63真空断路器交接试验作业指导书
第4部分:
电气试验
真空断路器交接试验作业指导书
编码:
BDYCSY-ZW-05
目次
1适用范围························································································································································31
2编写依据························································································································································31
3作业流程························································································································································31
4安全风险辨析与预控·····························································································································31
5作业准备························································································································································32
6作业方法························································································································································33
7质量控制措施及检验标准···················································································································34
1适用范围
本作业指导书适用于真空断路器。
2编写依据
表2-1编写依据
序号
引用资料名称
1
GB50150—2006《电气装置安装工程电气设备交接试验标准》
2
DL408—1991《电业安全工作规程(发电厂和变电站电气部分)》
3作业流程
图3-1作业(工序)流程图
4安全风险辨析与预控
4.1真空断路器交接试验前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与真空断路器交接试验相关联的《电网建设安全施工作业票》(编码:
BDYCSY-ZW-05-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须重新办理作业票,在工作完成后上交项目部保存备查。
表4-1作业任务安全基准风险指南
序号
危害名称
风险种类
风险等级
风险控制措施
1
试验设备未接地或接地不良
设备损坏
低风险
试验前,应认真检查接地线连接可靠,接地良好
2
试验人员接线错误
设备烧损
中等风险
在试验前工作人员需熟悉说明书、图纸,按照要求接线,并有工作负责人核查接线正确性
3
试验区域未设置安全围栏
人身伤残
中等风险
试验区域必须按规定设置安全围栏和标示牌等安全措施,并安排专人进行监护
4
引接试验电源时触电
人身伤亡
高风险
严格执行电气工作票,落实各项安全措施,加强监护
序号
危害名称
风险种类
风险等级
风险控制措施
5
试验电源不稳定
设备损坏
中等风险
试验前应用仪器测量电源电压,确保符合试验要求
6
试验设备吊装时安全防护措施不完善
设备损坏
高风险
吊装时工作人员必须持证上岗、专人指挥吊装
7
机械运动部分
人身伤残
中等风险
试验前确保断路器机构箱处无人工作
8
登高作业安全防护措施不完善
人身伤残
高风险
使用高空平台车、梯子登高接线,如必须作业人员登高作业时,需正确使用安全带,穿胶鞋
9
设备存在感应电
人身伤残
中等风险
使用保安接地线
10
高压试验过程中防范措施不到位
