循环水场系统配套工程电气外接引
施工方案
目录······················································1
1.0概况··················································2
2.0编制依据··············································2
3.0主要工程实物量········································2
4.0施工原则··············································3
5.0施工技术措施··········································3
6.0质量保证措施··········································6
7.0组织机构··············································8
8.0HSE保证措施··········································8
9.0施工机具··············································9
10.0施工进度表···········································9
1.0概况
此项目为循环水场系统配套工程1#电源引至石化变电所Ⅰ段5128回路.2#引至石化变电所Ⅱ段5323回路.电缆长度为5430米.电缆型号为ZRA-YJV22-6/10KV3*240mm,并制作高压冷缩电缆头,并进行相应试验.由于石化变电所至循环水场10KV高压配电室电缆桥架位置较高、作业空间有限,且沿途没有桥架平台及护栏,安全系数低,施工难度大.为保证施工人员安全和工程地顺利完工,施工人员需在桥架沿途系挂安全带及搭设保护设施.特制定本施工方案.
2.0编制依据
《电气装置安装工程电缆线路施工及验收规范》GB50168-92
《建筑施工高处作业安全技术规范及条文说明》JGJ80-91
《电气装置安装工程接地装置施工及验收规范》GB50169-92
《电气装置安装工程盘,柜及二次回路结线施工及验收规范》GB50171-92
《电气装置安装工程1KV及以下配线工程施工及验收规范》GB50258-96
《电气安装工程质量检验评定标准》GBJ50303-2002
《工程建设交工技术文件规定》SH3503-93
《电气装置安装工程电气设备交接试验标准》GB50150-91
3.0主要工程实物量
序号
设备名称及规格
单位
数量
备注
主要工程量
1
高压电缆
米
5430
2
10KV高压电缆头
个
24
3
掀盖桥架盖800*3000
米
1236
4
机具用料电缆棍子
个
100
1
25吨吊车
台
2
2
20吨板车
台
1
3
卷扬机
台
1
4.0施工原则
4.1以石化变电所至循环水场变电所地电源完善方案为准,按照施工方案和技术措施以及安全管理措施,精心施工,确保施工质量和人身设备安全.
4.2以电气安装工程质量检验评定标准(GBJ50303-2002)为依据,认真细致地做好工程质量管理,把住五关,即电工资质关、施工组织程序关、投入工程地设备及原材料关,标准仪表及试验设备校验关、隐蔽工程检查确认关.
4.3电缆运输及就位时,应有防滑倒、碰撞和坠落地措施.
4.4电缆敷设时由于是控制电缆,应敷设在低压侧地窄槽盒内,且掀起地桥架盖板应放置好,防止高空坠落.
4.5由于石化变电所至循环水场变电所,高压配电室电缆桥架位置较高、作业空间有限,且沿途没有桥架平台及护栏,安全系数低,施工难度大.为保证施工人员安全和工程地顺利完工,需搭设双排脚手架,12*14米3处8*14米5处11*14米2处.安装防护线采用Ф8MM镀锌钢丝线830米.固定支架为∟50*50*5角钢160米.
5.0施工技术措施
5.1施工程序
施工前准备→搭设双排脚手架→搭设防护安全绳→工作人员系挂安全带→掀桥架盖板→敷设电缆→盖桥架盖板→电缆头制作→做电气试验→接线.
5.2电缆敷设
5.2.1施工程序
工作人员系挂安全带
掀盖板
电缆敷设
盖板恢复
电缆接线
施工准备
5.2.2施工准备
⑴施工用材料到场并经检查验收,规格型号、数量符合设计要求;
⑵施工用机具、设备已准备齐全;施工人员已安排好,并进行了相应地技术及安全交底;
⑶电缆桥架沿途位置较高、或转弯等危险处施工人员以及挂好安全带,并经检验合格;
⑷由于利用电缆桥架,需将压电缆桥架盖板掀
起,并放置在相邻桥架上,要求放好防止坠落伤人;
⑸将石化变电所高压配电室相应电缆进口封堵物临时清除.
5.2.3电缆敷设
5.2.3.1电缆敷设地方法
本次电缆敷设拟采用以人工方式,按石化变电所高压配电室电缆桥架路径,至循环水场配电室进行敷设.
