workPreparation
LineCheck-survey
施工前准备
Check-survey
&Lay-out
复测、分坑
Calculation
&Lay-out
分坑测量
FabricationofRe-bars
Excavation
土石方开挖
钢筋加工
Formwork
&GroundingInstallation
ConcretePouring
基础浇浇制
ConcretePouring
Backfilling
Curing&formworkDismantlement
OhmerMeasuringfortheGrounding
2.2LINECHECK-SURVEY
Priortoconstruction,StructureListandPlanandProfileshallbefollowedintheverificationofanglesofdeflection,spanningandlegextensions,etc;duetothetree-ladensituationofthetransmissionline,andinordertoensuretheaccuracyofcheck-survey,GPS(GlobalPositioningSystem)willbeemployedforsuchpurpose.
Figure2-1GPSCheck-surveybyProfessionals
2.3FOUNDATIONLAY-OUT
2.3.1Throughthewholeline,theodolitewillbeusedinfoundationlay-out.Center
Linepointswillbestakedoutbythetheodolite,andfour45°referencepoints
willbemarkedforthefourpitstofacilitateformworking.(namely45°
referencepoint)
2.3.2Lay-outIllustration(Figure2-2)
2.4FOUNDATIONEXCAVATION
2.4.1Pitwillbeexcavatedmanuallyormechanically.
ForwardCenterLine
45°Point
45°Point
GP
BC
EP
CenterHub
AD
45°Point45°Point
BackwardCenterLine
Instruction:
GP——distancebetweenthecenterhubandthefarthestpointofthepit,furnishedbyDesignDepartment;
EP——distancebetweenthecenterhubandthenearestpointofthepit,furnishedbyDesignDepartment;
Figure2-2PlanformoftheFoundationLay-out
2.4.2Inthecaseofsoftsoillikethericefieldlocation,shoringshallbeplacedand
strengthenedenoughtoensurethesecurityofpersonsworkinginthe
pit.(Figure2-3)
2.4.3Inthecaseofstrongcurrentcomingupfromunderground,waterpumpshall
beemployeduntildesignedpitdepthhasbeenachieved,andconcretelean
shallbeplacedassoonastheexcavationhasbeenfinished.
Figure2-3ShoringFacility
2.5REPUIREMENTSFORTHEMATERIALS
2.5.1RequirementsforCement
2.5.1.1Cementqualityshallbeincompliancewiththelatestrequirements
oftheStandardSpecificationsforPortlandCement(ASTMC-150);
2.5.1.2Grand,APO,Unionshallbeoptionalsourcesforsubcontractorsto
choosecementmanufacturerfortheirapprovedqualityby
TRANSCO;
2.5.1.3Moisturizedandagglomeratedcementshallbeprohibitedfromany
useinfoundationworks;
2.5.1.4Cementpilingplaceshallbedryandventilative,storingperiod
shallnotexceed30calendardaysandcementoverlappingheight
shallbewithin14bags.
2.5.2RequirementsforCoarseAggregate(Gravel)
2.5.2.1Gravelshallconformtotherequirementsofthelatesteditionof
ASTMC33andshallconsistofhard,durableanduncoated
particleswhicharereasonablyfreefromthin,flatorelongated
particlesinallsizesandwellgraded.Thediametershouldconform
tocontinuousgrid.
2.5.2.2StandardsfollowedforGravelTestingasbelow:
SieveDesignation
U.S.Std.SquareMesh
CumulativePercentageByWeightPassing(%)
2″
100
1-1/2″
95-100
1″
-
3/4″
35-70
1/2″
-
3/8″
10-30
2.5.3StandardsFollowedforSandTestingasbelow:
SieveDesignation
U.S.Std.SquareMesh
CumulativePercentageByWeightPassing(%)
3/8″
100
NO.4
95-100
NO.8
80-100
NO.16
50-85
NO.30
25-60
NO.50
10-60
NO.100
2-10
NO.200
0-3
2.5.3.1Sandfromtheseaisstrictlyprohibitedfromanyuseinwork
mentionedherein;sourceselectionofgravelandsandshallbeasfollowsfortheirapprovedqualitybyTRANSCO:
EBRCrusherPlant,ALLOSACrusherPlant,JESSICACrusher
Plant,MCBUILDERSCrusherPlant,CODILLACrusherPlant,
HILONGOSCrusherPlant,BALTUNADOCrusherPlant。
2.5.4RequirementsforWater
2.5.4.1Waterforpreparingconcreteandmortarshallbeclean,fresh,
andfreefromorganicand/orinorganicmatterinsolutionor
suspensioninsuchamountsthatmayimpairthestrengthor
durabilityoftheconcrete;noseawaterorwaterfromexcavations
shallbeusedandwatershallbestoredincleancontainers;
2.5.4.2TherequirementsofACIshallbeapplied.
