15C卧式双吸泵HorizontalShaftDrivenDoubleSuctionPumps
SPECIFICATIONSFORHORIZONTALSHAFTDRIVENDOUBLESUCTIONPUMPINGSETSANDACCESSORIES
TableofContent
PageNo.
1.0PART1–GENERAL
1.1SCOPE6c-3
1.2Type6c-3
1.3UNITRESPONSIBILITY6c-3
1.4DesignRequirements6c-3
1.5CRITICALSPEEDS6c-4
1.6FACTORYTESTING6c-4
1.6.1Materials6c-4
1.6.2PerformanceTests6c-4
1.6.3HydrostaticTests6c-4
1.6.4VibrationTests6c-5
1.6.5MotorTests6c-5
1.7ENVIRONMENTALCONDITIONS6c-5
1.8Warranty6c-5
2.0PART2–PRODUCTS
2.1PUMPS6c-6
2.1.1OperatingConditions6c-6
2.1.2Speed6c-7
2.1.3Efficiency6c-8
2.1.4ConstructionMaterials6c-8
2.1.5Coupling6c-8
2.1.6PressureGauges6c-8
2.1.7Construction6c-8
2.1.8CalibrationofInstruments&Meters6c-9
2.2ELECTRICMOTORSANDLTEQUIPMENT6c-10
2.2.1Motors6c-10
2.2.2Insulation6c-10
2.2.3ThermalProtection6c-10
2.2.4SpaceHeaters6c-10
2.2.5Bearings6c-10
2.2.6MotorMounting6c-10
2.2.7Balance6c-11
2.2.8ProtectionofEnclosure6c-11
2.2.9Motor-PumpCoupling6c-11
2.2.10MotorRating6c-11
2.2.11
Revisedon29-04-2013
MotorControlCentre6c-11
PageNo.
2.2.12PanelEnclosureConstruction6c-11
2.2.13Dimensions6c-12
2.2.14ArrangementofComponentswithinEnclosures6c-12
2.2.15WiringwithintheEnclosures6c-12
2.2.16SupplyIncomingSection6c-12
2.2.17Busbars6c-13
2.2.18MotorStartingSection6c-13
2.2.19AutomaticControllers&Interlocks6c-14
2.2.20ElectricalPanelBasicElements6c-14
2.2.21MouldedCaseCircuitBreaker(Mccb)6c-14
2.2.22Contactors6c-14
2.2.23AutoTransformers(IfApplicable)6c-15
2.2.24AmmetersandVoltmeters6c-15
2.2.25Controls–IndicatorsandAlarms6c-15
2.2.26EarthingTerminals6c-15
2.2.27PowerCables6c-15
2.2.28ControlCables6c-15
2.2.29CableInstallation6c-16
2.2.30.EarthElectrodes6c-16
2.2.31EarthConductors6c-16
2.2.32ItemstobeEarthed6c-16
2.3SPARES6c-17
3.0PART3–EXECUTION
3.1INSTALLATION6c-18
3.2CERTIFICATION6c-18
3.3TESTING6c-18
SPECIFICATIONSFORHORIZONTALSHAFTDRIVENDOUBLESUCTIONPUMPINGSETSANDACCESSORIES
1.0PART1-GENERAL
1.1SCOPE
Eachpumpingunitshallconsistofahorizontaldoublesuctioncentrifugalpump,coupling,squirrelcageinductionmotorandallnecessaryappurtenancestoprovideacompletepumpingsystem.Thecontractorshallrequirethatthepumpingunitsspecifiedhereintobesuppliedbyasinglemanufacturer.Thecontractorshallsupplyinstall,commissionandhandoverallequipmenttothesatisfactionoftheEngineer.
Thetenderermustvisitthesiteandinspectthespacerequirementandotherinstallationrequirementsbeforemakingthebid.
1.2Type
Eachpumpshallbeofthehorizontallysplitvolutecasing,enclosedimpeller,doublesuctioncentrifugaltype,designedsothattheimpellershaftandbearingscanberemovedwithoutdisturbingtheconnectingpipingorbottomcasing.Thepumpandmotorshallbemountedonafabricatedcommonsteelbaseforeasymaintenance.
1.3UNITRESPONSIBILITY
Thecontractorshallcauseallequipmentspecifiedunderthiscontracttobefurnishedbythepumpmanufacturerwhoshallberesponsiblefortheadequacyandcompatibilityofallpumpingunitcomponents.Anycomponentofeachpumpingunitnotprovidedbythepumpmanufacturershallbedesigned,fabricated,testedandinstalledbyfactoryauthorizedrepresentativesexperiencedindesignandmanufactureofsuchcomponents.Thisrequirement,however,shallnotbeconstruedasrelievingthecontractoroftheoverallresponsibilityforthisportionofwork.
1.4DesignRequirements
ThearrangementsshownonthedrawingsarebaseduponthebestinformationavailabletotheEngineeratthetimeofdesignandisnotintendedtoshowexactdimensionspeculiartoanyspecificequipmentunlessotherwiseshownorspecified.Therefore,itmaybeanticipatedthatthestructuralsupports,foundations,connectingpipingandvalvesshowninpartorwhole,mayhavetobechangedinordertoaccommodatethepumpingequipmentfurnished.Noadditionalpaymentwillbemadeforsuchchanges.AnysuchchangesshallbesubmittedtotheEngineerforhisapproval.
Pumpingunitsshallbedesignedtooperatewithoutoverloadingcavitationsordamagingvibrationatthespecifiedspeed,flowandheadconditions.Theshutoffheadoftheproposedpumpsshallbeatleast10%morethanthespecifiedheadatthespecifiedcapacity.
