SokotoCementFactoryProjectofthe17thBureau,ChineseRailwayConstructionCompany
ConstructionSchemesforFoundationpitExcavationAndReplacement
Composedby:
Editor:
Chiefeditor:
Fifthdivisionof17thBureauofCRCC,managerdepartmentoftheSokotoCementFactoryProject,Nigeria
23thNovember2104
Contents
1Introduction1
1.1Basisforthecomposition1
1.2Principlesforthecomposition1
2.1Location1
2.2Geographicreport2
2.3Groundwaterandundergroundwater.2
3Constructiontechniquesandmethods2
3.1Excavationofthefoundationpit2
3.1.1Gradientofthefoundationpit3
3.1.2Thestabilityofthesideslope3
3.1.3Theformofexcavation4
3.1.4Preparationfortheexcavation5
3.1.5Constructionprocedures6
3.1.6Methods6
3.2Gravelreplacement7
3.2.1Constructionmaterial7
3.2.2Constructionpreparation8
3.2.3Techniquesandconstructionalprocedure.8
3.2.4Methods9
4Organizationofconstructionandlogisticwork11
4.1Themanagingsystemforconstructionorganization.11
4.2Humanresourcesfortheconstruction11
4.3Logisticwork12
4.4Technicalguarantee12
4.5Qualityandtechniquesstandardandregulation12
4.5.1Qualitystandard12
4.5.2Qualitymonitoringorganization13
4.5.3Raisingawarenessfortheimportanceofqualityandprofessionalskills.13
4.5.4Establishingqualitymanagementcode.13
4.6Safetytechniquesmeasures14
4.6.1Safetyregulationsformechanicalconstruction14
4.6.2Trafficregulations15
4.6.3Safetyregulationsforfillingconstruction.15
4.7Environmentprotectionmeasures16
4.8Constructionduringtherainseason16
4.8.1Collectingweatherdata16
4.8.2Technicalmeasuresfordrainage16
4.9Technicalmeasuresforsandstorm17
4.10Contingencyplan17
ConstructionSchemesforFoundationpitExcavationAndReplacement
1Introduction
1.1Basisforthecomposition
1.1.1GeographicReportfortheSOKOTO3300T/DClinkerDryCementProductionLine
1.1.2DrawingssubmittedbytheOwner
1.1.3UnifiedStandardforConstructionalQualityAcceptanceofBuildingEngineering(GB50300-2001)。
1.1.4CodeforAcceptanceofConstructionQualityofFoundationEngineering(GB50203-2002)。
1.1.5TechnicalSpecificationforGroundTreatmentofBuilding(JGJ79-002)。
1.1.6TechnicalSpecificationforSafetyOperationofConstructionMachinery(JGJ33-2001)。
1.1.7CodeforInvestigationofGeotechnicalEngineering(GB50021-2001)。
1.1.8Statusofthesiteandsurroundingenvironment
1.1.9Calculationbookforconstructionengineering
1.2Principlesforthecomposition
1.2.1SignificantlyunderstandingtheBasisforthecomposition,composingwithintheframeofthepreviouscontractinthespiritofintegrity,subjectivityandtechnicalinnovationality.Developingexecutable,scientificandefficientconstructionschemesinthoroughconsiderationofthestatusofthesiteandotherprofessionaldrawings
2.Introductionoftheproject
2.1Location
ThesiteonwhichtheprojectistobecarriedoutlocatesinNorthCementFactory,Sokoto,Nigeria,adjacenttotheoriginalcementproductionline.Thesizeofthesiteis700metersby600meters.WiththehigherSouthendandlowerNorthend,thesiteconsistofthreestages:
114m,109mand105mrespectively.
2.2Geographicreport
InaccordancewiththegeographicreportprovidedbytheOwner,theexcavationinvolvesthreedifferenttypesofsoil.
Artificialfilllayer(Q4ml)(stratumnumber①)
Softsoilthatwidelyspreadsaroundthesite.Thickness:
0.3~11.5.Layerbottomelevation88.85~111.25m。
Clinosol(Q4dl)(stratumnumber②)
Themixofgravellysoilandcohesivesoilofbrownishredcolor.Thickness:
0.23~19.0m.Layerbottomelevation82.1~109.99m。
Cohesivesoil(stratumnumber③):
thesoiloflightgrayoryellow-graycolorandgoodsolidity.Medium/lowcompressibility.Characterizedbythehardcalcareouscore.Thickness:
3.25~24.83m,Layerbottomelevation75.27~87.99m。
2.3Groundwaterandundergroundwater.
Thesiteisgoingtousewaterfromundergroundwiththedepthofsevenmeters.Waterisaccessedtothroughwell.Theprecipitationamountissignificantlylowexceptinrainingseason,whichlastsfromJulytoSeptember.Thedrainagefacilitiesareneededfortheheavyprecipitation.
3Constructiontechniquesandmethods
3.1Excavationofthefoundationpit
Inconsiderationofthefeaturesofthesoilandthegeographicreport,itwasprimarilyconcludedthatlayer-by-layerslopeexcavationshallbeappliedforallbuildingsandstructuresfoundationpits.Incasethattherearebuildingsorstructuresthatrequiresupportforthesideslope,thenotherdesignshouldbemadeavailablefortheconstructionofthesupport.
