城市支路施工组织设计.docx
- 文档编号:23672744
- 上传时间:2023-05-19
- 格式:DOCX
- 页数:71
- 大小:66.10KB
城市支路施工组织设计.docx
《城市支路施工组织设计.docx》由会员分享,可在线阅读,更多相关《城市支路施工组织设计.docx(71页珍藏版)》请在冰豆网上搜索。
城市支路施工组织设计
第一章工程概况...........................................................................................................................1
一、工程概述...............................................................................................................................1
二、设计概况...............................................................................................................................1
三、工程施工特点.......................................................................................................................3
第二章编制依据及编制原则.......................................................................................................4
一、编制依据...............................................................................................................................4
二、编制原则...............................................................................................................................6
第三章准备工作...........................................................................................................................7
一、技术准备...............................................................................................................................7
二、资源准备...............................................................................................................................8
三、施工现场准备.......................................................................................................................8
第四章组织机构和人员配备.....................................................................................................10
一、组织机构保证体系.............................................................................................................10
二、主要施工管理人员安排......................................................................................................11
三、项目部规章制度和各主要职能负责人的职责.................................................................13
第五章施工方案、方法.............................................................................................................20
一、施工方案.............................................................................................................................20
二、施工方法.............................................................................................................................20
(一)、排水工程施工..................................................................................................................20
1、沟槽开_020
2、管道安_021
3、井室砌_122
4、闭水试_223
5、沟槽回_323
(二)、道路工程施工..................................................................................................................25
1、路床工_525
2、路面基层施工.......................................................................................................................25
2.1天然砂砾石基层施工...........................................................................................................25
2.2水泥稳定砂砾上基层施工.............................................................................................28
3、砼路面施工...........................................................................................................................31
3.1工艺流程图:
......................................................................................................................31
3.2操作要点..............................................................................................................................31
(三)、人行道施工......................................................................................................................39
1、8%石灰砂土基层..................................................................................................................39
2、路缘石的施工.......................................................................................................................40
3、嵌边石的施工.......................................................................................................................41
4、人行道砼块铺筑...................................................................................................................41
(四)、盲道铺装..........................................................................................................................42
第六章质量控制及保证措施.....................................................................................................43
一、质量控制目标.....................................................................................................................43
二、质量控制措施.....................................................................................................................44
第七章施工总平面布置.............................................................................................................64
一、施工总平面布置的原则.....................................................................................................64
二、基地建设.............................................................................................................................64
三、水、电、交通.....................................................................................................................65
第八章工期及施工进度计划.....................................................................................................66
一、施工进度计划表.................................................................................................................66
二、施工进度控制.....................................................................................................................66
三、工期的保证措施.................................................................................................................67
第九章劳动力安排计划.............................................................................................................71
第十章施工机械配置.................................................................................................................72
一、拟投入本合同的主要施工设备.........................................................................................72
二、拟配备本合同工程的主要试验、测量、质检仪器设备表..............................................72
第十一章安全控制措施.............................................................................................................73
一、安全保证体系.....................................................................................................................73
二、安全施工保证措施...........................................................................................................78
第十二章文明施工和环保控制措施.........................................................................................85
一、文明施工.............................................................................................................................85
二、环境保护措施.....................................................................................................................87
第十三章季节性施工措施........................................................................................................96
第十四章配套管线之间的配合.................................................................................................99
一、建立施工协调管理制度.....................................................................................................99
二、与配套管线工程施工单位的协调与配合.......................................................................102
第十五章各种图表...................................................................................................................104
拟投入的主要施工机械设备表表...........................................................................................105
拟配备本合同工程的主要试验、测量、质检仪器设备表...................................................106
劳动力计划表表.......................................................................................................................107
施工总平面布置图表..................................................................................错误!
