悬挑式脚手架方案终稿
目 录
一、编制依据···············································································3
二、工程概况················································································3
三、脚手架搭设方案选择···························································4
(二)构造要求··············································································5
1、纵向水平杆、横向水平杆、脚手板········································5
2、立杆··························································································6
3、连墙件·······················································································7
4、剪刀撑与横向斜撑····································································7
5、架体内外封闭············································································8
6、阳台锚固段的处理······································································8
7、转角处理····················································································9
四、脚手架施工要求····································································9
1、施工准备····················································································9
2、搭设要求····················································································9
3、拆除要求··················································································11
五、脚手架的检查和验收···························································12
1、构配件检查与验收···································································12
2、脚手架检查与验收···································································13
六、脚手架安全管理措施····························································14
七、应急措施···················································································15
1、应急人员组织···········································································16
2、应急措施····················································································16
八、文明施工···················································································16
九、悬挑式脚手架设计·······························································22
(一)计算书··················································································22
1、普通型钢悬挑脚手架计算书·······················································22
2、普通型钢悬挑脚手架连梁计算书················································39
3、悬挑脚手架阳角型钢计算书························································57
十、附图
1、脚手架平面布置图
2、脚手架立面图
3、脚手架剖面图
4、节点详图(连墙件、吊环、底座等)
脚手架工程专项施工方案
一、编制依据
1、《扣件式钢管脚手架安全技术规范》JGJ130-2011
2、《混凝土结构工程施工质量验收规范》GB5024-2011
3、设计施工图纸、会审纪要
4、《建设施工高处作业安全技术规程》JGJ80-91
5、《建筑施工安全检查标准》JGJ59-11
6、《施工手册》
7、《混凝土结构技术规程》JGJ3-2002
8《建筑工程施质量验收统一标准》GB50204-2001
9、《建筑结构荷载规范》GB50009-2001
9、《钢结构设计规范》GB50017-2003
10、本工程总体施工组织设计
11、本公司企业标准
二、工程概况
工程名称:
杭政储出[2013]1号地块
建设单位:
杭州世融汇盈置业有限公司
设计单位:
上海市建工设计研究院有限公司
监理单位:
浙江明康工程咨询有限公司
施工单位:
浙江银力建设集团有限公司
安全生产、文明施工目标:
争创省标化工地
本工程由3#楼、4#楼、及地下室组成,总建筑面积27992.49m2,其中3#楼9397.4平方米,4#楼11715.85平方米,一期地下室6879平方米。
3#楼为27层,层高2.9m,单体高度80m,首层为架空层,架空高度3.15m,为住宅。
4#楼为28层,层高2.8m,单体高度80m,一层二层为配套用房,为住宅楼。
三、脚手架搭设方案的选择
根据本工程的特点,决定采用落地架与悬挑式脚手架相结合,脚手架布置见平面布置图(见附图1)。
悬挑式脚手架最高搭设高度18米。
1、搭设方式与主要参数
(1)地下室及1-4层采用单立杆落地式脚手架搭设,1-4层在顶板上搭设;
(2)悬挑架采用16号槽钢作为水平挑梁。
槽钢悬挑长度1.20m。
水平间距1.5m,采用10步一挑,每挑脚手架搭设高度18m。
悬挑架从6、12、18、24层楼面开始悬挑,共悬挑4次。
底部脚手架为落地脚手架。
(3)水平挑梁设一道19号(型号、直径)斜拉绳,拉环采用ф18圆钢,位置、具体做法见附图。
(4)脚手架用ф48×3.0钢管和扣件搭设成双排架,其立杆横距为0.8m,纵距为1.5m,步距为1.8m。
(5)脚手架立杆下部支承在槽钢(工字钢)上,上部焊接L=100Φ25钢筋,便于钢管插入,然后在组成的钢架上与普通外架一样搭设上部架体。
(6)连墙件采用每层设置,两步三跨,转角1米位置设一拉结点及首步架位置拉结点加密。
立杆离墙为0.20m。
脚手架外立杆里侧挂密目安全网封闭施工,层层满铺80×1000脚手片。
立杆底部200mm处设扫地杆。
水平钢梁与楼板压点采用Φ18圆钢拉环,拉环一定要压在楼板下层钢筋下面,并要保证两侧30cm以上搭接长度。
楼层转角位置采用45度18号槽钢或16号工字钢外挑加强(计算按16号槽钢计算)。
(二)构造要求
1、纵向水平杆(大横杆)、横向水平杆(小横杆)、脚手板
1.1纵向水平杆(大横杆)置于小横杆之上,在立柱的内侧,用直角扣件与立柱扣紧,其长度大于3跨,不小于6m,同一步大横杆四周要交圈。
1.2纵向水平杆(大横杆)接长宜采用对接扣件连接,也可采用搭接。
纵向水平杆(大横杆)采用对接扣件连接,其接头应交错布置。
两根相邻纵向水平杆的接头不宜设置在同步或同跨内。
不同步不同跨两个相邻接头在水平方向错开的距离不应小于500mm,各接头中心至最近主节点的距离不宜大于500mm。
1.3纵向水平杆(大横杆)搭接长度不应小于1m,应等间距设置3个旋转扣件固定,端部扣件盖板边缘至搭接纵向水平杆杆端的距离不应小于100mm.
