锚杆挡墙施工方案
第一章工程概况·········································································3
一、工程概况·············································································3
二、施工平面布置·········································································4
三、施工要求·············································································4
四、技术保证条件·········································································5
五、施工现场重难点及应对措施·····························································5
第二章编制依据·········································································10
一、相关法律、法规及规范性文件··························································10
二、标准、规范··········································································10
四、结合本工程相关资料·····························································12
第三章施工计划········································································12
一、施工分析·······································································12
三、施工进度计划········································································13
四、材料与设备计划······································································13
第四章施工工艺技术····································································14
一、技术参数············································································14
二、工艺流程············································································15
三、施工方法············································································15
四、检查验收············································································26
五、扬尘治理·········································································28
六、排水措施·········································································29
第五章施工安全保证措施·································································29
一、组织保障···········································································30
二、技术措施············································································40
三、应急预案············································································40
四、监测监控············································································44
五、危险源识别及应急预案·································································48
六、文明施工环境保护措施·······························································49
第六章劳动力计划······································································53
一、专职安全生产管理人员································································54
二、特种作业人员及需求计划······························································54
第七章计算式及相关图纸······························································55
一、脚手架计算式······································································55
二、相关图纸········································································65
第一章工程概况
一、工程概况
工程地址位于重庆市沙坪坝区天星桥正街,施工区域呈长方形平行于天星桥正街,东面紧邻天星桥中学学生宿舍,西面为天骄教学楼,南面紧邻天宇教学楼,北面为西南医院家属区,施工道路相邻天宇教学楼右侧,与城市道路相连,受早、晚高峰影响及货车限行规定,施工车辆进出时间需做相应调整,满足施工进度要求。
1.工程名称
沙坪坝区天星桥中学整体改扩建项目
2.工程特点
本工程的边坡按板肋式锚杆挡墙支护,1:
0.15坡率放坡。
边坡支护划分3个施工段,即A1~A3、A3~A4、A4~A5,先行施工A4~A5段,长度30.0米,板高7.4米~10.5米;A3~A长度32.0米,板高10.5米~8.3米;A1~A3长度22.5米,板高10.6米;3.0米高做一施工段,分层自上而下逆作法施工,与土石方开挖相互交叉作业。
3.边坡概况
拟建教学楼西北侧与邻近三军医大家属院之间由于平场开挖,现已形成高8~11米左右的挖方边坡根据现场调查,结合前期钻孔ZK50,该边坡为岩土质混合边坡,土层厚度1~3米左右,不属于高切坡。
4.边坡工程地质及水文条件
本场地区域地貌形态为浅丘地貌,地形总体西南侧稍高,整体地势由西南向北东侧呈三级平台台阶状展布,第一级平台为现有西南侧各栋教学楼以及教学楼间的平台组成的一级平台,二级平台为现有学校足球场,三级平台为沿足球场北东侧的现有食堂部分地带,由于拟建场地为天星桥中学校园内,各级平台之间形成的陡坎均采用挡墙进行了支挡,目前整体稳定,未见明显变形开裂迹象,地面坡度3~8°,一般为5°。
拟建场地及周边地形最高标高为西南侧288.32m,勘察区北东侧最低标高271.40m,相对约16.92m,地形条件简单。
据调查,场区无化学污染源,且场内多数地段土层较薄,土层为未污染土,根据规范和当地经验判定环境水和土层对混凝土结构、对钢筋混凝土结构中钢筋仅具微腐蚀性。
根据区域地质资料、周边访问调查及本次勘察结果可知,在勘察区域内及周边无滑坡、危岩及崩塌体、泥石流、断层及破碎带等不良地质现象。
二、施工平面布置
根据本工程实际情况,对施工便道、水电、材料堆码场、钢筋加工场等进行合理的设置(详见附图)。
1、施工便道修筑路基宽度8m,(局部松软土层路基,片石换填),至施工点
2、水电按业主指定接口长约250m接入施工现场,电从业主配电室引出,施工现场设置2个二级配电箱,主线路沿施工外围铺设至各施工点。
其配备功率要满足所有用电量的功能,施工机械设置配电箱,做到一机一箱一闸一漏。
3、材料堆码场根据实际施工需要设置,材料堆场用C20,厚0.1m混凝土硬化。
4、钢筋加工房钢管搭设,按重庆市工程建设标准设计DJBT-046要求,及《重庆市房屋建筑和市政设施工程安全文明施工标准图集》
(二)12J02规定执行,两层间挂安全警示牌。
三、施工要求
1.加强施工过程中的质量与安全控制,确保施工质量及安全。
2.安装及机械操作人员需取得特殊作业人员资格上岗证。
3.施工前对施工人员进行安全技术交底,严禁盲目施工。
4.在确保施工质量及安全的前提下,制定赶工措施,确保工程进度满足业主要求。
5.施工过程中,交叉作业的现象时分突出,需加强与土石方开挖等相关协调工作,确保工程进度。
6.施工工程需严格执行本《专项施工方案》。
四、技术保证条件
1.严格执行现行国家标准、地方标准、规范及相关文件要求;严格按照施工设计图、边坡防护施工专项方案进行施工。
2.施工前严格履行交底程序,对施工人员及所有作业人员进行详细的技术和安全交底,做到各层交底到位并落实到具体人员上,明确各自岗位职责。
3.在施工过程中,按照质量监督程序进行随时跟踪和监控,保证施工安全和工程质量。
五、施工现场重难点及应对措施
1.如何确保高边坡开挖施工的安全?
应对措施:
为确保高边坡安全,同时为了确保工期,采取分层、分段自上而下逆作法施工。
在土石方开挖完成高度3m,分段长度原则上不超过30m,立即进行该段边坡支护施工,施工完毕后及时拆除该段边坡脚手架。
人力将架管、钢材、机具等材料转运至固定材料堆码场。
再进行下一层段土石方开挖、边坡支护施工,依次循环推进。
即便是纵向分段施工,亦不可避免相互干扰。
整个施工作业会产生大量二次转运物质(脚手架、模板、钢材、水泥、机具设备等)工程量。
需现场核量核价。
2.板肋式锚杆挡墙单面模板的加固直接影响坡面支护结构的完成质量及施工过程的安全,如何加固处理?
应对措施:
为了确保坡面完成质量及施工安全,采用锚杆对单面模板进行加固。
加固锚杆参数:
锚孔50mm,孔深1500mm,内设单根Ф14钢筋,并灌注M30水泥砂浆,锚固长度1500mm,按梅花形布置间距@800mm*800mm,外侧预留长度200mm,并与A14模板拉杆进行焊接。
(详见示意图如下)
3.板肋式锚杆挡墙施工脚手架如何分两次搭设?
如何确保脚手架的稳定?
应对措施:
为了确保工程进度及安全,采用脚手架分两次搭设施工。
第一次搭设施工:
开挖结构体土石方、修整坡面、锚杆(索)钻孔安装注浆、肋柱泄水孔嵌槽(坑)开挖、拆除脚手架;清理开挖的弃渣、第二次脚手架搭设、钢筋安装、模板安装、泄水孔制安、浇捣砼及养护、打磨坡面砼、拆除脚手架。
依据钻机自重和施工荷载以及钻机在钻进过程中的额定给进力的合力,锚杆(索)在脚手上钻孔作业施工,以确保脚手架架体稳定和安全,拟采用搭设三排脚手架,在坡面设置加固锚杆作为连墙件。
加固锚杆参数:
锚孔75mm,内设单根22钢筋,并灌注M30水泥砂浆,锚固长度2000mm,设置距离按3000mm*3000mm呈梅花形布置,外侧预留钢筋长度3500mm,另加工成200mm弯钩,钩住架体每根立杆并焊接成弯钩撑住架体内立杆。
连墙件从第一步开始设置,当搭设至有连墙件的构造点时,在搭设完该处的立杆、纵向水平杆、横向水平杆后,立即连接连墙件。
(详见脚手架剖面图和连接件大样图)
4.土石方施工按平场图开挖面至板肋式锚杆挡墙结构体外表面,此挡墙坡面结构体土石方如何开挖?
