旧路改造工程棚洞施工技术方案
旧路改造工程棚洞施工技术方案-
旧路改造工程棚洞施工技术方案
旧路改造工程棚洞施工技术方案
1.编制范围、原则及依据...........................................................................................................................................1
1.1编制范围...........................................................................................................................................................1
1.2编制原则...........................................................................................................................................................1
1.3编制依据...........................................................................................................................................................1
1.4技术标准...........................................................................................................................................................2
1.5方案选择因素...................................................................................................................................................2
2.工程概况..................................................................................................................................................................2
2.1工程概况...........................................................................................................................................................2
2.2水文、地质概况...............................................................................................................................................3
2.2.1自然地理条件...........................................................................................................................................3
2.2.2地形、地貌...............................................................................................................................................4
2.2.3气象、水文...............................................................................................................................................4
2.2.4地层岩性...................................................................................................................................................5
2.2.5地质构造与地震.......................................................................................................................................6
2.2.6不良地质...................................................................................................................................................6
3.施工工期总体安排...................................................................................................................................................7
4.工、料、机及其他准备...........................................................................................................................................7
4.1技术准备...........................................................................................................................................................7
4.2主要机械设备进场计划及资源安排..............................................................................................................10
4.3人员进场计划及资源安排..............................................................................................................................10
4.4主要工程量.....................................................................................................................................................11
5.棚洞施工方案........................................................................................................................................................12
5.1处理原则.........................................................................................................................................................12
5.2施工前准备工作.............................................................................................................................................12
5.3破碎岩石处理.................................................................................................................................................12
5.4基础换填片石砼.............................................................................................................................................13
5.5棚洞基础砼浇筑.............................................................................................................................................13
5.6棚洞墙身砼浇筑.............................................................................................................................................14
5.7棚洞顶板砼浇筑.............................................................................................................................................14
5.8棚洞顶土石回填.............................................................................................................................................17
6.安全生产预防措施.................................................................................................................................................18
6.1危险源的综合预防与控制措施..................................................................................................................18
6.2主要危险源安全预防措施.........................................................................................................................19
7.应急预案................................................................................................................................................................19
7.1目的.............................................................................................................................................................19
7.2应急反应预案.............................................................................................................................................19
8.质量保证措施........................................................................................................................................................21
8.1项目质量管理体系组织机构..........................................................................................................................21
9.针对本项目施工地点应急预案.............................................................................................................................23
9.1防汛预案.........................................................................................................................................................23
9.2避洪汛预案.....................................................................................................................................................23
10.针对本项目施工地点保通方案...........................................................................................................................23
10.1保通方案目的...............................................................................................................................................23
10.2保通指导思想...............................................................................................................................................24
10.3保通组织机构...............................................................................................................................................24
10.4省道**********施工保通方案....................................................................................................................24
10.5应急措施启动的条件....................................................................................................................................25
10.6具体应急处置保通措施................................................................................................................................25
棚洞施工方案
1.编制范围、原则及依据
1.1编制范围
本实施性施工组织设计编制范围为**********K64+570~K64+720段棚洞工程的施工,共长150km。
1.2编制原则
1、根据业主的“工期、质量、安全、成本”四大目标进行编制。
2、严格按照合同文件要求的原则进行编制。
认真阅读施工图设计、详细核对工程量、合同文件。
3、严格按照真实、合理的原则。
通过对本工程的理解,合理安排人员、设备、材料的投入。
4、严格按照科学、先进的原则。
根据工程实际情况,科学的选用流水作业法施工,充分运用先进的网络计划技术进行施工组织和管理。
5、严格按照节能、降耗的原则。
尽量采用机械化施工、减轻劳动强度;合理进行设备选型,提高劳动生产率;因地制宜,就地取材;采取革新、改造、挖潜措施,努力节约投入成本。
6、严格按照质量第一、安全生产的原则。
积极推行全面质量管理,确保工程质量与施工,切实贯彻施工技术规范、操作规程和制度;制定合理的安全保证措施,严抓严管,警钟长鸣。
1.3编制依据
1)《**********两阶段施工图纸设计》
2)《公路路基施工技术规范》JTGF10-2006
3)《公路工程质量检验评定标准》JTGF80/1—2004
4)《公路工程施工安全技术规程》JTJ076-95
5)《交通工程土工合成材料土工格栅》JT/T480—2002
6)《公路土工合成材料应用技术规范》JTG-TD32-2012
7)《公路工程技术标准》JTGB01-2003
8)《公路土工试验规程》JTGE40—2007
9)《工程测量规范》GB50026-93
10)施工现场考察及调查周边环境所了解的情况和收集的信息
11)公司现有的技术装备、管理水平和类似工程的施工经验
1.4技术标准
1)公路等级:
二级公路
2)棚洞设计速度:
40km/h
3)棚洞建筑界限:
净宽9m,净高5m,行车道3.5*2m,侧向宽度0.25m,检修道0.75m
4)棚洞路面横坡:
单向坡2%,超高段不大于±4%
5)棚洞内最大纵坡:
不大于±4%,最小纵坡±0.3%
6)路面设计荷载:
公路-II级
7)棚洞防水等级:
一级
1.5方案选择因素
1)地质条件:
充分考虑合同段内属于山区,挖方量较大,石方所占比例较大,需进行爆破施工,又是旧路改造工程,要保证道路畅通,保证施工安全及施工进度。
2)交通条件:
路线所经区域原道路交通较方便,选择红线内原有道路作为施工通道。
3)施工工期:
根据不同的地质条件采用不同处理方式,加大处理机械投入力度,缩短整个施工工期。
4)环保因素:
在施工期间对清除的非适用性材料进行合理堆放及处理。
2.工程概况
2.1工程概况
1、**********棚洞平面位于R=245的圆曲线,棚洞为单向坡,坡率分别为-0.7%、-2.689%;进口洞门桩号为K64+570,高程为2072.57,洞门为端墙式,出口洞门桩号为K64+720,高程为2070.52,洞门为端墙式;棚洞采用矩形框架结构。
结构顶板厚度1m,两侧边墙厚度1m。
均采用C30钢筋砼。
洞顶回填形式:
A型棚洞:
结构外包防水层,顶部满布一层C20细石砼厚10cm,其上部回填均厚2m的土石后,在整个回填层顶部做一层C20砼板块层厚25cm。
2、棚洞均位于Ⅷ度地震区,施工中要考虑挡拦部分可能落至棚洞左侧的石块,采取措施:
以钢筋砼以确保整体结构的抗震性能;结构底部采用筏形基础,同时设置伸入基础