CONSTRUCTABILITYPROGRAM
CONSTRUCTABILITYPROGRAM
TABLEOFCONTENTS
1.0SCOPE3
2.0PURPOSE3
3.0DEFINITIONS3
4.0RESPONSIBILITIES4
5.0INSTRUCTIONS5
6.0REFERENCES6
7.0ATTACHMENTS6
1.SCOPE
ThisprojectspecificationdefinestherequirementsforConstructabilityforallprocessunits,offsitesandutilitiesontheCNOOCandShellPetrochemicalsComplex(CSPC)Project.ThespecificationisapplicabletotheImplementationphase.
2.PURPOSE
ThepurposeofthisspecificationistodescribetheextentofConstructabilityreviewsthatwillbeundertakenfortheImplementationphaseofthisproject.Thespecificationalsoadvisestheinvolvedpartiesandtheirresponsibility.
3.DEFINITIONS
3.1Constructability,asdefinedbytheUSAConstructionIndustryInstitute(Cll),is“theoptimumuseofconstructionknowledgeandexperienceinplanning,design,procurementandfieldoperationstoachieveoverallprojectobjectives”.
Constructabilityistheongoingprocessofintegratingconstructionknowledgeandexperienceintoconceptualdesign,procurement,detailedengineeringandfieldconstructionoperationswhichprovidestheopportunitytoreducecostsandimproveprojectschedules.
Theabilitytoinfluenceprojectcostsandtoincorporateconstructionexperienceandmethodsintoaprojectplananddesignisgreatestduringtheearlystagesoftheproject.Therefore,thegreatestbenefitoftheConstructabilityprocesswillbederivedwiththeearliestestablishmentandimplementationofaConstructabilityplanonaproject.
3.2Constructabilityreviewreferstotheprocesswherebyexpertsfromeverydisciplinegathertogethertoconsiderandquestionadesigninordertoexplorethepossibilitythatdesignimprovementsmayallowreducedconstructioncostsorimproveconveniencefortheenduser.TheConstructabilityreviewwillbeattendedbyexperiencedconstructionandoperationspersonnel,someexperiencedpersonnelwhowerenotinvolvedintheoriginaldesign,togetherwiththedesignteam.
TheConstructabilitydesignreviewprocessgenerallyleadstosuggestionsfordesignimprovementswhich:
-
willensurebuild-ability
willalloweasierandhencelowercostconstruction
willimprovesafetyduringconstructionbyreducingrisk
willimproveaccessibilityduringboththeconstructionandoperatingphase
••••
4.RESPONSIBILITIES
4.1EPorEPCCONTRACTORshallsubmithisConstructabilityProgramforPMCapproval.Thisshalladdressasaminimumallareasidentifiedinthisspecification.
4.2PMCwillnominateaConstructionCoordinatorwhowillmonitorcompliancebytheCONTRACTORtohisConstructabilityProgram.
4.3CONTRACTORshallappointaConstructabilityEngineertoleadandco-ordinateallhisconstructabilityactivitiesthroughouttheengineering/procurementphaseoftheproject.
4.4EPorEPCProjectManager
4.4.1ShallensureascheduleofConstructabilityreviewsispreparedtosuitthescheduleofdesigndocumentproduction.
4.4.2ShallchairtheformalConstructabilityreviewsandensurethat,thecorrectexpertiseparticipates,andthatthefindingsoftheteamareproperlydocumentedandallocatedtoactioneesandthatcompletionisfollowedup.
4.4.3Shallreviewrelevantpreviousexperience(e.g.operationalerts)priortoConstructabilitymeetings.
4.4.4ShallprepareanagendafortheConstructabilityreview.
4.5EPorEPCConstructabilityEngineer
TheEPorEPCConstructabilityEngineershallprovideconstructionknowledge,experienceandengineeringinputintotheprojectthroughoutallphasesoftheproject.
TheConstructabilityEngineershallarrangeforotherconstructionspecialists,asrequiredbytheproject.Hisresponsibilitiesinclude:
•ArrangefortheproductionoftheContractorprojectsiteHSEplans
•ArrangeforHazardstoConstructionriskassessments/HEMPcompliance
•Developtheconstructionexecutionplan(asapplicable).
•Arrangeforconstructabilityanddesignreviews.
•Inputtotheconstructionschedule/constructionareabreakdown/detailedworkbreakdownstructure(WBS)andconstructionsequencing.
•Arrangetransportationandliftingstudies(formajorequipment).
•Arrangeandcoordinateallspecialistconstructionpersonnel
•Coordinatewithmaterialcontrolandshipping.
•Ensuresitesurveysareconducted
•Provideconstructioninputintopre-qualificationofsubcontractors.
•Developthetemporaryfacilities(asapplicable).
•Ensuretheappropriatelessonslearntfrompreviousprojectsaretakenintoconsideration.
•Developandarrangeforthetimelyproductionofallconstructiondeliverables.
•CarryforwardconstructabilityissuesidentifiedinDefinitionPhase(PMCwillprovide).
•PrepareandimplementConstructabilityAwarenessWorkshops.
5INSTRUCTIONS
5.1Programme
CONTRACTORshalldevelopaprogrammeofprojectspecificconstructiondeliverablesandformalreviews,whichwilldefineresponsibilitiesandduedatescompatiblewiththeprojectschedule.
