A7栋型钢外架施工方案.docx
- 文档编号:27265155
- 上传时间:2023-06-28
- 格式:DOCX
- 页数:20
- 大小:86.27KB
A7栋型钢外架施工方案.docx
《A7栋型钢外架施工方案.docx》由会员分享,可在线阅读,更多相关《A7栋型钢外架施工方案.docx(20页珍藏版)》请在冰豆网上搜索。
A7栋型钢外架施工方案
目录
一、编制依据·························································································1
二、编制说明·························································································1
三、材料要求·························································································1
四、脚手架搭设准备·············································································2
五、外脚手架搭的施工方法··································································3
六、安全管理························································································13
七、防电避雷措施················································································16
八、脚手架的验收················································································16
九、脚手架的维护与管理····································································17
一、编制依据
1)、《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2001(2002版)。
2)、《建筑结构荷载规范》GB50009-2001。
a)施工手册第四版。
b)《建筑施工安全检查标准》(JGJ59-99)。
c)《建筑施工高空作业安全检查标准》(JGJ80-91)。
二、编制说明
百里杜鹃大道拆迁安置房工程位于贵州省毕节市百里杜鹃大道。
该项目由A4、A6、A7住宅楼、及地下车库组成。
A7栋建筑面积为46287.54㎡(地下车库:
5056.78㎡;1F~4F商场:
8543.72㎡;5F~25F住宅:
32687.64㎡);A4及A6之间地下车库建筑面积为4217.4㎡;A4栋3280.49㎡;A6栋4307.88㎡。
建筑类别为一类,耐火等级为一级,抗震设防烈度为6度、结构合理使用年限50年。
A7栋工程为-2+4+25F层高层住宅楼,-2~-1层为地下车库(地下室);标准层为3.0m,地下室负二层-7.8m,负一层为-3.9m,1F为4.2m,2~3F为3.9m,4F为5.4m;建筑高度:
地下7.8m,地上高度98m;设计标高±0.000相当于黄海高程1472.00m。
为了确保在整个施工工程中的安全,实现项目部确定的安全生产目标,根据安全文明施工要求,决定采用全封闭式钢管外脚手架,对工程整个外围安全防护实施全封闭施工方案,即将整个工程外墙施工区域逐层进行严密包裹。
