187电缆井作业指导书
第8部分:
配网工程
电缆井作业指导书
编码:
DLTJ-03
目次
1适用范围······················································································································································483
2编写依据······················································································································································483
3作业流程图···················································································································································483
4安全风险辨析与预控···································································································································484
5作业准备························································································································································13
6作业方法··························································································································································6
7质量控制措施及检验标准·······························································································································9
1适用范围
本节适用于35kV及以下配网工程电缆沟、管工程配套的电缆工井、检查井、过渡井的施工。
2编写依据
表2编写依据
序号
引用资料名称
1
GB50204—2002《混凝土结构工程施工质量验收规范》
2
GB50210—2001《建筑装饰装修工程质量验收规范》
3
GB50203—2002《砌体工程施工质量验收规范》
4
GB50202—2002《建筑地基基础工程施工质量验收规范》
5
Q/CSG11105—2008《南方电网工程施工工艺控制规范》
6
《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3作业流程图
图3作业流程图
4安全风险辨析与预控
4.1电缆井作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与电缆井作业相关联的《电网建设安全施工作业票》(编码:
DLTJ-03-01/01),
结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业
人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号
危害名称
风险种类
风险等级
风险控制措施
1
施工区域安全围蔽措施不足
摔绊扭伤坠落打击
低风险
施工区域必须做好安全围蔽及警示标志措施,晚上设置夜间警示灯,防止外人误入工作区域
2
作业人员前后间距不足
碰撞打击
低风险
确保作业人员前后间距不得小于3m
3
挖掘机械回转半径范围内站人
碰撞
中等风险
施工区域必须做好警示标识,挖掘机械工作期间禁止人员进入
4
在基坑内排水时,抽水设备漏电或电源线损坏
触电
高风险
严格执行一机一闸一漏电的电源箱,使用合格电源线,操作人员穿胶鞋
5
土方(泥浆)运输车辆撒漏
工作环境污染
低风险
工地现场必须设置洗车槽,做好有效的防撒漏、防扬尘措施,未经清洗干净的车辆不得离开工地
6
土方(泥浆)运输车辆超载、超速等违章驾驶
交通意外
特高的风险
设专人监管,确保工地装载土方(泥浆)不得超载、超速等违章驾驶
7
挖掘机操作手无证上岗
碰撞打击
低风险
挖掘机操作手必须持证上岗
8
混凝土浇筑时,平板振动器或电源线漏电
触电
高风险
严格执行一机一闸一漏电的电源箱,使用合格电源线,操作人员穿戴胶鞋、胶手套及防护眼镜
9
手推车运送混凝土、砂浆时撒把
碰撞
低风险
禁止手推车运送混凝土、砂浆时撒把
10
混凝土搅拌时,搅拌机料斗的钢丝绳断股
碰撞
打击
低风险
发现钢丝绳断股,必须更换
