中标工程英文技术标
Range and goal
The quality planning regulates the quality management of the engineering project. It applies to basic phases of the earthwork construction, the groundwork construction, and the management of “Beijing TV Center Project”. The goal of the quality planning is to guarantee the quality goals that the customers and engineering conductor put forward.
2Referenced standard, definition and quality system
2.1 Referenced standard
2.1.1The paper of inviting public bidding
2.1.2The blueprint and design criterion
2.1.3Current national standard and criterion
2.1.4The quality guarantee pattern of production, installation and service in the quality system(GB/T19001-2000)
2.2 Definition
The quality guarantee intends to adopt the glossaries and definitions in GB/T19001-2000 The Foundation of Quality control System and Glossaries and the concerned definitions in the company’s Quality Planning.
2.3 The contents in the quality guarantee system
2.3.1 Quality goals of the engineering project
●Keep effective implementation of the quality system;
●The eligibility rate of subentry engineering should reach 100%,while the choiceness rate should be at least 70%.
●The eliminating rate of the quality common fault should reach 80%;put an end to serious quality accident,eliminate common quality accident, try to set up high quality project.
●Improve the quality guarantee system continuously; insure at least 80% of the customers satisfy.
2.3.2 Quality policy
Everyone participates; make high quality products; standardize construction; Insure that the productions satisfy the demands of concerned national and trading laws.
Keep promises; consumers first; ameliorate continuously; set up high quality engineering; meet customers’ needs continuously.
3Organization and responsibility
According to the standard items in GB/T19001-2000,the company established and consummated the organization and all the functional parts. The standard items are required to apply to corresponding posts and branches. At the same time, we give the following regulations to the posts and branches in charge of primary quality responsibilities for their specific responsibility and popedom.
●Project manager
1)The project manager should organize the implementation of national laws,technology criterions and standards, the superiors and customers’ demands. He should also organize the implementation of the enterprise’s papers of quality management system。
2)The project manager should implement the enterprise’s quality policy, goals and papers earnestly. He should consummate the administrant regulations of the project manager department step by step. He needs to nail down the quality responsibilities, check up the implementation of the quality goals, and organize mass quality activities.
3) The project manager takes charge of constituting quality planning,construction organizing device scheme, and construction technique measures. He is responsible for dividing the work,and enhancing the related persons’ consciousness of meeting the customers and laws’ needs.
4). The project manager is responsible for the contract and related agreements signed by the enterprise and clients. He should take part in the judging of the contract, and carry out the contract strictly.
5)The project manager constitutes the construction schedule and organizes the construction. He presides over the arrangement of manpower, material and equipments on the spot. He should organize the safety inspection of the construction.
6)The project manager organizes the quality inspection of the project and presides over quality analysis meeting of his department.
7)The project manager should accept the unqualified items raised by the auditing group, constitute ameliorating measures, and bring them into effect after authorization.
8)The project manager must master the statistical technique and reach the requests in the 8.4th chapter of the handbook.
9)The project manager should abide by the quality agreements in the engineering contract and the enterprise work plan. He should insure the realization of the enterprise quality goals, especially the engineering quality.
10) The project manager should accept the organ department’s quality inspection. He should report to the company’s managing department about the implementation of the quality system. He answers for harmonizing the relationship between branches and the managing department. He is also responsible for inner and outer quality auditing. He should organize and provide materials needed in auditing.
●Manufacture assistant manager
1)The manufacture assistant manager should carry out the company’s quality policy and goals. He deals with the production as a whole, organizes the activities such as constituting, examining and approving annual and monthly production plan. He is responsible for the implementation of the enterprise quality policy and the entire realization of the quality goals.
2)The Quality Function Distribution Table in Quality Handbook decides the requirements of the managing department and the quality guarantee system. The manufacture assistant manager should conform to the requirements. He should develop quality control system, master the quality circumstances during the construction, find out the operational status of quality control system, detect questions, then let related branches dispose them in time, and supervise the disposal status. He should accept inner quality auditing report, take part in the management evaluation, and report to the supervisor commissary about the operational status of the quality system.
3)The manufacture assistant manager should establish perfect safe production administrant regulation. He is responsible for harmonizing enterprise’s work force, materials and mechanical facilities. He should organize the construction and production in reason and urge engineering project to be brought into effect favorably according to the plan. He should insure effective implementation of the quality system papers.
4)The manufacture assistant manager should arrange the production resources in reason,and take the leading responsibility for safe production directly. He should provide production resources,create favorable production environment, boost the related departments’ consciousness of meeting the customers and laws’ needs,refrain deeds of neglecting quality,and charge the item department to shutdown and reform the items fall short of quality demands.
5)He should organize check and accept after the project completes.
●Chief engineer
1)The chief engineer answers for technique administrant task of the engineering project.
2)The chief engineer leads the work of constituting Construction Organizing Devise and Construction Scheme. He supervises the implementation as well.
3)The chief engineer answers for technique questions.
4)The chief engineer organizes the beforehand inspection of the engineering project.
5)The chief engineer organizes the work such as scale, inspection, experimentation, computation, and the protection of the environment.
6)The chief engineer answers for the devise alteration and engineering palaver.
7)The chief engineer organizes the work of collection, clearing up, and sorting the technique resources.
8)The chief engineer is responsible for popularizing new technologies, new techniques, new materials, and summarizing the work.
●Chief economic master
1)He answers for financial affairs and economic accounting. He is responsible for realizing the quality policy and goals. He organizes constituting financial affairs managing method.
2)He answers for constituting annual financial plan and managing financial affairs according to the contract.
3)He organizes and supervises financial system to do cost accounting and clear off the debts.
●Technique quality department
1)The department implements concerned national laws and the customers’ requests. They carry out quality policy and goals constituted by the company. They answer for constituting the company’s science and technology scheme. They are responsible for popularizing new techniques, new projects, and new materials.
2)They should supervise and control the project quality outright, collect the information of rejected products, and report the quality operational status to the managing leader.
3)They constitute administrant method of the engineering quality and study out annual quality control plan for the enterprise.
4)They supervise the project quality according to concerned laws and assessing criterions. They direct the inspection of the project quality, which is implemented by project conductor department (water and electricity section, crane and loading section).
5)They collect, clear up and feed back the information of the project quality. When serious quality problems appear, they report to the chief engineer. They collect, clear up and manage the input and output data of the quality analysis meeting. They tail after the implementation of defending and ameliorating measures constituted by the meeting .
6)They answer for constituting managing measures of the construction. They organize the auditing of Construction Organizing Devise and Construction Scheme. They constitute currently effective listing for concerned laws, statute, technique criterion, project, and drawing. Then they put out the listing and manage it.
7)They are responsible for managing, measuring and surveillance. They should manage the work such as scale, experimentation, and computation. They should also direct and manage the application of statistical techniques.
8)They take part in the inspection before the project completes, the final acceptance, and interview the customers. They inspect the construction data. Following tasks should also be taken:
examine and approve, pigeonhole, handover the data about the completed construction. They take part in the final acceptance for