A4、A6住宅楼、地下车库及A7栋-2~-1地下车库、1F~4F商场外脚手架都采用双排钢管外防护脚手架,每层按步距0.9m,立杆纵距按1.8m搭设。
5F~25F住宅标准层采用长3m的[14槽钢悬挑,每六层悬挑一次,悬挑长度1.2m,在建筑物室内1.7m处设置Φ12的钢筋锚环,距外边缘向内0.3m处再设置一道Φ12的钢筋锚环都用木削削牢;形式为单杆双排外防护脚手架,外防护脚手架外侧满挂密目式安全网。
三、材料要求:
1、钢管:
(1)使用符合《低压流体输送用焊接钢管》(GB/T3092)中规定的φ48×3.5钢管,不得与其它类型规格钢管混用;
(2)长度宜为4~6m长;
(3)凡严重腐蚀、弯曲、压扁或裂纹者,严禁使用;
2、扣件:
(1)符合《钢管脚手架扣件》(GB15831)中的规定;
(2)重要部位重复使用的扣件,按规定抽检;
(3)有出厂合格证,并应与架杆规格配套使用;
(4)有裂缝、变形的严禁使用;出现滑丝的螺栓必须更换。
3、安全网:
(1)三证齐全;
(2)能承受160kg/m2以上的荷载;
四、外脚手架搭设准备
外封闭脚手架搭设准备:
根据外脚手架搭设的长度及高度,计算出所用的钢管、扣件的数量,绿色密眼安全网、竹压板的数量等,并按脚手架搭设要求确定出钢管的各种规格尺寸,扣件的各种数量以及绿色密眼安全网(1.8×6.0m)、5mm厚竹压板(1.0×2.0m)的需用量编制供应计划,可根据现场施工进度分批供应入场。
为了使外脚手架达到便于施工的作用和美观的效果,决定将外架钢管的颜色统一涂刷成长度为500mm黄黑相间的颜色,钢管必须先涂刷完成再运送至现场进行搭设,不准搭设后涂刷,并对入场材料的质量进行检查,禁止使用不合格的材料。
五、外脚手架搭设的施工方法
1、A4栋、A6栋、地下车库及A7栋-2~-1地下车库、1F~4F商场外脚手架搭设施工方法:
1)、杆件间距参数:
防护脚手架构造形式:
双排外防护脚手架
立杆距外墙面距离:
外立杆距墙1m,内立杆距墙200mm
立杆间距:
1.8m步距:
0.9m
小横杆间距:
0.9m步距:
1.8m
2)、搭设方法:
、放线、定位(确定柱距、排距、步距),按脚手架柱距、排距要求进行放线、定位。
、搭设顺序:
铺垫板放置纵向扫地杆立柱横向扫地杆第一步纵向水平杆第一步横向水平杆连墙件(或加抛撑);第二步纵向水平杆第二步横向水平杆……。
、搭设注意事项:
、搭设前必须进行施工技术交底,按要求备料;
、按1.8m间距,架设立杆,垂直偏差控制在1/400以内,立杆接头必须采用对接扣件;
、纵向水平杆设置在立杆内侧,其长度不宜小于三跨。
两根相邻纵向水平杆的接头不宜设置在同步或同跨内;不同步或不同跨两个相邻接头在水平方向错开的距离不应小于500mm,各接头中心至最近主节点的距离不宜大于纵距的1/3,搭接长度不应小于1m,应等间距设置3个旋转扣件固定,端部扣件盖板边缘至搭接纵向水平杆杆端的距离不应小于100mm。
、主接点处必须设置横向水平杆,用直角扣件扣接且严禁拆除。
主节点处两个直角扣件的中心距不应大于150mm。
作业层上非主节点处的横向水平杆,宜根据支承脚手板的需要等间距设置,最大间距不应大于纵距的1/2,横向水平杆的两端采用直角扣件固定在立杆上。
横向水平杆连墙件的一端,应用直角扣件固定在立杆上,另一端应与框架柱、短肢墙固定。
一字型、开口型脚手架的两端必须设置连墙件,连墙件垂直间距不应大于建筑物的层高,并不应大于4m(2步)。
连墙杆的水平间距不宜大于6m。
连墙件宜布置在靠近主节点设置,偏离主节点的距离不应大于300mm。
脚手架必须设置纵、横向扫地杆纵向扫地杆应采用直角扣件固定在距底部大于200mm的立杆上,横向扫地杆采用直角扣件固定在紧靠纵向扫在杆下端的立杆上。
当立杆基础不在同一高度上时,必须将高处的纵向扫地杆向低处延长两跨与立杆固定,高低差不应大于1m,靠边坡上方的立杆轴线到边坡的距离不应小于500mm。