坡面如遇特殊地质情况形成凹面如何保证混凝土浇筑厚度及质量?
应对措施:
土石方施工按平场图开挖面至板肋式锚杆挡墙构外表面,此挡墙坡面结构体土石方拟采用人工小型风镐凿打开挖;清坡时尽量减少坡面凹凸不平处,坡面如遇特殊地质情况形成凹面,拟采用M5.0水泥砂浆砌MU30片石嵌补找平,以业主、监理现场实际收方为准。
其为保证混凝土浇筑厚度及质量。
5.本工程边坡支护挡墙混凝土如何浇筑?
本工程按分层、分段,自上而下逆作法施工,单次混凝土浇筑量较少时的协调处理?
应对措施:
在浇筑挡墙混凝土时,采用47米的臂架泵配合浇筑完成;单次分层分段边坡支护工程量较小时,将存在单次浇筑混凝土数量过小的情况,臂架泵费用增大,为了确保工程的顺利推进,采取对商品混凝土单位进行补助的方式进行处理,结算按商品混凝土浇筑时实际发生情况计算工程量,补助单价以商品混凝土单位收费标准为依据。
6.为了各施工区域正常顺利推进及确保整个工程进度,现场水电布置如何处理?
应对措施:
根据本工程现场实际情况,从业主单位配电室引出,施工现场设置2个二级配电箱;用水采用设置直径50mm主管道并预留相应接口。
水电主线路沿施工外围铺设至施工区域。
7.截排水沟基槽遇较硬石方开挖,如何处理?
应对措施:
放好基槽开挖线,如遇较硬基岩沿基槽开挖线两边采用Ф100水钻钻孔取芯,再用人工风镐剔打成型。
详见示意图如下:
8.挡墙泄水孔为2500*2500呈梅花布置,坡体嵌岩500*500*500,用PVC100外斜5%堆积砂卵层施工,施工难点:
(1)、泄水孔基坑开挖施工在脚手架平台上系水平施工作业,施工难度大且工效缓慢,如何处理?
(2)、砂卵石反滤包堆码填充成型和反滤包极易垮塌,如何处理?
(3)、浇捣挡墙砼时避免水泥浆渗透入泄水孔砂卵反滤包,如何处理?
对应措施:
(1)、泄水孔基础坡体嵌岩四周用Ф100水钻钻孔取芯,再用人工风镐剔打成型。
施工难度大,功效极度缓慢,一个泄水孔基坑开挖需1个技工、1.5个工日完成。
每个泄水孔人工剔打嵌岩基坑需核价。
详见示意图如下:
(2)、在泄水孔基础坡体上方人工剔打200*300喇叭口形状,基坑四周内铺设双层土工布,砂卵反滤包用胶桶装好,人工在脚手架平台上逐级传递至施工部位倒入喇叭口;为了稳固反滤包的砂卵石在泄水孔基础内不泄漏,在基础坑坡面四角20㎝处钻孔,孔径50㎜,深度0.5m孔内预埋Ф12钢筋并外露出坡面5㎝灌注M30水泥砂浆,再用15*2*2规格的镀锌网片和预埋钢筋有效连接,阻挡反滤包的砂卵石泄漏。
(3)、浇捣挡墙砼时在泄水孔反滤包的立面用1000*1000的塑料布封闭,以防止水泥浆渗透入泄水孔砂卵反滤包内,以确保滤水质量。
9.锚杆基本实验如何处理?
应对措施:
按规范要求,基本试验在相同的地质条件下做,位置结合现场实际在无锚杆区域选择。
种类按锚杆钢筋的规格分别做三根基本性能试验。
基本性能试验锚杆孔径、孔深经业主、监理按现场实际收方为准。
以满足整个验收实验,达到验收标准。
10.施工过程中严格遵守并执行重庆市沙坪坝区和业主对环境保护的相关规定。
进出施工场地车辆如何处理?