3.1.1Gradientofthefoundationpit
1)Laterite C=15Kpaφ=8.4degreeγ=19.7KN/M
2)Shale C=20Kpaφ=11.4degreeγ=26KN/M
ItisnotedinthedesigndrawingsthatthedepthofthedeepfoundationpitHisnomorethan10meters,whichfallintotwocategoriesintermsofdepth:
0m≤H≤5m,5m≤H≤10M。
Basedontheequationonthepage41ofCalculationbookforconstructionengineering,thestableslopeangleiscalculatedtobenomorethan73degrees.Thegradientofthegradingissetat1/0.5onaccountofthesafetycoefficientandvehiculardisturbance.
Specificweightofthesoil(kg/m3)
Angleofgradient(°)
Internalfrictionangleofthesoil(°)
Cohesiveforceofthesoil(kg/m3)
Whenthesoilisinthestateoflimitequilibrium,themaximumheightofthesideslope(h)canbecalculatedthroughthisformula.
3.1.2Thestabilityofthesideslope
Thesafetycoefficientis1.13basedonthediagrambelow,whichmeetstherequirementofthedesignandregulations.
Thetextabove:
safetycoefficient:
1.13(Swedenfiniteslicemethod,totalstressmodel)
3.1.3Theformofexcavation
Accordingtothedesigndrawing,excavationofthefoundationpitshouldbeconductedintwodifferentformscorrespondingtodifferentdepthH:
H≤5m,5m<H≤10m.Thedetailsarepresentedbelow.Incasethattheexcavationdepthismorethan5meters,aone-meter-wideplatformshouldbecreatedwhentheexcavationreachesthecushion.
3.1.4Preparationfortheexcavation
1)Technicalpreparation:
a)Elevationbenchmarkhasbeenintroducedtotheconstructionareaonthebasisofelevationpointgivenbytheconstructionunit.
b)Otherpreparationworkincludegettingfamiliarwithdrawingsandgeographicalstatus,plantingaxis-controlpile,checkingundergroundpipeline,machineries,completingdisclosurework.
2)Sitepreparation:
a)Double-checkingoriginalcontrolplantsandbenchmark,layingoutpositioningline,settingupperimeterforfoundationpitexcavationlineandsideslopeline.Theexcavatedlateriteshouldbeputinasecurelocationwithinthesiteforthepurposeofbackfilling.ShaleshouldbedumpedintothedumpinggrounddesignatedbytheOwner.
b)Properlypreservingthefoundationpit,examiningthestabilityofthesideslopebeforeexcavating,mendingpartiallydamagedsideslopetoensurethestability.
c)Organizingmachineriesandworkforcetoenterthesiteinatimelymanner.Threeexcavators,onewheelloaderandsixtippersaretocoordinatewiththetransportation.Excavator,wheelloaderandtipperneedtobecheckedbeforedrivingtoensurethereliability.Alldriversshouldbeproperlylicensedandallmachineoperatorsshouldobserverelevantregulationsformachineoperating.Afterthevehicleisstarted,panel,light,alarmsteeringsystem,brakeandothernecessarypartsshouldbeexaminedforreliabilityandsensitivity.Fuel,lubricatingoilandhydraulicoilalsoneedtobecheckedtoensurethequality.Hingingparts,connectorsrequirecheckingforlooseningandhydraulicpressuresystemandhydraulictransmissionsystemforleakage.Loadingpeopleinthegrappleandviolatingdrivingregulationarestrictlyforbiddenandsubjecttopenalty.
d)Constructionschemesareopentoadjustmentbroughtupbythechangingsituationonthesiteormajoramendmenttothedrawing.
3.1.5
Surveyingandpositioning
riskeliminating
groundclearing
machineryentry
excavating
mendingandmaintainingsideslope
(continuingexcavatingandmaintaining)
flatteningthefoundationbase
testing
proceedingtonextstage
Constructionprocedures
3.1.6Methods
1)Aftersurveyingandpositioning,theexcavationlineonthehillcrestistobelaidoutandexcavatedbybackhoe.
2)Theexcavationworkshouldbeconductedlayerbylayeronbothsideofthesideslope.Toensurethestabilityofthesideslope,allexcavatedearthworkshouldberemovedouttimely.Forrectangularorpolylateralfoundationpit,thenumberofexcavatorandothervehiclesaretobedeterminedbythesizeanddepthofthefoundationpit,
3)Theelevationdemandsconstantattention.accuratemeasurementbythedumpylevelisrequiredasitisabouttoreachthedesignelevationtopreventover-excavating.Standingwithintheturningradiusofmechanicalarmwhileitisoperatingisstrictlyprohibited.Theexcavatingshouldbecarriedoutinorderandtheexcavatedearthworkneedtoberemovedastheexcavationgoeson.However,poorlyprotectedworkerarenotallowedtoworkinthesamespotasthemachine.Significantilluminationfacilitiesshouldbeinplaceifitisconsiderednecessarytoworkatnight.Onespeciallydesignatedtechnicianshouldberesponsibleforconductingexcavatorsandothervehicles.Thefoundationpitneedstobethoroughlyexaminedbyaninspectorforgeneralstabilitystatusandunstablefactorssuchascracksandsliding.Anyfactorthatmightleadtomajordamageshouldbeimmediatelyreportedtotheprojectmanager,whileinthemeantimetheconstructionneedstobesuspendedforevacuation.
4)Thetre
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 基坑开挖换填施工方案1123 英文版 基坑 开挖 施工 方案 1123 英文
![提示](https://static.bdocx.com/images/bang_tan.gif)