未定义书签。
计划开、竣工日期和施工进度计划横道图表.......................................................................108
第一章工程概况
一、工程概述
本标段工程为某A街、楞伽街、某C街道路整治工程。
某B街起点位于某A街,道路由西向东终点与银丝街相交,道路总长
度186.03米。
道路红线宽度14米,其中9米车行道,两边各2.5米人行道。
某C街西起银丝街,道路由西向东终点与草市街相接,道路总长度171.61米。
道路红线宽度14米,其中9米车行道,两边各2.5米人行道。
某A街道路西起红石柱街,道路由南向北终点与五岳富街相接,道路总长度185.12米。
道路红线宽度12米,其中7米车行道,两边各2.5米人行道。
工程施工区为市区,小灵通、手机信号都很好,通讯方便,总体
而言施工条件初步具备。
二、设计概况
(一)道路工程
1、设计参数
道路类别:
城市支路
道路级别:
Ⅱ级
设计车速:
20Km/h
路面结构类型:
沥青混凝土面层。
设计使用年限:
15年
2、横断面设计
本工程断面为:
路面为4cmAC-13-I细粒式改性沥青混凝土,6cmAC-20-I中粒式沥青混凝土,20cm5%水泥稳定砂砾上基层,30cm的天然砂砾下基层。
(二)排水工程
管材:
当管顶覆土0.7 水管,管道接口采用橡胶圈接口。 管道基础: 当管顶覆土0.7 雨 水管道地基承载力不小于100KPa。 雨水检查井: 采用φ1000圆形检查井,车行道下的检查井采用重型井 盖及井座,人行道下的采用轻型井盖及井座。 道路雨水口: 均采用单篦雨水口,连接管道为d200,坡度为1%。 雨 水口篦子为铸铁篦子。 本工程,每条街均规划设计雨水管道一条。 某B街、某C街雨水管道 位于规划道路中线北侧3米;雨水由西向东排入草市街雨水管道。 某A街雨水管道位于规划道路中线西侧2米;雨水由北向南排入红石柱街雨水管道。 三、工程施工特点 根据施工招标文件的要求,参照设计图结合现场踏勘的情况本工程 的施工特点如下: 1、本工程的施工期跨今年夏季,7、8月份正是成都地区的雨季, 也是最热的时候,所以在施工进度计划安排时,应尽可能赶在大雨来临前完成所有道面以下工程。 雨季施工时应作好排水工作;夏季施工砼工程时应作好洒水养护工作。 2、本工程排水管设计使用管材为钢筋混凝土承插管。 第二章编制依据及编制原则 一、编制依据 本施工组织设计是根据XXX招标代理公司提供的施工招标文件 和施工设计图、工程量清单及答疑书,结合现场踏勘情况和我单位在 类似市政工程的施工经验进行编写。 (一)、《某A街、楞伽街、某C街道路整治工程招标文件》和 施工设计图、工程量清单及答疑文件。 (二)、根据现场踏勘所获的有关地形、水文、地质、交通、用水、 用电等资料。 (三)、依照有关主要法律、法规: 1、《中华人民共和国建筑法》 2、《中华人民共和国招标投标法》 3、《成都市建筑管理条例》 4、国务院令279号《建设工程质量管理条例》 5、成建委发[2002]280号《关于全面开展创建“绿色环保工地” 活动中的实施意见的通知》 6、成建委发[2002]287号《关于印发〈成都市建筑市场主体不良 行为记录、扣分、公示与处理暂行办法〉的通知》 7、《创建国家环境保护模范城市活动中实施四项专项整治工程的 通知》 8、《成都市建筑工程夜间施工管理执行办法》 9、成都市人大2004年4月27日公布的《成都市建筑施工现场 监督管理规定》 (四)、有关国家、行业、部颁标准的技术规范、规程及技术标准: 1、《市政排水管渠工程质量检验评定标准》CJJ3—90 2、《联锁型路面砖路面施工及验收规程》CJJ79—98 3、《给水、排水管道工程施工及验收规范》GB50268-97 4、《预制混凝土构件质量检验评定标准》GBJ321-90 5、《建筑施工安全检查标准》JGJ59-99 6、《建筑机械使用安全技术规程》JGJ33-86 7、《工程测量规范》GB50026-93 8、《城市道路路基施工及验收规范》CJJ44-91 9、《市政道路工程质量检验评定标准》CJJ1-90 10、《市政桥梁工程质量检验评定标准》CJJ2-90 11、《建设工程施工现场供用电安全规范》GB50194-93 11、《公路桥涵施工技术规范》JTJ041-2000 13、《混凝土结构工程施工质量验收规范》GB50204—2002 14、《砌体工程施工质量验收规范》GB50203—2002 15、《水泥混凝土路面施工及验收规范》GBJ97—87 16、《城市道路照明工程施工及验收规程》CJJ89-2001 17、《道路交通标志和标线》GB5768—1999 二、编制原则 (一)、严格遵循《施工招标文件》规定的内容,达到设计文件的 标准,充分体现业主的要求。 (二)在仔细考察工程实地、认真研究招
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 城市 支路 施工组织设计