900
900
≤2000
900
≥500
<1000
200
200
1800
1800
立杆接长除顶层顶步可采用搭接外,其余各层各步接头必须采用对接扣件连接扣件连接。
对接、搭接应符合下列规定:
a、立杆上的接扣件应交错布置:
两根相邻立杆的接头不应设置在同步内,同步内隔一根立杆的两个相隔接头在高度方向错开的距离不宜小于500mm;各接头中心至主节点的距离不宜大于步距的1/3;
b、搭接长度不应小于1m,就采用不少于2个旋转扣件固定,端部扣件盖板的边缘至杆端距离不应小于100mm。
、立杆顶端宜高出4F女儿墙上皮1m。
≥500
≤L/3
立杆
纵向水平杆
LL
立杆底部素土夯实后铺60×160垫木。
、剪刀撑的角度应在45-60度为宜;剪刀撑宽度不应小于4跨,且不应小于6m;高度24m以下的脚手架中间各道剪刀撑之间的水平净距不应大于15m,高度24m以上的脚手架应在外侧立面整个长度和高度上连续设置剪刀撑;双排脚手架必须设置横向斜撑,一字型、开口型双排脚手架的两端均必须设置横向斜撑,横向斜撑的设置应在同一节间,由底至顶呈之字形布置。
、作业层上主节点处的横向水平杆,宜根据支承脚手板的需要等间距设置,最大间距不应大于纵距的1/2;脚手板应铺满,铺稳,离开墙面120mm—150mm脚手板采用搭接铺设,接头必须支在横向水平杆上,搭接长度应大于200mm,其伸出横向水平杆的长度不应小于100mm。
作业层端部竹脚手板探头长度取150mm,脚手板探头应用直径3.2mm的镀锌钢丝固定在支承杆件上;自顶层作业层的脚手板住下计,宜每隔12mm满铺一层脚手板;其板长两端均应与支承杆可靠地固定。
、一次搭设高度不应超过相邻连墙件以上二步
用安全绳将密目式安全网满挂于脚手架外侧,并封堵严密、绑扎牢固;
、第4F商场转换层主体施工完成后,予以拆除;
3)、因本工程-2~-1地下车库、1F~4F商场的外防护架搭设方法为常规施工方法,无其它特殊要求,可不进行验算。
2、A7栋5F~25F住宅标准层外脚手架搭设施工方法:
从A7栋建筑物第5F住宅标准层开始搭设单立双排钢管外防护脚手架。
采用长3m的[14槽钢悬挑,每六层悬挑一次,悬挑长度1.2m,室内1.7m处设置Φ12的钢筋锚环,距建筑物外边向内0.3m处再设置一道Φ12的钢筋锚环都用木削把[14槽钢削牢。
1)杆件间距参数
脚手架构造形式:
单立双排钢管脚手架
立杆离墙面距离:
内立杆:
0.15mLb=1.00m外立杆:
1.15m
立杆纵向间距:
La=1.8m步距:
1.8m
小横杆间距:
1.00m
连墙件竖向间距:
H1=3.6m(二步),水平间距L1=5.4m(三跨)
2)、脚手架的荷载计算
荷载计算参数
a、脚手架搭设高度Hd=18m,采用Φ48×3.5钢管,材料为Q235(3号)钢,脚手架排距Lb=1.00m;其截面特性:
A=489㎜2,I=12.19cm4,W=5.08cm3,I=15.8㎜;。
1.8×6.0m绿色密目安全网网目尺寸为5.0mm×5.0mm,绳径3.2mm,自重0.01KN/㎡。
外立面铺设安全网全封闭,基本风压ω0=0.40kN/㎡(查GB50009-2001);
b、脚手板自重标准值:
采用竹串片脚手板0.35kN/㎡;
c、拦板与挡墙脚手板自重标准值:
竹串扯脚手挡板0.14kN/m;
d、脚手架外侧立面采用密目安全网自重标准值:
0.01kN/㎡;
e、每米立杆承受的结构自重标准值勤:
0.1161kN/m;(查JGJ130-2001表A-1)
f、装饰脚手架作业层上的施工均布活荷载:
2kN/㎡;
g、水平风荷载标准值:
μz=1.0(查GBJ50009-2001)
μS=1.3ψ=1.3×1.2×0.5(安全网的挡风系数)=0.78
Wk=0.7μzμSW0=0.7×1.0×0.78×0.40=0.22kN/㎡。