1.4小横杆伸出外排大横杆边缘距离不小于10cm,伸出里排大横杆距结构外边缘20cm,且长度不大于40cm。
上、下层小横杆应在立杆处错开布置,同层的相临小横杆在立柱处相向布置。
1.5横向水平杆主节点处必须设置一根横向水平杆,用直角扣件扣接且严禁拆除。
主节点处两个直角扣件的中心距不应大于150mm。
靠墙一端的外伸长度不应大于300mm。
作业层上非主节点的横向水平杆根据支撑脚手架的需要等间距设置。
端部扣件盖板边缘至横向水平杆杆端的距离不应小于100MM;在同一根立杆上设置的上下两步横向水平杆宜左右交错设置.
1.6脚手板:
也称为脚手片,脚手片必须垂直于墙体铺设,25M以下建筑物的外脚手架除操作层以及操作层的上下层.底层.顶层必须满铺外,还应在中间至少满铺一层,25米以上建筑物的外脚手架应层层铺设脚手片.装饰阶段必须层层满铺脚手片.脚手片须用不细于18号铅丝双股并联绑扎少于4点,要求绑扎牢固,交接处平整.无探头板,不能满铺处必须采取有效防护措施.
2、立杆
2.1脚手架立杆下部支承在槽钢上,上部焊接L=100Φ25钢筋,便于钢管插入。
2.2立杆顶端高出女儿墙上皮1m,高出结构檐口上皮1.5m。
2.3脚手架必须设置纵、横向扫地杆。
纵向扫地杆应采用直角扣件固定在距底座上皮不大于200mm处的立杆上。
横向扫地杆亦应采用直角扣件固定在紧靠纵向扫地杆下方的立杆上。
2.4立杆接长除顶层顶步外,其余各层各步接头必须采用对接扣件连接。
(强制性条文)接头交错布置,两个相邻立柱接头避免出现在同步同跨内,并在高度方向错开的距离不小于50cm,各接头中心距主节点的距离不大于60cm。
2.5立杆必须采用连墙件与建筑物可靠连接。
3、连墙件
3.1连墙件的布置宜靠近主节点设置,偏离主节点的距离不应大于300mm。
当大于300mm时必须增加斜拉杆。
(见详图)
3.2连墙件应从底层第一步纵向水平杆处开始设置,当该处设置有困难时,应采用其他可靠措施固定。
3.3连墙件布置应优先采用菱形布置,也可采用方形布置、矩形布置。
拉结点在转角和顶部部位加密。
水平方向间距不大于6m,垂直方向间距每施工层布置。
3.4必须采用刚性连墙件与建筑物可靠连接。
3.5连墙件中的连墙杆或拉筋宜呈水平布置,当不能水平布置时,与脚手架的一端应下斜连接,不能采用上斜连接。
3.6连墙件伸出扣件距离应大于10cm。
底部第一根大横杆就开始布置连墙杆。
3.7架高超过40且有风涡流作用时,应采用抗上升翻流作用的连墙措施。
4、剪刀撑和横向斜撑
4.1脚手架应设剪刀撑与横向斜撑。
4.2剪刀撑的设置应符合下列规定:
4.2.1每道剪刀撑跨越立杆的根数宜下表的规定确定。
每道剪刀撑宽度不应小于4跨,且不应小于6m,斜杆与地面的倾角宜在45°~60°之间(图6.6.2)。
表一剪刀撑跨越立杆的最多根数
剪刀撑斜杆与地面的倾角a
45°
50°
60°
剪刀撑跨越立杆的最多根数n
7
6
5
4.2.2高度在24m以上的双排脚手架应在外侧立面整个长度和高度上连续设置剪刀撑;
4.2.3剪刀撑斜杆的接长宜采用搭接,搭接长度不得小于1米,应采用3个扣件固定;
4.2.4剪刀撑斜杆应用旋转扣件固定在与之相交的横向水平杆的伸出端或立杆上,旋转扣件中心线至主节点的距离不宜大于150mm。
5、架体内外封闭
5.1脚手架外侧在立杆内侧必须挂设经建设主管部门认证的合格的密目式安全网.应用不少于18号铅丝张挂严密.