应对措施:
在施工大门口处平整长度35m、宽9m场地,并用强度C25、长度30m、宽度8m、厚0.3m的混凝土进行硬化,其中设置长15m、宽5m、深0.8m的U型过水槽和长7m、宽2m、深2.5m的沉砂池。
施工车辆进入市政道路前,先进入过水槽,在用高压水冲洗干净,保证道路清洁。
避免将泥土带入市政道路,引起扬尘污染空气。
派专人进行清理并冲水清洗。
11.锚杆施工中如遇土层或软弱层塌踏孔严重,无法正常成孔;保证孔内注浆时不漏浆,砂浆饱和,锚杆体与砂浆有效锚固粘接,如何处理?
应对措施:
经业主现场确定后,采用钢套管跟进钻孔并一次性预埋成孔施工工艺。
具体参数:
材质:
地质无缝管材,壁厚30mm;;直径:
套管内径满足设计孔径;加工成每节长度1.2米,两端一公一母丝扣;套管连接头(200*8);钢套管前端安装一次性满足设计孔径钻头,并嵌入岩层不小于1m。
需现场核量。
12.天星桥中学有强、弱电和排污管沿坡顶布设,施工中如何处理?
应对措施:
经现场查看,该强、弱电和排污管已投入使用,施工中需采取措施加以保护,保护费用现场签证确认。
13.坡顶西南医院家属区已建围墙,施工中如何处理?
应对措施:
经现场查看,围墙基础搁置与土层上,受连续雨天影响,部分围墙基础出现渗水,并有局部坍塌,需拆除,挡墙完工后复建。
第二章编制依据
一、相关法律、法规及规范性文件
1.中华人民共和国《建筑法》
2.中华人民共和国《安全生产法》
3.中华人民共和国《建设工程安全生产管理条例》
4.住建部建质(2009)87号文件《危险性较大的分部分项工程安全管理办法》
5.关于印发《建筑工程预防高处坠落事故若干规定》和《建筑工程预防坍塌事故若干规定》的通知(建质【2003】82号)
二、标准、规范
《建筑工程项目管理规范》(GB/T50326-2014)
《建筑工程施工质量验收统一标准》(GB50300-2013)
《工程测量规范》(GB50026-2012)
《建筑地基基础工程施工质量验收规范》(GB50202-2002)
《市政工程边坡及挡护结构施工质量验收规范》(DBJ50-126-2011)
《建筑边坡工程技术规范》(GB50330-2013)
《建筑基坑支护技术规程》(JGJ120-2012)
《建筑与市政降水工程技术规范》(JGJ/T111-1998)
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011)
《建筑施工扣件式钢管模板支架技术规程》(DB33/1035-2006)
《钢管脚手架扣件》(GB/5831-2006)
《机械设备安装工程施工及验收规范》(GB50231-2009)
《施工现场临时用电安全技术规程》(JGJ46-2012)
《建筑机械使用安全技术规程》(JGJ33-2012)
《建筑工程施工现场用电安全规范》(JGJ46-2005)
《建筑工程雨期施工规程》(JGJ104-2011)
《建筑施工安全检查评分标准》(JGJ59-2011)
《建筑施工高处作业安全技术规范》(JGJ80-2011)
《高处作业分级》(GB/T3608-2008)
《企业职工伤害事故分类标准》(GB6441-1986)
《生产过程危险和有害因素分类与代码》(GB/T13861-2009)
《建设工程施工现场消防安全技术规范》(GB50720-2011)
《建筑施工土石方工程安全技术规范》(JGJ180-2009)
《施工现场机械设备检查技术规程》(JGJ160-2008)
《建筑施工作业劳动防护用品配备及使用标准》(JGJ184-2009)
《生产经营单位安全生产事故应急预案编制导则》(GB/T29639-2013)
《质量管理体系要求》(GB/T19001-2008idtISO9001:
2008)
《环境管理体系规范及使用指南》(GB/T24001-2004idtISO14001:
2004)