、支撑横杆受弯承载力计算:
a、支撑横杆所受荷载简化为均布荷载:
q=[(1.0×1.8×2)×1.4+(0.35×1.0×1.8+1.8×0.14)×1.2]÷1.0=6.10kN/m。
b、支撑横杆所受的最大弯矩:
M=0.125ql2=0.125×6.10×1.02=0.763kN·m
c、强度计算:
σ=M/W=0.763×106÷(5.08×103)=150N/㎜2满足要求
d、挠度计算:
W=5ql4/(384EI)5×6.10×10004÷(384×2.06×105×12.19×104)=3.16mm<1/150=1000150=6.67mm满足要求
、连墙杆计算:
连墙杆采用二步三跨设置,与结构进行可靠连接。
a、连墙杆的轴向力设计值
Nl=Nlw+No
由风荷载产生的连墙杆的轴向力设计值:
Nlw=1.4Wk·Aw=1.4×0.22×(1.8×2×1.8×3)=5.99KN
所以Nl=Nlw+No=5.99+5=10.99KN
b、扣件抗滑移计算
R=11.65kN<13.0kN(双扣件抗滑力)
所以需要双扣件。
、立杆的稳定性计算
a、立杆的有效长度计算
L0=kμh=1.155×1.5×1.8=3.12m
b、立杆的长细比
λ=L0/I=3.12×1000÷15.8=197,查表得Φ=0.186
c、风荷载设计值产生的立杆段弯矩
Mw=0.85×1.4Wk·M=0.85×1.4Wk·la·h2/10
=0.85×1.4×0.22×2.0×1.82÷10=0.170kN·m
d、立杆段的轴向力设计值:
N=1.2(NGik+NGzk)+0.85×1.4ΣNQk
NGik=21×0.1161+(0.35×1.0×1.8+1.8×0.14)×2÷2+1.8×21×0.01=3.7kN
NQk=2×1.0×1.8×2÷2=3.6kN
所以N=1.2×3.7+0.85×1.4×3.6=8.724kN
e、立杆稳定性计算:
б=N/(ΦA)+Mw/W
=8.724×103÷(0.186×489)0.176×106÷(5.08×103)
=129N/mm2 满足要求 、型钢承载力计算: NGik=21×0.1161+(0.35×1.0×1.8+1.8×0.14)×2÷2+1.8×21×0.01=3.7kN NQk=2×1.0×1.8×2÷2=3.6kN 所以N外=1.2×3.7+1.4×3.6=9.48kN N内=(21×0.1161=0.35×1.0×1.8×2÷2)×1.2+2×1.0×1.8×2÷2×1.4=8.72kN Mmax=PL=8.72×0.15+9.48×1.15=12.21kN·m б=M/rW=12.21×106/1.05×80.5×103=144.45N/mm2 满足要求 锚环验算: P×1.7=8.72×0.15+9.48×1.15 P=7.18kN<3.14×62×50×2=11.304kN 满足要求 3)、外全封闭脚手挑架的搭设方法 、放线、定位[14槽钢(确定柱距、排距、步距),按脚手架柱距、排距要求进行放线、定位。 、搭设顺序: 铺[14槽钢放置纵向扫地杆立柱横向扫地杆第一步纵向水平杆第一步横向水平杆连墙件(或加抛撑);第二步纵向水平杆 第二步横向水平杆……。 、搭设注意事项: 、操作工人进行施工技术交底: a、操作外架时,操作人员心须戴好安全帽、系好安全带,严禁酒后作业。 b、设立警戒区域,派专人进行监护,严禁上下同时作业。 c、对操作工人进行详细安全施工方案和技术交底,做好交底记录,同时组织工人学习相关的脚手架搭设操作规范。 、外脚手挑架的搭设方法 立杆: 立杆沿建筑物周边间距为1.8m(跨距),垂直二建筑物方向间距1.0m (排距),内侧立杆距结构边缘为0.15m,立杆接头必须采用对接扣件连接,接 头交错布置,相邻立杆接头不能设置在同步或同跨内,且相邻两个接闲位置错 开心须大于500mm,接头中点至主节点不宜大于步距的1/3,立杆垂直偏差控 制在1/400以内。 