5.2Constructability
TheConstructabilityEngineerwillarrangefortheConstructabilityreviewteam,whichwillbedrawnfromkeymembersoftheprojectteamandotherrequiredspecialists.Thesekeypersonnelwillconductformalreviewsasdeterminedbythescheduleandprojectrequirements.Thekeypersonnelwillnormallybedrawnfromthefollowing:
PMCConstructionCo-ordinator
CompanyRepresentative
FromContractor
ProjectManager
EngineeringManager
ChiefEngineers
ConstructionManager
PlanningEngineer
HSEManager
QualityAssuranceManager
ProjectCommissioningEngineer
MaterialsManager
Otherspecialistsmayberequiredtoparticipateintheconstructabilityreviewsdependingonthesubjectbeingreviewed.Itisanticipatedthatmostconstructabilityactivitieswillinvolveonlyasmallnumberoftheaboveatanyonetime.
TheagendaforeachConstructabilityreviewwilldefinewhichpersonnelarerequiredtoattend.
5.3ConstructabilityAwarenessWorkshops
ContractorshallsubmithisproposalsforPMCapprovalforConstructabilityAwarenessatalllevelsinhisorganisation.
5.4ConstructabilityIdeasLog
ContractorshallincludehisproposalsforoperatingaConstructability
IdeasLogtoraiseandcloseoutgoodpracticesandinnovativeideas.••••••••••••
5.5LessonsLearned
PreviousexperiencesonsimilarprojectsandlocationsincludingfromPMCshallbeconsideredtogetherwithapplicableitemsfromthe“lessonslearned”databaseandcorporatealerts.
PriortoabovereferencedConstructabilityreviews,attendeesshallprovidereferencestopreviousexperience/lessonslearnedtotheConstructabilityEngineertocollate.
5.6BasisofReviews
Thereviewsshallusethechecklistsprovidedinsection7attachments.
5.7DocumentationforReviews
TheContractorEngineeringManagershallensuredocumentsrequiredundersection7attachmentlistsareavailableattheConstructabilityreview.
5.8MaintenanceofConstructabilityRecords
TheContractorConstructabilityEngineershallmaintainrecordsofconstructabilityactivities/outcomes.
5.9PMCConstructabilityForums
PMCwillleadamaximumofthreeonedayConstructabilityForumstobeattendedbyContractorConstructabilityEngineers.AdditionalattendeeswillbedrawnfromConstructabilityreviewattendeeslistedin5.2.Thefirstwilltakeplacewithinsixmonthsofcontractaward.
Thepurposeoftheseforumswillbetoshareprogressandlessonslearntandagreeactionplanswhereappropriate.
6REFERENCES
6.1HSEPlan:
ManagementSystemsOverviewSP-8560-0000-0003
6.2HSEPlan:
SiteManagementSP-8560-0000-0006
6.3ConstructionEnvironmentalControlPlanPR8560-000-1503
7.ATTACHMENTS
7.1CheckListforConstructabilityreviews.
7.2Engineeringdocumentstobereviewed.
ATTACHMENT7.1
CONSTRUCTABILITYCHECKLIST
CONTRACTORshallnotethatintheDefinitionPhasePlotPlanandConstructabilityreviewswerecarriedout.PMCwillprovidecopiesoftheminutestoCONTRACTORforDefinitionPhasestatusonfollowingitems:
1.Arethereanyexistingbuildings/structuresonthesitewherethenewplantisduetobebuilt?
2.Isthereanycontaminatedlandonthenewsite?
Ifsohavetheproblemsassociatedwiththisbeenquantified?
3.Arethereanyexistingoverheadorundergroundservices?
4.Willconstructioninvolveworkerscomingintocontactwithlead,asbestos,PCBsorradioactivesubstances?
5.Istheproposedconstructionsiteadjacenttoanyotherindustrial,commercial,domesticactivityorexistingoperatingplant?
Howwillconstructionbemanagedtoensurethattherewillbenoadverseinteractionsorcanthesebeengineeredout?
6.Arethereanyverylarge,heavy,specialorcomplexitemsofequipmentrequiringspecialattention?
7.Areitemsin(6)beingdesignedfortransportandlift?
8.Howwillsuchitemsgettothesite?
9.Whatisthestrategyfordressingofvesselsandmodularisation?
10.Arethereanyspecialrequirementsforon-siteconstruction?
11.Howarethelinestobetested?
12.Towhatextentischemicalcleaningrequired?
13.Arethereanyspecialsafetyrequirements?
14.Whatisthedesignstrategytominimisethelevelofriskduringconstructionandcommissioning?
15.Wherearethelaydownareasandconstructionoffices?
16.Arethereadequateareasforliftingoperations?
17.Whicharetheroutesforthemovementoflargeloadsonplot?
18.Areroadswideenoughforcranestogetinandoutagain?
19.Willfiredheatersarriveonsiteinonepiece?
Willtheyneedtobeerectedonsite?
20.Areanyvesselsortanksbeingerectedfrompiecesonsite?
Isspaceavailable?
21.Arecompressorsbeingerectedonsite?
Isspaceavailable?
22.Isthereastrategyfor