5.2脚手架的架体里立杆距墙净距超过20CM时必须铺设站人片,站人片设置平整牢固.
5.3脚手架施工层里立杆与建筑物之间应进行封闭,施工层以下每隔3步以及底部应用密目网或其它措施进行封闭。
5.4脚手架外侧自第二步起必须设置1.2m高同材质的防护栏杆。
顶排防护栏杆不得少于2道,高度分别为0.9m和1.3m。
脚手架内侧当遇大开间、门窗洞等形成临边时,在脚手架内侧设1.2m防护栏杆。
6、阳台锚固段处理
水平悬挑梁如搁置在外挑阳台板上,锚固长度必须加长伸入到室内结构,第一道锚固点必须锚固在结构梁上,锚固长度≥35d。
(详见附图)
7、转角处理
悬挑架转交处需加设45°斜挑梁,具体做法见详图。
五、脚手架施工要求
1、施工准备
1.1项目部技术负责人应按照专项施工组织设计向架设和使用人员进行技术交底。
交底内容要有针对性,交底双方履行签字手续.
1.2按照规范规定和施工组织设计要求对钢管、扣件、脚手片进行检查验收,不合格产品不得使用。
1.3经检查验收合格的构配件应按照品种、规格分类,堆放整齐、平稳,堆放场地不得有积水。
2、搭设要求
2.1脚手架必须配合施工进度搭设,一次搭设高度不应超过相邻连墙件以上二步。
2.2每搭完一步脚手架后,应按照规范规定校正步距、纵距、横距及立杆的垂直度。
2.3立杆搭设应符合下列规定:
2.3.1严禁将外径48mm与51mm的钢管混合使用;(强制性条文)
2.3.2相邻立杆的对接扣件不得在同一高度内,错开距离应符合规范的规定;
2.3.3开始搭设立杆时,应每隔6跨设置一根抛撑,直至连墙件安装稳定后,方可根据情况拆除;
2.3.4当搭至有连墙件的构造点时,在搭设完该处的立杆、纵向水平杆、横向水平杆后,应立即设置连墙件;
2.3.5顶层立杆搭接长度与立杆顶端伸出建筑物的高度应符合规范的规定。
2.4纵向水平杆搭设应符合下列规定:
2.4.1纵向水平杆的搭设应符合本规定第6.2.1条的构造规定;
2.4.2在封闭型脚手架的同一步中,纵向水平杆应四周交圈,用直角扣件与内外角部立杆固定。
2.5横向水平杆搭设应符合下列规定:
2.5.1搭设横向水平杆的应符合本规定第6.2.2条的构造规定;
2.5.2双排脚手架横向水平杆的靠墙一端至墙装饰面的距离不宜大于100mm。
2.6连墙件、剪刀撑、横向斜撑等的搭设应符合下列规定:
2.6.1当脚手架施工操作层高出连墙件二步时,应采取临时稳定措施,直到上一层连墙件搭设完后方可根据情况拆除;
2.6.2剪刀撑、横向斜撑搭设应随立杆、纵向和横向水平杆等同步搭设。
2.7扣件安装应符合下列规定:
2.7.1开口朝向:
用于连接大横杆的对接扣件,开口应朝架子内侧;螺栓向上,避免开口朝上,以防雨水进入
2.7.2扣件规格必须与钢管外径(φ48或φ51)相同;
2.7.3螺栓拧紧扭力矩不应小于40N·m,且不应大于60N·m;
2.7.4在主节点处固定横向水平杆、纵向水平杆、剪刀撑、横向斜撑等用的直角扣件、旋转扣件的中心点的相互距离不应大于150mm;
2.7.5各杆件端头伸出扣件盖板边缘的长度不应小于100mm。
2.8作业层、斜道的栏杆和挡脚板的搭设就符合下列规定:
2.8.1栏杆和挡脚板均应搭设在外立杆的内侧;
2.8.2上栏杆上皮高度应为1.2m;
2.9脚手板的铺设应符合下列规定:
2.9.1脚手板应铺满、铺稳,离开墙面120~150mm;