11
混凝土搅拌时,料斗提升后下方站人
碰撞打击
低风险
混凝土搅拌时,料斗提升后,下方不准站人
12
电缆井砌筑时,斗车运送毛石、砖块装载过满
碰撞
低风险
1.搬运砖石料的工器具要牢固;
2.搬运砖石料要量力而行,往沟槽里下料时要采用滑道,且下面不准有人
13
电缆井砌筑时,整理砖、毛石操作不当
碰撞打击
低风险
不准向有人的方向打砖、毛石
14
混凝土浇筑时,振动捧或电源线漏电
触电
高风险
严格执行一机一闸一漏电的电源箱,使用合格电源线,操作人员穿戴胶鞋、胶手套及防护眼镜
15
拆模时,将带钉模板随意乱放
刺伤
低风险
拆模时,不得乱扔乱放,做到工完料清
16
混凝土养护不足、强度不够
坍塌
低风险
混凝土养护时间应不小于7天,有添加剂时应不小于14天
17
砂浆搅拌机或电源线漏电
触电
高风险
严格执行一机一闸一漏电的电源箱,使用合格电源线,操作人员穿戴胶鞋、胶手套及防护眼镜
18
搬运铺设混凝土预制盖板操作不当
碰撞
中等风险
1.搬运预制盖板的工器具要稳固可靠,同时做好前后扶稳的配合;
2.搬运预制盖板要量力而行,不许从高处翻下;
3.作业人员要相互配合默契
19
电缆坑盖板摆放不稳
打击
低风险
保护盖板放摆放应整齐、合理、安全
20
打夯机或电源线漏电
触电
高风险
严格执行一机一闸一漏电的电源箱,使用合格电源线,操作人员穿戴胶鞋、胶手套
5作业准备
5.1作业前施工条件
表5.1作业前施工条件
序号
项目
内容
确认人
说明
1
任务单
根据本单位实际设置内容(包含本项工作)
本工序施工负责人
经审批
2
相关证照
根据需要办理涉及进入工作场所的手续、证件
本工序施工负责人
有效
3
工程合同或协议
合同及安全协议
本工序施工负责人
有效
4
图纸
设计图纸
本工序施工负责人
经审批
5
施工方案
施工措施、安全技术交底(项目部级)
本工序施工负责人
经审批
5.2人员、主要工器具及仪器仪表配置
表5.2人员、主要工器具及仪器仪表配置
序号
项目
内容
说明
1
人员配置
施工员、施工作业人员等
技术岗位必须持有与作业工种相应、有效的上岗证
2
施工内容相对应的设备材料
钢筋、水泥、砖、砂、石、石粉、HDPE管等
(1)钢筋、水泥、砖应符合设计要求,有出厂合格证及检验报告。
砂、石、石粉的质量应符合现行标准要求。
(2)水质应符合国家现行标准《混凝土拌和用水标准》的规定。
定向钻铺管使用管
材通常为HDPE管,其材质及性能应符合
国家有关现行标准及相应规定
3
施工内容相对应的器具、机械及工器具仪表
施工所需的工器具、机械、仪器等
根据现场情况使用的工器具、机械符合相关要求。
仪器、仪表使用前必须经有资质的单位检验合格且在检测有效期内才能使用
4
完成开工程序
工作负责人向项目负责人报开工,并由项目负责人完成向监理单位开工报审手续
施工准备完成后可报开工,当施工准备不足时,上报该项目负责人协调解决
6作业方法
表6作业方法
序号项目内容说明
1作业前工作
(1)现场施工负责人向进入施工范围内所有人员详细交待本次施工作业内容、进度要求、特殊项目施工要求、作业标准、安全注意事项、危险点及控制措施、危害环境的相应预防控制措施、人员分工,并签署(班组级)安全技术交底。
(2)现场施工负责人负责办理相关的工作许可手续,开工前做好现场施工防护围蔽警示措施;夜间施工的须有足够的照明。
(3)现场施工负责人组织检查所有工作人员是否正确使用劳保用品及着装,并带领施工作业人员进入作业现场
按安规规定佩戴统一的安全帽,统一佩戴有个人照片的作业证(或胸卡证),穿着统一的工作服
开始主要
2
作业
现场施工负责人发出许可开工命令
3土方开挖
开挖应严格按挖沟断面分级开挖,沟体开挖应连续进行,挖出土方应及时外运,不得随意堆放。
施工过程中严禁超挖,如发生超挖,应用石屑回填压实至设计标高。
人工修整沟体基沟,根据设计图纸要求把沟底夯实、找平
现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全、质量监控
人工平整
4
沟底
挖土完成后对基层土进行夯实处理
浇捣混凝土
5
垫层、底板
(1)垫层混凝土厚度、强度等应符合设计
要求。
(2)浇捣混凝土垫层,强度达到设计要求后,
进行钢筋绑扎,钢筋工程经检验合格后浇捣混凝
土底板混凝土,浇筑的混凝土板基础要平直,浇
灌过程中用平板振动器振捣。
(3)混凝土浇筑方法:
混凝土自由下落度应不
大于2m,且下灰不得集中于一点,尽量匀铺。
混凝土试压件送有资质的检验部门试验并出具
合格证
6砌砖
(1)砖砌筑前须复测,确定方向后进行砌筑,宜采用灰砂砖,用水泥砂浆砌筑,灰砂砖砌筑前24h要淋透水。
砌筑砂浆要充分搅拌均匀,确保砂浆质量,砖砌体要横平竖直,灰缝饱满均匀。
(2)砌筑宜采用挤浆法,或者采用“三一砌砖
法”,即:
一铲灰、一块砖、一挤揉并随手将挤
出的砂浆刮去。
操作时砌块要找平、跟线,并经
常进行自检,如发现有偏差,应随时纠正,严禁
事后采用撞砖纠正。
砌墙应随砌随将溢出砖墙面
的砂浆刮除
7
圈梁混凝土浇筑
(1)圈粱钢筋绑扎:
按图纸要求进行井口圈粱的钢筋绑扎,并预留竖向连接筋,沿井口圈梁每米内外各设一根,令圈粱与初衬连成一体,保证结构稳定。
圈梁钢筋经检验合格后方可进行下一道工序。