《职业健康安全管理体系规范》(GB/T28001-2011)
三、地方标准及要求
《关于印发进一步规范重庆市高切坡、深开挖、高填方项目管理的若干规定的通知》(渝建发【2002】47号)
《关于认真贯彻落实进一步规范重庆市高切坡、深开挖、高填方项目管理的若干规定的通知》(渝建发【2002】76号)
《关于进一步加强基础安全施工的规定》(渝建安发【2003】21号)
《关于开展建筑工地安全文明施工标准化评价工作的意见》(渝建发〔2008〕46号)
《重庆市房屋建筑和市政基础设施工程现场文明施工标准》(渝建发【2008】169号)
《重庆市建筑工地文明施工标准》的通知(渝建发【2009】39号)
《关于进一步加强全市高切坡、深基坑、高填方项目勘察设计管理的意见》(渝建发【2010】166号)
《关于印发危险性较大的分部分项工程安全管理实施细则的通知》(渝建发【2014】16号)
四、结合本工程相关资料
1、建设单位提供的工程施工图纸(见附图)、地勘
2、工程施工图纸会审纪要。
3、有关现场文明施工管理细则。
4、施工组织设计文件
第三章施工计划
一、施工准备
1、建立项目经理部,具体布置如下图:
2、完成施工图纸的学习与会审、施工技术方案的审批,施工技术交底;完成施工便道的修筑、施工用水电的架设引入、材料堆码场及钢筋加工房;根据设计要求,对各种原材料选定合格厂家并进行相关试验,以确保工程进度和质量。
二、施工分析
1、边坡工程量较大,且按逆作法与土石方开挖交叉作业施工,转换工序多,因此工期较紧,应重点考虑边坡工程施工程序,土石方工程需及时配合边坡工程各施工工序施工
2、施工程序制定:
根据施工合同、施工图和图纸会审纪要,以及各施工内容的相关性,合理制定施工程序。
本工程拟定为先上后下、由底到高的主要施工程序进行协调作业施工,先施工标高低的部分,原因该边坡下方有主体结构,标高高的部分下方无主体基础。
3、施工顺序:
边坡支护划分3个施工段,即A1~A3、A3~A4、A4~A5,先行施工A4~A5段,长度30.0米,板高7.4米~10.5米;第二流水段A3~A4长度32.0米,板高10.5米~8.3米;第三流水断A1~A3长度22.5米,板高10.6米;3.0米高做一施工段,分层自上而下逆作法施工,与土石方开挖相互交叉作业。
三、施工进度计划
工期目标:
本边坡治理为增加工程,需与土石方工程交叉施工。
结合本工程的实际情况,优化细分为三个施工阶段:
第一阶段(A4~A5段):
工期45天;第二阶段(A3~A4):
工期45天;第三阶段(A1~A3):
工期45天。
待边坡治理施工结束后,主体基础方能施工,因此边坡治理施工时间不能纳入合同工期计算,总工期需顺延。
四、材料与设备计划
钢管、扣件、水泥、砂、碎石、钢材、水管、配电箱、电缆线、钢绞线、防滑草袋、铁锨、扫帚、安全警示带等物资,其数量及进场时间根据现场施工情况配备。
主要设备计划表
序号
设备/机械名称
规格型号
数量
1
对讲机
BATT703
3对
2
全站仪
TOP-102
1台
3
水准仪
苏光DZS-3
1台
4
汽车吊
30T
1辆
5
空压机
3m3
2台
6
风动凿岩机
YT28-10
2台
7
水泵
扬程30m
3台
8
磅秤
1台
9
钻机
DZ-25
3台
11
注浆机
ZJB-3型
1台
12
搅拌机
JQ250型
1台
13
钢筋弯曲机
GW40-B
1台
14
调直机
Y112M
1台
15
切割机
GQ40
1台
16
电焊机
BX1-315
2台
主要材料计划表
序号
名称
规格型号
数量
1
钢材
HRB400
30T
2
水泥
普通硅酸盐水
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 挡墙 施工 方案
![提示](https://static.bdocx.com/images/bang_tan.gif)