2.5.5RequirementsforReinforcingSteel
2.5.5.1Allreinforcingsteelshallcomplywithcriteriaspecifiedinthe
drawingandconformtotherequirementsofASTMA615Grade60;
2.5.5.2Surfaceofreinforcingsteelshallbefreefromdirt,impairment,
oilyfilthandpollution,andnosteelwithgrowth,defectsorlocal
rustingonitssurfaceshallbeusedinfoundationwork;
2.5.5.3Thereinforcingsteelshallnotbeplacedongrounddirectlywithout
anycushionbetweenthereinforcingsteelandtheground.
2.6FORMWORKING
2.6.1Stub-anglesettingcanbeundertakenonthebasisofasinglepit,and
formworkingandpouringcanbeexecutedpitbypitrespectively,orfourpits
undertakensimutaneously;
2.6.2Formworkdimensionsshallbecomputatedwithinthescopeofonepit;
2.6.3Computationformulaforstub-angleandformworkdimensions:
L1=L2–L×Sinα
L2=FP+√2E0×Cosα
LA1=AP+(√2b/2)×Cosα-H2tgα
LA2=AP-(√2b/2)×Cosα-H2tgα
LB1=FP+(√2b/2)/Cosα-H1tgα
LB2=FP-(√2b/2)/Cosα-H1tgα
L1DistancebetweenCenterHubandupperpointofStub-angle
L2DistancebetweenCenterHubandbottompointofStub-angle
LA1DistancebetweenCenterHubandupperfarthestpointofChimney
LA2DistancebetweenCenterHubanduppernearestpointofChimney
LB1DistancebetweenCenterHubandbottomfarthestpointofChimney
LB2DistancebetweenCenterHubandbottomnearestpointofChimney
GPDistancebetweenCenterHubandfarthestpointofPad
EPDistancebetweenCenterHubandnearestpointofPad
H1HeightfromBottomLevelofChimneytoBottomLevelofPad
H2HeightfromCenterPointofChimneyBareParttoGroundLevel
bDimensionsofChimneySectionalSurface
FPDistancebetweenCenterHubandCenterofthePit
APDistancebetweenCenterHubandConvergentPointofCenterofChimneyandGroundLevel
αAngleofStub-angleInclination
2.6.4Stub-angleandFormworkDimensions(Figure2-4,Figure2-5)
L1Centerline
LA1
LA2
GroundLevelH2
H1
EP
LB2
L2
LB1
GP
Figure2-4ProfileofFormworkDimension
FP
CenterHub
EP
LA2
L1
LB2
LA1
L2
LB1
GP
Figure2-5PlanformofFormworkDimensions
2.6.5ParameterL1andstub-anglegradientshallbecalculatedtwiceandtheerrors
betweentwocomputationsshallfallwithin1‰ofthecalcuatedvalues
respectively;
2.6.6Duringformworking,specificationandlengthofstub-angleshallbeinspected
toavoidmisusing;
2.6.7Duetothe100mmdifferencebetweenthebottomofthestub-angleandthe
bottomofthepit,andinordertofixthestub-angle,aconcreteblockshallbe
placedunderthestub-angle,ofwhichthestrengthshallexceedthatofthe
foundation.(refertoFigure2-6)
2.6.8InordertoadjustparameterL1andstub-anglegradientconveniently,flange
boltandturnbuckleshallbeemployed;(refertoFigure2-7)
2.6.9Formworkforthechimneyshallbefirmedenoughtoholdtheconcretepouring.
2.7CONCRETEPOURING
2.7.1Priortopouring,concretepouringpermitshallbepreparedand
representativesfromTRANSCObeinformed;
2.7.2Mechanicallymixingandvibratingshallbeadoptedinconcretepouring;
2.7.3Priortopouring,thedepthofthepit,stub-angledimensions,and
specificationsandquantitiesofre-barsshallbeverified.
Groundlevelstub
HG
Concreteblock
Figure2-6ConcreteBlockPlacement
StubAngle
Figure2-7OverlookofStub-angleFixingandAdjustingFacility
2.7.4Priortoconcretepouring,Insepectionforaggregates,sand,cement
andwater,etc.shallbeapplied,specificationsandquantitiesofsaidmaterials
shallcomplywithrequirementsmentionedhereof;
2.7.5Mixtingtimeshallnotlastlessthan1-1/2minutes;
2.7.6Forpouringonelegonetime,3cylindersamplesshallbeprepared,whereas6
samplesshallbemadeforpouring2legsandaboveatonetime.TowerNo.,
legseriesandpouringdateshallbebornoneachsample;
2.7.7Concretefallingfromthemixershalltravelnomorethan2meters,otherwise
chutingfacilityshallbeused.(refertoFigure2-8)
Figure2-8ChutingFacility
2.8CURINGANDBACKFILLING
2.8.13hoursafterthecompletionofpouring,curingmeasuresshallbe
appliedbywatering,andwateringcanbeexceptedinrainydays;
2.8.214daysafterthecompletionofconcretepouring,thepitshallbe
backfilled,backfillingpermitbesubmittedbeforehandandTRNASCO
representativesbeinformed
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 线路 施工工艺
![提示](https://static.bdocx.com/images/bang_tan.gif)