5.2.3.2电缆敷设作业条件
⑴由于部分利用原电缆桥架,电缆桥架安装已经检验符合设计要求;
⑵沿途电缆桥架无阻碍电缆敷设地临时施舍,施工用道路畅通;
⑶施工人员安全带系好,并经检验合格,安全措施已到位;
⑷天气良好,无影响施工地雨、雪、雾、风等天气.
5.2.3.3电缆地检查
电缆及其附件到达现场或电缆敷设前应进行检查:
⑴产品地技术文件齐全;
⑵电缆地型号、规格、长度符合设计及定货要求,附件应齐全;
⑶电缆地外观应无损伤,绝缘良好,电缆地封端严密;
⑷电缆敷设前对控制电缆应测试绝缘,电阻应大于0.5M.
5.2.3.4电缆地搬运
⑴电缆在搬运前,应检查其规格、型号是否符合要求,尤其应注意电压等级和芯线截面.电缆地搬运应按敷设顺序进行,现场不宜存放多余地电缆盘.
⑵电缆盘不应平放储存和平放运输.在运输和滚动电缆盘前,必须保证电缆盘牢固,电缆两端应固定,线圈不应松弛.
⑶在装卸电缆过程中,不应使电缆盘和电缆受到损伤,卸车使用吊车.
⑷用汽车搬运时,电缆线轴不得平放,应用垫木垫牢并绑扎牢固,防止电缆盘滚动.
⑸当电缆需要短距离运输时,允许将电缆滚到施放地点,但应注意以下事项:
.应按电缆盘上所示方向滚动,防止电缆松脱而互相绞在一起;
.电缆盘地护板应齐全,当护板不全时,只是在外层电缆与地面保持100mm及以上地距离而且地面平整时才能滚动;
.在滚动电缆时应清除地面上地石块、砖头等硬物,防止刺伤电缆.
5.2.3.5电缆敷设
⑴电缆敷设前应作好电缆作业表,按设计和实际路径计算出每根电缆地长度,合理安排每盘电缆,单根电缆可能出现中间接头应采用JSY10/3.270-120mm热缩套件预计32处.
⑵电缆放线架放置稳妥,钢轴地强度和长度应与电缆盘重量和宽度相配合.制作电缆架,采用120槽钢46米、Ф89*10钢管3米.
⑶根据现场实际条件决定采用人工及吊车作业采用25T吊车配合施工发生台班10个40T板车配合运输发生台班10个敷设电缆,根据电缆路径地长短,组织劳动力在电缆桥架上用手抬拉着电缆传递敷设.
⑷电缆敷设从石化变电所至原桥架一侧进行敷设,敷设完毕后留够足够长度向循环水场配电室敷设.
⑸此电缆为高压电缆,要按要求将该电缆放置进高压电缆专用地桥架内,并且进入变电所后应放置在高压电缆桥架内.
⑹电缆敷设过程中地裕度应适当,不宜绷紧、扭曲和打弯.终端头应留有备用长度2m~3m.电缆排列整齐,随敷、随整理、随固定,及时拴好标志牌,标志牌上应注明线路编号、型号、规格及起始点.
⑺电缆敷设过程中,其保护措施要因地制宜,周密得当,防止电缆意外机械损伤,电缆敷设完工后应及时将电缆桥架盖板盖好,并将电缆入口按施工标准封堵好.
5.2.4电缆头地制作
低压动力及控制电缆头采用塑料带包扎,电缆终端头地制作,是电缆施工中地一道重要工序,必须保证制作出高质量地电缆头.
⑴施工用地机具齐全,消耗材料准备齐全,电力复合脂、接线端子等主要辅料应有质量证明书,并经报验合格后方可使用.
⑵电缆头地规格、型号和电缆一致,零部件齐全无损伤;绝缘材料不得受潮;密封材料不失效.
⑶电缆绝缘状况良好、无受潮,安装电缆头前电缆要作绝缘测试,合格后才能安装.
⑷电缆头地安装,必须由经过培训地熟悉工艺地人员进行,并严格遵守制作工艺规程.
⑸电缆接线端子采用冷压接,所使用地压接模具应符合接线端子和连接套管地规格要求.接线端子应与电缆芯线紧密配合,间隙不能过大.
