PMI-001ProjectManagementProfessional
QUESTIONNO:
1
TheinputsofthePerformanceReportingprocessincludeallofthefollowingexceptforwhichone?
A.Performancereviews
B.Workperformanceinformation
C.Forecastedcompletion
D.Performancemeasurements
Answer:
A
Explanation:
PerformancereviewsarenotaninputofthePerformanceReportingprocess.Theremaining
inputsofthisprocessarequalitycontrolmeasurements,projectmanagementplan,approved
changerequests,anddeliverables.
QUESTIONNO:
2
YouareaprojectmanagerforPizzaDirect,whichisaretailpizzadeliverystore.Yourcompanyis
competingwithanotherretailstorefortheoptionofopeningtwonewstoresinaforeigncountry.
Youknow,buthavenotyetinformedyourcompany,thatyouaregoingtogotoworkforthe
competitor,whichhappenstobebiddingforthissameopportunity.Whatisthemostappropriate
response?
A.Youdecidetoparticipateintheinitialmeetingswiththeforeignbusinesspartnersbecauseany
informationyougainnowwillhelpyouwhenyoumakethemovetothenewcompany.
B.Youinformtheforeignbusinesspartnersthatyou'regoingtobeworkingwithanewcompany
andthatyouknowthedealthey'llreceivefromthecompetingcompanyisbetterthantheonethis
companyisproposing.
C.Youdeclinetoparticipateintheinitialmeetingswiththeforeignbusinesspartnersbecauseofa
conflictofinterest.
D.You'venotyetreceivedanofficialofferfromthecompetingcompanyforyournewjob
opportunity,soyouchoosetoparticipateintheinitialmeetingswiththeforeignbusinesspartners.
Answer:
C
Explanation:
Themostappropriateresponseistodeclinetoparticipatebecauseofaconflict
ofinterest.
QUESTIONNO:
3
Themosteffectiveteammotivatoris:
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P2
PA.understandingtheimportanceoftheprojectB.thesatisfactionofmeetingachallenge
C.Alloftheotheralternativesapply.
D.thevisibilityoftheteam'scontributionE.theindividual'sprofessionalchallenge
Answer:
D
QUESTIONNO:
4
Completefinalcontractperformancereportingandverifyproductisdonein
_______.
A.ConductProcurements
B.CloseProcurements
C.PlanProcurements
D.AdministerProcurements
Answer:
B
Explanation:
Completefinalcontractperformancereportingandverifyproductisdonein
CloseProcurements.
QUESTIONNO:
5
Continuallymeasuringandmonitoringtheactualcostversusthebudgetis
doneto_____.
A.Noneoftheotheralternativesapply
.
B.analyzethereasonsforvariances
C.establishthevariances
D.identifytheproblems
E.Alloftheotheralternativesapply.
Answer:
E
QUESTIONNO:
6
YouareaprojectmanagerforGiraffeEnterprises.You'verecentlytakenover
foraproject
managerwholiedabouthisPMIcertificationandwassubsequentlyfired.
Unfortunately,hedida
poorjobofscopedefinition.Whichofthefollowingcouldhappenifyoudon'tcorrectthis?
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P3
PA.Theprojectcostscouldincrease,theremightberework,andscheduledelaysmightresult.
B.Theprojectmanagementplan'sprocessforverificationandacceptanceofthedeliverables
needstobeupdatedasaresultofthepoorscopedefinition.C.Thepoorscopedefinitionwilladverselyaffectthecreationoftheworkbreakdownstructure,
andcostswillincrease.
D.Thestakeholderswillrequireovertimefromtheprojectteamtokeeptheprojectonschedule.
Answer:
A
Explanation:
OptionAmightseemlikeacorrectanswer,butoptionDismorecorrect.Thereisn'tenough
informationtodeterminewhetherstakeholderswillrequireovertime.Wedoknowthatpoorscope
definitionmightleadtocostincreases,rework,scheduledelays,andpoormorale.
QUESTIONNO:
7
Youareaprojectmanagerworkinginaforeigncountry.Youobservethatsomeofyourproject
teammembersarehavingadifficulttimeadjustingtothenewculture.Youprovidedthemwith
trainingonculturaldifferencesandthecustomsofthiscountrybeforearriving,buttheystillseem
uncomfortableanddisoriented.Whichofthefollowingstatementsistrue?
A.Thisconditionisknownascultureshock.
B.Thisistheresultofjetlagandtravelfatigue.
C.Thisistheresultofworkingwithteamsofpeoplefromtwodifferentcountries.
D.Thisconditionisknownasglobalculturalism.
Answer:
A
Explanation:
Whenpeopleworkinunfamiliarenvironments,cultureshockcanoccur.Trainingandresearching
informationaboutthecountryyou'llbeworkingincanhelpcounteractthis.