Motorratingshallbeatleast10%morethanthepowerrequiredbythepumpatthespecifieddutypointincaseofpumprunningsolo.Incaseofpumpsrunningparallel,ratingofeachmotorshouldbehigherthanthemaximumcapacityrequiredbyeachpump.
Thepumpbaseshallbedesignedforanchorboltingtoaconcretefoundation,assumingthatthepump,withoutrestraintatthesuctionanddischargeconnections,issubjectedtoadisplacingforceequaltothatdevelopedbyaninternalpressureequaltothreetimesshut-offheadattheoperatingspeed.
Themotorshallbeconnectedtothepumpbyasemiflexiblecoupling.
Thecompletepumpingunitshallbedesignedtooperatewithoutoverloadonanycomponentatanypointalongthepumpcurveatthespecifiedspeed.
1.5CRITICALSPEEDS
Eachcompletesystem,includingpump,motorandallappurtenances,shallhavenodangerouscriticalorresonancefrequenciesormultiplesofresonancefrequencieswithin20%aboveand35%belowtheoperatingspeedofthepump.
Forthepurposesofdesign,adangerousvibratorycriticalspeedshallbedefinedasone,whichproducesatorsionstressexceeding2.4x107Nm-2.Thecontractorshallberesponsiblefortheanalysisofcriticalspeeds,whichshallbeanalyzedandcertifiedbyaprofessionalengineerregularlyengagedinthistypeofwork.
1.6FACTORYTESTING
1.6.1Materials
Meltandstrengthtestsofthecastironusedinthemanufactureofthepumps’majorcomponentsshallbeperformedinaccordancewiththeapplicableBSstandardsasindicatedinthespecification.ThecontractorshallfurnishtheEngineerwithcertifiedcopiesoftheresultsofalltests.
1.6.2PerformanceTests
PumpshallbefactorytestedforperformanceinaccordancewithISO9906byatestingagentapprovedbytheEngineerandshallbetoaccuracyclassC.Thesuppliershallsubmitthesetestcurvespriortoshipmentoftheequipment.ThesetestcurvesshallincludeHead,Efficiency,PowerabsorbedandNPSHrequiredagainstCapacity.TheEngineershallwitnessthesetests.
Pumptobesuppliedunderthiscontractwithmotorshigherthan30kWshallbetestedwithitsdistinctivecontractmotor.
1.6.3HydrostaticTests
Eachpumpshallbehydrostaticallytested.Testpressureshallnotbelessthantwicetheshut-offheadasshownontheapprovedhead-capacitycurve.
Thetestprocedureshallbeasfollows:
Condition
Time(Minutes)
1TestPressure
180
2Atmospheric
05
3TestPressure
15
4Atmospheric
05
5TestPressure
30
Atnotimeduringthistestshallthecasingshowunduedeflectionorsignsofweaknessatanypoint,norshalltheexternalsurfacesofthecasingshowsweatingthroughporousmetalorleakingthroughgasketorcracksorotherdefects.
ThecontractorshallfurnishtheEngineerwithcertifiedresultsofthetests.
1.6.4VibrationTests
VibrationtestsshallbecarriedoutinaccordancewithISO2372–1974.
1.6.5MotorTests
MotorshallbetestedinaccordancewithNEMAandIEEEProcedures.Thetestsshallinclude,
a.RoutineTests
i.Noloadcurrent
ii.LockedRotorCurrent
iii.WindingResistance
iv.HighPotentialTest.
b.CompleteTests
i.RatedLoadTemperatureRise.
ii.Slip.
iii.LockedRotorTorque.
iv.BreakdownTorque.
v.Efficienciesat100,75and50percentofFullLoad.
vi.Powerfactorat100,75and50percentofFullLoad.
Thecontractorshallfurnishtheallcertifiedtestresultsbeforeshipment.
1.7ENVIRONMENTALCONDITIONS
Theequipmenttobeprovidedunderthiscontractshallbesuitableforinstallationandoperationatelevationsofabout………………………….m.abovesealevelinsideweatherprotectedstructures.Outsideambienttemperaturesrangebetween………and…………….0Candwatertemperaturevariesbetween…………and………………0C.
RelativeHumidityisexpectedtorangebetween…………..and100%.Atmosphereisdusty.
1.8warranty
Thecontractorshallprovidemanufacturer’swarrantytotheemployerthattheGoodsandServicesSuppliedunderthecontractwillcomplystrictlywiththeContractandshallbefirstclassineverycaseandshallbefreefromdefects.ThesupplierfurtherwarrantstothePurchaserthatallmaterials,equipmentandsuppliesfurnishedbythesupplierforthepurposeofthegoodswillbenew,merchantableofthemostsuitablegrade,andfitfortheirintendedpurposes.Thesuppliershallwarrantthattheservicestobecarriedoutunderthiscontractwillconformtogenerallyacceptedprofessionalstandardsandengineeringprincipals.
ThiswarrantyshallremainvalidfortheperiodmentionedintheDataSheet.Afterthefinalacceptance,anypartoftheequipmentwhichfailsordoesnotgivesatisfactoryperformanceduringthisperiodofwarranty,shallbereplacedwithinthenumberofdaysasmentionedintheDataSheetfromthedatetheContractorhasbeennotifiedtodoso.
Allexpensesinvolvedinthisconnectio
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 15 卧式双吸泵Horizontal Shaft Driven Double Suction Pumps 卧式 双吸泵 Horizontal
链接地址:https://www.bdocx.com/doc/25394880.html