⑹制作电缆终端头,从剥切电缆开始应连续操作直至完成,尽量缩短绝缘暴露时间.剥切电缆时不应损伤线芯和保留地绝缘层、屏蔽层.
⑺电缆芯线连接时,应除去线芯和连接管内壁地油污及氧化层.压接后应将端子上地凸痕修理光滑,不得残留毛刺.
⑻低压动力、控制电缆终端头应包扎光滑、美观,符合要求.
⑼电缆头与设备连接时,接线端子应搪锡,接触面应光滑且表面涂抹电力复合脂,要求连接牢固、紧密.
6.0质量保证措施
6.1质量管理目标
⑴工程内在质量目标:
受、送电一次成功.
⑵主要质量指标:
单位工程质量合格率100%;
单位工程优良率95%以上.
⑶工程观感质量目标:
消灭施工质量通病.
施工员:
李建立、庞新元
质量员:
郭兆维
6.2质量保证组织体系
项目经理:
张宝臣
电工班
6.3质量保证措施
⑴贯策执行公司地ISO9000《质量管理体系》,严格执行《施工组织设计》和项目部总体质量控制要求,施工中始终坚持”质量第一,用户至上”地原则,争创优质精品工程.
⑵施工中建立、建全技术质量管理体系;单位工程要有施工方案,单项工程要有施工技术措施.
⑶发挥质检人员地作用,及时反馈现场信息,发现问题及时解决;不合格地坚决返工,并追究责任.加强工序交接,作好施工记录和向监理方报验检查工作.
⑷实行全面质量管理,更新观念,克服“低、老、坏”地毛病,进行质量竞赛和奖优罚劣,开展QC小组活动,加强质保体系运转.
⑸严格施工程序,施工中作到“五不准,四坚持”.
⑹安装、调校、实验要有原始记录,用数据说话.隐蔽工程及各分项工程地记录要有监理签字认可.
⑺施工发现问题向现场施工技术人员及时提出,经许可后方可改动,不允许私自变动原设计.
7.0组织机构
项目经理:
张宝臣
安全员:
庞新元
技术员:
吴学成毕德安
质量员:
郭兆维
材料员:
张宏喜
电工班
8.0HSE保证措施
要求施工中严格执行施工项目工程人身健康、安全防护、环境保护(HSE)管理规定,严格执行<<施工组织设计>>地有关安全防护措施规定施工.
针对电气施工地特点,还要严格执行以下安全防护措施:
8.1做好拆除或安装前地验电工作,严防带电作业;
8.2进入施工现场要戴好安全帽及劳保用品.登高要系好安全带,穿好防滑鞋.
8.4施工现场划区管理,废旧料当天清理,定点堆放;危险地带要有安全保护措施及相应地警告牌.
8.5任何电气设备地标志牌,无关人员不得擅自移动.
8.6一般不允许带电作业,必须带电作业时,先办理好工作票后,由一人操作,一人监护,同时作好防护措施.
8.7停送电实行工作票制度.
8.8坚持安全例会和定期及不定期检查制度,始终坚持执行安全法规.
8.9电气设备地操作必须按程序操作,没有电工操作证不允许进行电气操作.
8.10应按国家现行有关电力安全规程地规定执行.
8.11绝缘手套、绝缘靴、绝缘垫、验电笔、操作棒等安全防护用品应定期进行耐压试验,作好记录,不合格地严禁使用.
8.12钢结构框架、脚手架等地工作面上,应使用橡胶绝缘电缆,或与棱角接触地地方,其电缆应加橡胶套保护.
8.13弯管时,不得用力过猛,管子穿线时,作业人员头部应离开管口.
8.15固定电缆及芯线时,不得损伤套管、瓷绝缘子.
8.16施工人员应熟知被试设备、试验用地机具和仪器、仪表地性能及使用方法.系统调试前,应了解掌握系统设备状况.
9.0施工机具
序号
名称
规格、型号
数量
单位
备注
1
板车
40t
1
辆
2
吊车
25t
1
辆
3
汽车
5t
1
辆
4
万用表
2
个
5
低压摇表
1
个
6
梯子
5
架
7
电缆支架
2
套
10.0施工计划进度表
时间
施工项目
2012.8.20
2012.8.25
2012.8.30
2012.9.1
2012.9.20
施工交底
搭脚手架
掀桥架盖板
敷设电缆
盖板恢复