人身伤残
高风险
试验开始时,应通知附近作业人员,并设置安全围栏,派专人把守;操作人员应大声告知各在场人员,得到回应“可以开始”后方可升压,如有异常应立即断电
11
高压试验过程中发生电压反击
设备损坏
中等风险
严格按照规定流程操作
12
攀爬瓷件
设备损坏
中等风险
作业人员攀爬瓷件时需佩戴安全带,穿胶鞋。
不得采用抛物形式传递工具,必须使用绳索正确传递工具
13
被试品残余电荷
人身伤残
低风险
试验后,应及时对被试品充分放电,放电用的接地线必须可靠接地
5作业准备
5.1人员配备
表5-1作业人员配备
工序名称
建议工作人数
负责人数
监护人数
元件检查
2
1
1
主绝缘检查
2
1
1
开关直流电阻测量
2
1
1
导电回路直流电阻
2
1
1
开关特性试验
2
1
1
交流耐压试验
4
1
1
注:
作业人数根据具体工程量规模配备。
5.2工器具及仪器仪表配置
表5-2主要工器具及仪器仪表配置
序号
名称
规格/编号
单位
数量
备注
1
绝缘电阻表
只
1
2
大电流回路电阻测试仪
台
1
3
高压开关特性测试仪
台
1
表5-2(续)
序号
名称
规格/编号
单位
数量
备注
4
万用表
只
1
5
交流耐压设备
套
1
6
工具
套
1
7
2.5mm2导线及接地线
m
若干
注:
主要工器具及仪器仪表根据具体工程量规模配备。
6作业方法
6.1作业条件检查
6.1.1检查开关安装完毕,符合试验条件。
6.1.2现场条件满足试验要求。
6.1.3检查工作票完善,工作安全措施完善。
6.1.4试验人员符合要求,熟悉相关资料和技术要求。
6.1.5相关试验仪器已准备,并保证其完好。
6.2外观检查
6.2.1检查开关安装完好,无机械损伤。
6.2.2检查开关柜内无杂物,元器件无受潮现象。
6.2.3柜体接地已完善可靠。
6.2.4柜内二次接线完善、牢固。
6.2.5柜体型号、铭牌参数与设计一致。
6.3元件检查
6.3.1测量分、合闸线圈的绝缘电阻和直流电阻,用500V绝缘电阻表分别测量分闸线圈和合闸线圈对
地的绝缘电阻,要求不低于10M,用万用表或单臂电桥分别测量分闸线圈和合闸线圈的直流电阻。
6.3.2储能电机检查。
用500V绝缘电阻表测量电机的绝缘电阻;检查储能电机额定电压与设计相符;通入电机额定的电源,检查电机运转是否正常和储能机构工作是否正常。
6.4主导电回路绝缘电阻测量
6.4.1测量断路器导电回路对地及断口间的绝缘电阻,断路器在合闸状态,分别测量每相导电回路对地的绝缘电阻;在分闸状态测量各断口之间的绝缘电阻。
6.4.2测试时要求用专用测试导线。
6.5测量每相导电回路的直流电阻
6.5.1用大电流回路电阻测试仪分别测量每相导电回路的直流电阻。
6.5.2回路电阻测试仪要求可靠接地,通过专用引线和断路器可靠连接,电压测量线应在电流输出线内侧。
6.5.3测量时电流要求不小于100A。
测量读数要求在稳定数值时开始读数。
6.5.4测量完毕要求待测试仪放电完才能断开测试回路。
6.5.5要求测试结果符合产品技术规范,测试时必须记录当时环境温度,以进行电阻值的换算。
6.6断路器的特性试验
6.6.1用高压开关特性测试仪分别测量断路器的分、合闸时间、弹跳时间及同期性,将试验仪器可靠接地。
6.6.2测量时要求电源电压及气压都在额定条件。
6.6.3合闸过程中断路器弹跳时间在40.5kV以上不大于3ms,40.5kV以下不大于2ms。
6.6.4分、合闸时间测试实际数据应符合产品技术条件的规定。
6.6.5测量操动机构的电气特性。
调节断路器控制回路电压,在85%~110%Un情况下断路器能可靠的分、合,在65%Un情况下断路器能可靠地分开,在30%Un情况下断路器不能分、合。
6.7交流耐压试验
用试验变压器、调压器组成一个高压交流回路作为高压交流电源,分别对断路器每相的合闸状态对
地、分闸状态断口间进行耐压试验(具体试验方法见特殊性试验交流耐压试验部分)。
7质量控制措施及检验标准
7.1质量控制措施
7.1.1测量断路器主触头的分、合闸时间,测量分、合闸的同期性,测量合闸过程中触头接触后的弹跳时间。
7.1.2测量绝缘拉杆的绝缘电阻值,不应低于1200M。
7.1.3测量每相导电回路的电阻值应符合产品技术条件的规定。
7.1.4交流耐压试验。
应在断路器合闸及分闸状态下进行交流耐压试验;当在合闸状态下进行时,试验
电压应符合表7-1的规定;当在分闸状态下进行时,真空灭弧室断口间的试验电压应符合产品技术条件的规定,试验中不应发生贯穿性放电。
表7-1合闸状态下进行交流耐压时的试验电压
额定电压
kV
最高工作电压
kV
1min工频耐受电压峰值,kV