2.9.2采用对接或搭接时均应符合本规范第6.2.3条的规定;脚手板探头应用直径3.2mm的镀锌钢丝固定在支承杆件上;
2.9.3在拐角、斜道平台口处的脚手板,应与横向水平杆可靠连接,防止滑动;
3、拆除要求
3.1拆除准备工作
3.1.1划出工作区标志,禁止行人进入;
3.1.2全面检查脚手架的扣件连接、连墙件、支撑体系等是否符合构造要求;
3.1.3根据检查结果补充完善施工组织设计中的拆除顺序和措施,经主管部门批准后方可实施;
3.1.4由项目技术负责人进行安全拆除技术交底,并履行签字手续;
3.1.5清除脚手架上的杂物及地面障碍物。
3.2严格遵守拆除顺序,由上而下,后支的先拆,先支的后拆,一般是先拆栏杆、脚手板、剪力撑,而后拆小横杆、大横杆、立杆等;
3.3统一指挥,上下呼应,动作协调,当解开与另一人有关的结扣时应先告知对方,以防坠落;
3.4材料工具要用滑轮绳索运送,不得乱扔。
拆除中,应派专人看管,不得随意乱从高空往下抛材料。
各类构配件严禁抛掷至地面。
3.5拆除作业必须由上而下逐层进行,严禁上下同时进行;(强制性条文)
3.6连墙件必须随脚手架逐层拆除,严禁先将连墙件整层或数层拆除后再拆脚手架;分段拆除高差不应大于2步,如高差大于2步,应增设连墙件加固.(强制性条文)
3.7当脚手架拆至下部最后一根长立杆的高度(约6.5米)时,应先在适当位置搭设临时抛撑加固后,再拆除连墙件;
3.8当脚手架采取分段、分立面拆除时,对不拆除的脚手架两端应采取加固措施.
六、脚手架的检查与验收要求
1、构配件的检查和验收
1.1新钢管的检查应符合下列规定:
1.1.1应有产品质量合格证;
1.1.2应有质量检验报告,钢管材质检验方法应符合现行国家标准《金属拉伸试验方法》(GB/T228)的有关规定,质量应符合本规范规定;
1.1.3钢管表面应平直光滑,不应有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道;
1.1.4钢管外径、壁厚、端面等的偏差,应分别符合本规范表8.1.5的规定;
1.1.5钢管必须涂有防锈漆。
1.2旧钢管的检查应符合下列规定:
1.2.1表面锈蚀深度应符合本规范表8.1.5序号3的规定。
锈蚀检查应每年一次。
检查时,应在锈蚀严重的钢管中抽取三根,在每根锈蚀严重的部位横向截断取样检查,当锈蚀深度超过规定值时不得使用;
1.2.2钢管弯曲变形应符合本规范的规定。
1.3扣件的验收应符合下列规定:
1.3.1新扣件应有生产许可证、法定检测单位的测试报告和产品质量合格证。
当对扣件质量有怀疑时,应按现行国家标准《钢管脚手架扣件》(GB15831)的规定抽样检测;
1.3.2旧扣件使用前应进行质量检查,有裂缝、变形的严禁使用,出现滑丝的螺栓必须更换;
1.3.3新、旧扣件均应进行防锈处理。
2、脚手架检查与验收
2.1脚手架及其地基基础应在下列阶段进行检查与验收:
2.1.1基础完工后及脚手架搭设前;
2.1.2作业层上施加荷载前;
2.1.3每搭设3步进行验收;
2.1.4达到设计高度后;
2.1.5遇有六级大风与大雨后;寒冷地区开冻后;
2.1.6停用超过一个月。
2.2脚手架使用中,应定期检查下列项目:
2.2.1杆件的设置和连接,连墙件、支撑、门洞桁架等的构造是否符合要求;
2.2.2扣件螺栓是否松动;
2.2.3安全防护措施是否符合要求;
2.2.4是否超载。