QUESTIONNO:
8
WhichofthefollowingisnottrueforaResponsibilityAssignmentMatrix(RAM):
A.DefineswhatprojectmemberisresponsibleforeachactivityB.DefinesresponsibilitiesforeachWBScomponent
C.DefinesallpeopleassociatedwitheachactivityD.Textdescriptionofroles,responsibilities,authoritiesAnswer:
D
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P4
PExplanation:
TheResponsibilityAssignmentMatrix(RAM)detailsthedifferenttasksforthe
peoplelistedinthe
matrixchart.
QUESTIONNO:
9
Theerectionoffoundationformworkbeforetheplacementoffoundationconcretewouldbean
exampleofa_____dependency.
A.Softlogic
B.Subcontracted
C.Mandatory
D.Discretionary
E.External
Answer:
C
QUESTIONNO:
10
Youaretheprojectmanagerofaproject.YouhavejustcompletedtheCollect
RequirementsandDefineScope.Whatshouldyoudonext?
A.ControlScope
B.CreateWBS
C.Valueanalysis
D.VerifyScope
Answer:
B
Explanation:
CreatetheWBSistheprocessthatfollowsCollectRequirementsandDefineScope.
QUESTIONNO:
11
WhichofthefollowingisnottrueforaResponsibilityAssignmentMatrix(RAM):
A.DefineswhatprojectmemberisresponsibleforeachactivityB.Definesallpeopleassociatedwitheachactivity
C.DefinesresponsibilitiesforeachWBScomponentD.Alloftheotheralternativesapply
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P5
P
Answer:
D
Explanation:
TheResponsibilityAssignmentMatrix(RAM)detailsthedifferenttasksforthe
peoplelistedinthe
matrixchart.
QUESTIONNO:
12
Givingapartofprojectworktoacontractorisanexampleof:
A.riskassumption
B.riskassignment
C.riskdelegation
D.riskdeflection
E.riskmitigation
Answer:
D
QUESTIONNO:
13
Giventhefollowingestimates:
Optimistic3days,Pessimistic9days,andmost
likely
6days,whatisthePERTweightedaverage?
A.6.1
B.6.3
C.6
D.4
Answer:
B
QUESTIONNO:
14
Managementreservesarenormallydefinedasa%ofthetotalbudget.Asa
projectprogresses,
theprojectmanagerwantsthe$valueofmanagementreserveto_____,
whereasthecustomer
wantsthemanagementreserveto_____.
A.Increase,increase.
B.Increase,decrease.
C.Remainthesame,returntocustomer.
D.Decrease,increase.
E.Decrease,decrease.
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P6
PAnswer:
C
QUESTIONNO:
15
Theprojectmanagerhas,asaprimeresponsibility,toassureproperintegrationofactivities.In
whichorganizationalformdoestheprojectmanagerprobablyhavetheeasiest
timeinintegrating
work?
A.Matrix
B.Pureproject
C.Coordinator
D.Classical
E.Expediter
Answer:
B
QUESTIONNO:
16
Formalwrittencorrespondenceismandatedinwhichofthefollowingsituations:
A.ClientrequestsadditionalworknotcoveredundercontractB.Noneoftheotheralternativesapply
C.Both1)Clientrequestsadditionalworknotcoveredundercontract,and2)
Projectmanager
callsameeting.
D.Projectmanagercallsameeting
E.Productundergoescasualin-housetesting
Answer:
A
QUESTIONNO:
17
Smoothingoutresourcerequirementsfromperiodtoperiodiscalledresource
_____.
A.Noneoftheotheralternativesapply.
B.Leveling.
C.Quantification
D.Partitioning
E.Allocation.
Answer:
B
PMIPMI-001:
PracticeExam
"PassAnyExam.AnyTime."-www.P7
PQUESTIONNO:
18
YouareaprojectmanagerforCinemaSnickerProductions.Yourcompanyspecializesin
producingcomedyfilmsforthebigscreen.Yourlatestprojecthasjustbeencompletedand
accepted.You'vebeengivenyournextproject,whichstartsrightaway.Whichofthefollowing
statementsistrue?
A.Thisprojectendedduetointegrationbecauseitwascompletedandaccepted.
B.Thisprojectendedduetoextinctionbecauseitwascompletedandaccepted.
C.Thisprojectendedduetointegrationbecauseitwascompletedandacceptedandtheproject
managermovedontoanewproject.
D.Thisprojectendedduetoadditionbecauseitwascompletedandacceptedandarchivedinto
thecompany'scatalogofavailablefilms.
Answer:
B
Explanation:
Extinctionisthebesttypeofprojectendbecauseitmeanstheprojectwascompletedsuccessfully
andacceptedbythesponsororcustomer.
QUESTIONNO:
19
Whichisavalidresponsetonegativerisks?
A.mitigation
B.Enhance
C.Exploit
D.Share
Answer:
A
Explanation:
Riskmitigationisaresponsetonegativerisksandnotpositiverisks.Positiverisksmaybe
respondedby-"Exploit","Enhance","Share","Accept".QUESTIONNO:
20
Projectleadershiprequiresthattheprojectmanagerpayattentionsimultaneouslytothe:
A.Time,costandperformancedeliverables
B.Taskstobeperformedandneedsoftheteam
C.Quantityandqualityo