相对地
相间
断路器断口
隔离断口
3
3.6
25
25
25
27
6
7.2
32
32
32
36
10
12
42
42
42
49
35
40.5
95
95
95
118
66
72.5
155
155
155
197
110
126
200
200
200
225
230
230
230
265
7.1.5测量断路器主触头的分、合闸时间,测量分、合闸的同期性,测量合闸过程中触头接触后的弹跳
时间。
7.1.6合闸过程中触头接触后的弹跳时间:
40.5kV以下断路器不应大于2ms;40.5kV及以上断路器不应大于3ms。
7.1.7测量应在断路器额定操作电压及液压条件下进行。
7.1.8实测数值应符合产品技术条件的规定。
7.1.9测量分、合闸线圈及合闸接触器线圈的绝缘电阻值,不应低于10M;直流电阻值与产品出厂试
验值相比应无明显差别。
7.1.10断路器操动机构的试验,应符合下列规定:
(1)合闸操作的操作电压在85%~110%Un时操动机构应可靠动作。
(2)分闸操作的操作电压在大于65%Un时,应可靠地分闸;当小于30%Un时,不应分闸。
7.2质量控制表
表7-2质量控制表
序号
控制点
控制方式
W
H
S
1
真空断路器试验
●
注:
质量控制点中H:
停工待检点;W:
见证点;S:
旁站点。
7.3检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第4册:
变电电气试验工程》
中的Q/CSG表4-11.1.1、Q/CSG表4-11.2.1~4-11.2.2要求执行。
附件1安全施工作业票
编码:
BDYCSY-ZW-05-01/01
工作时间
工作地点
技术员
现场安全员
现场负责人
安全风险分析及控制措施
序号
危害名称
风险种类
风险等级
风险控制措施
1
试验人员接线错误
设备烧损
□中等风险
现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施:
□试验前,应认真检查接地线连接可靠,接地良好。
□接试验前应用仪器测量电源电压,确保符合试验要求。
□在试验前工作人员需熟悉说明书、图纸后,按照要求接线,并有工作负责人核查接线正确性。
□试验前确保断路器机构箱处无人工作。
□试验区域必须按规定设置安全围栏和标示牌等安全措施,并安排专人进行监护。
□使用保安接地线。
□试验开始时,应通知附近作业人员,并设置安全围栏,派专人把守;操作人员应大声告知各在场人员,得到回应可以开始,方可升压,如有异常应立即断电。
□试验人员正确使用必要的绝缘工具、安全防护用品。
□试验后,应及时对被试品充分放电,放电用的接地线必须可靠接地。
□严格按照规定流程操作。
□使用高空平台车接线,如必须作业人员攀爬瓷裙时,需穿戴安全带,穿胶鞋,不得采用抛物形式传递工具,必须使用绳索正确传递工具。
□指挥、司索专人持证上岗;起吊前检查吊具;作业过程中遵守作业规范。
□严格执行电气工作票,落实各项安全措施,加强监护。
□试验完毕认真检查,确认拆接引线已恢复,临时接地线已拆除,现场无遗留工具和杂物
2
被试品残余电荷
触电
□低风险
3
高压试验过程中发生电压反击
设备破损
□中等风险
4
试验设备未接地或接地不良
设备烧损
□低风险
5
试验电源不稳定
设备烧损
□中等风险
6
登高作业安全防护措施不完善
坠落
□高风险
7
设备存在感应电
触电
□中等风险
8
试验电源不稳定
设备烧损
□中等风险
9
机械运动部分
夹伤坠落
□中等风险
10
高压试验过程中防范措施不到位
触电
□高风险
11
试验区域未设置安全围栏
触电
□中等风险
12
攀爬瓷件
设备破损
□中等风险
13
试验设备吊装时安全防护措施不完善
设备破损
□高风险
14
引接试验电源时触电
人身伤亡
□高风险
安全补充事项/平面布置图
现场接受交底人员签名
备注
说明:
(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。
现场负责人开工前核对风险控制措施
并宣读。
(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变
更时,应在备注栏记录变更情况。
对新增人员进行交底,并签名确认。
(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。
(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。
(五)基准风险等级与风险控制措施在开工前现场打“√”。
(六)签名不齐全(含代签名的)均作废票处理。