2.3安装后的操作螺栓拧紧扭力矩应采用扭力扳手检查,抽样方法应按随机分布原则进行。
抽样检查数目与质量判定标准,应按本规范的规定确定。
不合格的必须重新拧紧,直至合格为止。
七、脚手架安全管理措施
1、脚手架搭设人员必须是经过考核合格的专业架子工。
上岗人员应定期体检,合格者方可持证上岗。
(强制性条文)
2、搭设人员必须戴安全帽、系安全带、穿防滑鞋。
3、脚手架的构配件质量与搭设质量应按规定和施工方案要求进行检查验收,合格后方可使用。
4、作业层的施工荷载应符合设计要求,不得超载。
本工程设计荷载为3KN/m2。
不得将模板支架、缆风绳、泵送砼和砂浆的输送管等固定在脚手架上;严禁悬挂起重设备。
5、当有六级以上大风和雾、雨、雪天气时应停止脚手架搭设与拆除作业。
雨雪后上架作业应有防滑措施,并扫除积雪。
6、脚手架使用中应加强日常维护和安全检查。
安全网应按照规定搭设和拆除。
7、脚手架使用期间,严禁拆除下列杆件:
(强制性条文)
7.1主节点处的纵、横向水平杆,纵、横向扫地杆;
7.2连墙件
7.3不得在脚手架基础及其临近2米处进行挖掘作业,否则应采取加固措施.
7.4临街搭设脚手架时,外侧应有防止坠物伤人的防护措施。
7.5在脚手架上进行电、气焊作业时,必须有防火措施和专人看守。
7.6各种电线不得直接在钢管架上缠绕,电线和电动机具必须与脚手架接触时,应当有可靠的绝缘措施,并要通过安全员的检查方可使用。
7.7防火措施:
应设置足够数量的灭火器。
每层各安放2个干粉灭火器。
电焊操作时,必须有专人看守,防止火星点燃易燃物品。
不准任何人在脚手架上吸烟,或从吸烟室内向脚手架上扔烟头。
7.8防雷措施:
脚手架顶部按规定要求做好防雷接地工作。
7.9搭拆脚手架时,地面应设围栏和警戒标志,并派专人看守,严禁非操作人员入内。
八、应急措施
1、应急人员组织
组长:
张小成(项目经理)
副组长:
曹立海、朱云伟、
组员:
汪文涛、沈方土、边平来、潘奇峰
2、应急措施
2.1如架体倾斜或变形过大,采用活动葫芦校正后增加连墙件;
2.2架体密目网着火,立即组织人员用就近配置的灭火器和浇水灭火,切断相关电源,并拨打119通知消防部门;
2.3如发生架体倒塌,立即采取急救措施,保护好现场,通知相关部门。
九、文明施工
1、进入现场一切材料必须按照现场管理平面图指定位置一次性放置到位,各类材料分类码放,按贯标要求挂牌,控制高度符合要求,保持现场材料整齐统一。
2、所有钢管、扣件等涂刷防锈漆二度,桔红色面漆,底层脚手架钢管均漆成黑、黄颜色。
项目部对操作人员进行文明施工交底,明确责任。
必须做到施工层每天落手清。
3、安全密目网按照规定悬挂整齐,不得使用破损和污染严重的网片。
并在每施工楼层混凝土浇捣完成后进行清洗,保证架体外观整洁。
4、每楼层混凝土施工完成后对脚手架底部进行清理,确保架体底部清洁。
5、定期定人对排水沟进行清理,保证排水畅通,不积水。
4、节点详图(连墙件)
连墙件详图一
连墙件立面布置图
四、悬挑式脚手架设计
型钢悬挑脚手架(扣件式)计算书
计算依据:
1、《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011
2、《建筑施工门式钢管脚手架安全技术规范》JGJ128-2010
3、《建筑结构荷载规范》GB50009-2012
4、《钢结构设计规范》GB50017-2003
架体验算
一、脚手架参数
脚手架搭设方式
双排