(2)圈梁模板安装:
1)圈梁模板要用托架稳固、模板要平直、支
撑合理、稳固、并考虑拆卸方便,压脚及支撑多
采用松木枋、板材。
2)为保证所施工的工井圈梁顺直,圈梁内侧
模板可采用槽钢做内模。
模板安装过程中,施工
员、质检员要对模板的各个部位详细检查,保证
截面尺寸及位置准确。
(3)混凝土浇筑:
圈粱混凝土浇筑时用振捣
8
拆模养护
(1)拆模:
非承重构件的混凝土强度达到
1.2MPa且其拆模时构件不缺棱掉角,方可拆除
模板;承重构件的防水混凝土拆模时间以设计、
规范要求及同条件养护试块强度为依据确定。
(2)养护:
常温浇水养护,指定专人经常洒水
养护,保持湿润状态,混凝土养护时间应符合规
范要求
9
电缆井壁抹灰
(1)抹灰工程施工的环境温度不应低于5
℃,当必须在低于5℃的气温下施工时,应有保
证工程质量的有效措施。
(2)抹灰的表面平整度应符合设计要求
10
铺设预制盖板
(1)电缆槽盒、盖板:
预制构件不得有露筋、蜂窝、麻面、裂缝、破损等现象,外露面光洁、有出厂合格证及检验报告。
(2)盖板就位时,应调整构件位置,使其缝宽均匀、板面高低平整,正反面位置正确
11
电缆井回填
在井室外四周由槽底到地面范围,宜采用砂、石粉等填料进行回填,严格控制施工工艺,确保密实度符合设计要求
7质量控制措施及检验标准
7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措
施。
7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。
质量检验一般采用三级检验制,施工队(组)对所施工的分项
工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。
7.1.7混凝土浇筑施工,应提前24小时通知监理进行现场旁站。
7.2质量控制点
表7.2电缆井工程质量控制点表单
控制点
控制方式
W
H
S
电缆线路土建工程
●
7.3检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:
配网工程》中的Q/CSG
表8-7.21要求执行。
●附件1安全施工作业票
编码:
DLTJ-03-01/01
工作时间
工作地点
技术员
现场安全员
现场负责人
安全风险分析及控制措施
序号
危害名称
风险种类
风险等级
风险控制措施
1
施工区域安全围蔽措施不足
摔绊、扭伤、坠落、打击
□低风险
现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施:
□施工区域必须做好安全围蔽及警示标志措施,晚上设置夜间警示灯,防止外人误入工作区域。
□工地现场必须设置洗车槽,未经清洗干净车辆不得离开工地。
□设专人监管,确保工地装载土方(泥浆)车辆不得超载、超速等违章驾驶。
□禁止手推车运送混凝土、砂浆时撒把。
□发现钢丝绳断股,必须更换。
□混凝土搅拌时,料斗提升后,下方不准站人。
□往沟槽里下料时要采用滑道,且下面不准有人。
□不准向有人的方向打砖、毛石。
□严格执行使用“一机一闸一漏电”的电源箱,使用合格电源线,设备外壳直接接地。
□拆模时,不得乱扔乱放,做到工完料清。
□混凝土养护时间应不小于7天,有添加剂时应不小于
14天。
□搬运预制盖板的工器具要稳固可靠,同时做好前后扶稳的配合。
□搬运预制盖板要量力而行,不许从高处翻下。
□作业人员要相互配合,盖板放摆放应整齐、合理、安全。
□做好井内白蚁的预防工作
2
挖掘机械回转半径范围内站人
碰撞
□中等风险
3
设备漏电或电源线损坏
触电
□高风险
4
土方(泥浆)运输车辆撒漏
工作环境污染
□低风险
5
土方(泥浆)运输车辆超载、超速等违章驾驶
交通意外
□特高的风险
6
手推车运送混凝土、砂浆时撒把
碰撞
□低风险
7
混凝土搅拌时,搅拌机料斗的钢丝绳断股
碰撞、打击
□低风险
8
混凝土搅拌时,料斗提升后下方站人
碰撞、打击
□低风险
9
电缆井砌筑时,斗车运送毛石、砖块装载过满
碰撞
□低风险
10
电缆井砌筑时,整理砖、毛石操作不当
碰撞、打击
□低风险
11
拆模时,将带钉模板随意乱放
刺伤
□低风险
12
混凝土养护不足、强度不够
坍塌
□低风险
13
搬运铺设混凝土预制盖板操作不当
碰撞
□中等风险
14
电缆坑盖板摆放不稳
打击
□低风险
安全补充事项/平面布置图
现场接受交底人员签名
备注
说明:
(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。
现场负责人开工前核对风险控制措施
并宣读。
(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变
更时,应在备注栏记录变更情况。
对新增人员进行交底,并签名确认。
(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。
(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。
(五)基准风险等级与风险控制措施在开工前现场打“√”。
(六)签名不齐全(含代签名的)均作废票处理。