立杆与槽钢相接部位,在槽钢上焊接长≥500mm的Φ25钢筋, 使立杆在槽钢上不会发生偏移。 大横杆: 大横杆应设置在立杆的内侧,垂直步距为1.8m,并在外侧立杆上 两大横杆之间增加一道大横杆,此道大横杆距下面一道大横杆0.9m,以满足裙房 外装饰时的使用安全和方便防护架进行封闭。 大横杆可采用对接连接,也可采用 搭接,采用对接时,两根相邻横杆不能在同步或同跨内设置接头,且接头位置在 水平、垂直方向错开必须大于500mm。 采用搭接时,搭接长度大于1.0m,应等 距设置3个旋转扣件固定,端部扣件盖板边缘至搭接水平杆的端部的距离大于 100mm。 小横杆: 小横杆按水平间距1.8m、步距1.8m进行搭设,并设置在大横杆与 立杆的交点处,两面端固定,小横杆伸出防护架外侧的长度严格控制在 100mm~150mm之间,以保证防护架的美观。 连墙杆: 连墙杆采用Φ48钢管刚性连接,水平方向每隔1根立杆设置一道, 垂直方向每隔2根大横杆(或每一人层高)设置一道,设置时一端设置在防护架 节点处,偏离主节点不大于200mm,另一端与墙、柱梁连接牢固。 连墙件从防护 架底层开始设置,在搭设至设有连墙杆部位时搭设完成该处立杆、横杆后应立即 设置连墙杆,以保证架的稳定。 剪刀撑: 剪刀撑采用连续设置,每道剪刀撑宽度不应小于4跨,且不 应小于6m。 斜杆与地面的夹角必须控制在45—60度之间。 中间各道剪刀撑之间的净距不应大于15m。 竖向封闭: 保证防护架高出每层楼面1.5以上防护架,就应立即铺设防护网。 首先,用细铁丝将竹压板竖向捆绑在防护架的外侧水平杆上,竹压板应置于绿色密眼安全网的内侧,捆绑时应用双股铁丝进行牢固连接,相邻(上、下、左、右)两块竹压板应连接紧密并用铁丝绑牢,不得有空隙或漏绑现象。 其次,应在外侧立杆的内侧(或大横杆)上挂设绿色密眼安全网,在挂设安全网时,必须用防雨、不易腐蚀的专用尼龙绳进行捆绑,要用力拉紧安全网并用绳子穿过网上预留的穿绳孔与水平杆紧密捆绑。 保持安全网的平整度,来格控制好网与网相连的水平连缝和竖向连缝,不得漏捆,以防影响其安全防护功能的发挥和外侧立面的美观。 水平防护: 安全防护架和竖向防护网搭设完毕后为了保证使用安全首先在第 五层高度位置设置一道全封闭水平防护。 此道水平防护满铺一层中枋,再铺设一 道竹压板。 其余的水平防护应沿竖向每隔5步架高(8.0~9.0m)铺设一道临时防 护网。 中间层水平防护做法为: 首先在短横杆上铺60×160长木枋,木枋应用10 号铁丝将其与横杆牢固连接,木枋间距不大于400mm。 在木枋接头处应增设双短横杆,以撑住木枋端部避免瞎子跳。 木枋铺设完成后,在其上铺放一道竹压板进行来密封堵,并用铁丝相边牢固严禁出现孔洞。 每日派专人对水平防护上的垃圾进行清理,以确保水平防护的完整性和安全性。 、护架搭设完毕、验收后,应办理好验收手续,任何人不得擅自破坏防护 设施的任何部位。 如遇特殊情况需要临时拆除局部防护架时,应提前向安全部门申请,并提供相应的安全防护措施,得到批准后,按补救措施进行实施,应根据具体情况及时恢复防护架的原样。 3、检查 用扭矩扳手检查其固定脚手架的扣件螺栓拧紧强度,发现有未拧紧或达不到规定的强度值,应立即重新拧紧,防止发生安全事故。 脚手架搭设过程中、使用前均严格按“脚手架搭设技术要求和允许偏差”对架体进行遂项检查,及时纠正不合格点、及时排除安全隐患。 4、拆除 ①拆除前全面检查脚手架的扣件连接、连墙件、支撑体系等是否符合安全要求,遂层作好技术交底,并清除架体上杂物,障碍物等。 ②拆除顺序应逐层由上而下进行,严禁上、下同时作业。 ③所有连墙件应随脚手架逐层拆除,严禁将连墙件整层或数层拆除后再拆除脚手架,分段拆除高差不得大于2步,否则应增设连墙件加固。 ④脚手架拆至下部最后一根立杆时,应先在适当位置搭临时抛撑作加固处理。 ⑤拆卸的配件、架管及时整修、保养,并整齐推码于指定地点。 六、安全管理 (一)人员要求 1、脚手架搭设人员必须是经过国家现行标准《特种作业人员安全技术考核管理规则》考核合格的专业架子工。 上岗人员应定期体检,体检合格者方可发上岗证。 2、搭设脚手架人员必须戴安全帽、系安全带,穿防滑鞋等。 (二)搭设阶段 1、脚手架的构配件质量必须按规定要求进行检验,合格后方准使用。 2、脚手架搭设应按下列阶段进行质量检查,发现问题应及时校正。 (1)操作层上施加荷载前; (2)每搭设完10m高度后; (3)达到设计高度后。 3、脚手架的搭设质量必须符合要求,并经现场业主、监理及公司安全科等部门、人员检查,合格后方能投入使用。 (三)使用阶段 1、操作层上的施工荷载应符合设计要求,不得超载;不得将模板支撑、缆风绳等固定在脚手架上,严禁任意悬挂起重设备。 2、六级及六级以上大风和雾、雨天应停止脚手架作业,雨后上架操作应有防滑措施。 3、应设专人负责对脚手架进行经常检查和保修: (1)在下列情况下,必须对脚手架进行检查; 1)在六级大风与大雨后; 2)停用超过一个月,复工前。 (2)检查保修项目: 1)各主节点处诸杆件的安装,连墙件、支撑、门洞等的构造是否符合施工组织设计要求; 2)地基是否积水,底座是否松动、立柱是否悬空; 3)扣件螺栓是否松动; 4)安全防护措施是否符合要求。 4、在脚手架使用期间,严禁任意拆除下列杆件: (1)主节点处的纵、横向水平杆,纵、横向扫地杆; (2)连墙件; (3)支撑; (4)拦杆、挡脚板。 要拆除上述任一杆件均应采取安全措施,并报项目部批准。 5、严禁任意在脚手架基础及其邻近处进行挖掘作业,否则应采取安全措施,并报项目部批准。 6、在脚手架上进行电、气焊作业时,必须有防火措施和专人看守。 7、工地临时用电线路的架设及脚手架接地、避雷措施等应按国家现行标准《施工现场临时用电安全技术规范》(JGJ46-88)的有关规定执行。 (四)拆除阶段 拆除脚手架进,地面应设围栏和警戒标志,并派专人看守,严禁一切非操作人员入内。 七、防电避雷措施 (一)该工程临时用电线路均从地下埋敷,不存在安全隐患。 ①施工期间遇有雷雨时,钢脚手架上的操作人员立即停止施工,撤离危险区域。 ②于建筑物各个转角且不超过30m,隔层将主体避雷引下线与架管立杆用Φ12筋相互焊接。 八、脚手架的验收 架子搭设和组装完毕,在投入使用前,应逐层、逐流水段由主管工长、架子班组长和专职技安人员一起组织验收,并填写验收单。 内容如下: 1、架子的布置、立杆、大小横杆间距; 2、架子的搭设和组装,包括工具架和起重点的选择; 3、连墙点或与结构固定部分要安全可靠;剪刀撑、斜撑应符合要求; 4、架子的安全防护;安全保险装置要有效;扣件和绑扎拧紧程度应符合规定;脚手架的起重机具、纲丝绳、吊杆的安装等要安全可靠,脚手板的铺设应符合规定; 5、脚手架的基础处理、作法、埋置深度必须正确可靠。 九、脚手架的维护与管理 1、使用完毕的脚手架(包括构配件)应及时回收入库、分类存放。 露天堆放时,场地应平整,排水良好,下设支垫,并用苫布遮盖。 配件、零件应存放在室内。 2、凡弯曲、变形的杆件应先调直,损坏的构配件应先修复,方能入库存放,否则应更换。 3、要定期对脚手架的构配件进行除锈、防锈处理。 扣件要涂油。 螺栓宜镀锌防锈或在每次使用后用煤油洗涤,再涂上机油防锈。 4、脚手架使用的扣件、螺母、垫板、插销等小配件极易丢失,在支配时应将多余件及时回收存放,在拆除时亦应及时验收,不得乱扔乱放。 5、建立健全脚手架工具材料的领发、回收、检查、维修制度,按照谁使用、谁管理的原则,实行限额
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- A7 型钢 施工 方案