储水罐厚竖井烟道吊装资料
作业指导书
工程名称:
内蒙古大唐国际托克托电厂五期扩建工程
编号:
X-030
作业项目名称:
#10机组储水罐、后竖井烟道吊装作业
编制单位:
中能建江苏省电力建设第一工程有限公司大唐托电项目部
编写:
日期:
审核:
日期:
审定:
日期:
日期:
批准:
日期:
出版日期:
版次:
第一版
目录
1适用范围·······························································2
2编制依据·······························································2
3主要工程量·····························································2
4组织机构和作业人员的资格要求···········································2
5主要机械及工器具·······················································4
6施工进度·······························································4
7施工准备·······························································4
8作业程序·······························································5
9作业方法、工艺要求及质量标准···········································5
10相关计算··························································11
11工序交接及成品保护····················································14
12安全和文明施工措施····················································14
13强制性条文····························································14
14应急处置方案··························································15
附表:
重大危险源/重要环境因素控制计划表···································19
1适用范围
本作业指导书适用于指导和实施我公司承建的内蒙古大唐国际托克托电厂五期扩建工程#10机组储水罐、后竖井烟道吊装作业。
2编制依据
《中华人民共和国安全生产法》中华人民共和国主席令第70号《特种设备安全法》2014年1月1日起施行《中国能源建设股份有限公司起重机械安全监督管理办法》中能建股发生产160号
《起重机械安全规程》GB6067.1—2010
《特种设备作业人员监督管理办法》国家质量监督检验检疫总局令第140号
《起重机械监督检验规程》国家质量监督检验检疫总局
《大唐托克托电厂五期扩建工程第二标段施工组织设计》江苏电建一公司
《起重机械安全规程》GB6067.1—2010
《电力建设安全工作规程》火力发电厂部分DL5009.1-2014
《储水罐安装图》
《后竖井烟道安装图》
《CC2500(450t)履带吊使用说明书》
《1380(63)塔吊使用说明书》
《起重机设计手册》
3主要工程量
序号
吊装项目
尺寸
就位位置
吊装总重量
吊车工况
1
后竖井烟道
22492mm×9464mm
中心对齐G5轴线、偏K5轴线3m,就位高度为37m
144t
SWSL工况、78m+24m
2
储水罐
890mm×19750mm
偏G3轴线2.92m、偏K1轴线2.5m,就位高度为54.47m
45t
SWSL工况、78m+42m
4组织机构和作业人员的资格要求
4.1组织机构
以江苏电建一公司大唐托克托项目部为依托,按照以下表格内要求抽调专业骨干实施作业。
为保证吊装安全,特成立“大唐托克托项目部#10机组储水罐、后竖井烟道吊装”专项组织机构,见下表:
序号
姓名
分工
职务/职称
1
吕从军
吊装总负责人
副经理/高工
2
翁庆松
现场安全管理
安全科长
3
李安保
吊装区域安全监督
安全员
4
丁兴宏
吊装机械安全监督
机修工地安全员
5
毕正斌
安装负责人
机炉工地主任
6
孙逸诚
施工协调
工程科科长
7
邓海雄
吊装负责人
机修工地主任
8
陆茂生
起重总指挥
机炉工地起重班长
9
林大亮
方案编制、技术指导
机修工地专工
10
丁庆涛
现场应急预案准备
办公室主任
4.2劳动力计划和作业人员的资格要求
序号
工种
技术等级
数量
特殊工种上岗证
备注
1
电工
中级工
1
电工证
监护现场供电
2
钳工
中级工
2
监护履带吊
3
起重指挥
中级工
2
起重指挥证
吊装指挥
4
起重司索
初级工
4
起重司索证
吊装司索
5
操作工
中级工
3
起重机械操作
操作起重机械
6
安装工
初、中级工
4
安装设备
7
架子工
初、中级工
4
架子工证
7
安全员
2
安全员证
安全监护
8
电风焊工
中级工
2
焊工证
加固焊接
9
总指挥
高级工
1
协调吊装作业
10
技术员
中级
1
措施、技术交底
5主要机械及工器具
序号
名称
规格型号
数量
备注
1
履带式起重机
450t
一台
吊装
2
塔式起重机
63t
一台
吊装
3
卸扣
25t
4只
4
千斤绳
6×37-170-φ65mm
2对
48m
5
钢丝绳
6×37-170-42mm
2对
12m
6
溜绳
60m
2根
7
风焊工具
2套
8
链条葫芦
5t
若干
9
卷尺
5m
若干
6施工进度
预计03月底开始吊装后竖井烟道,04月初吊装储水罐。
7施工准备
7.1履带吊工作场地准备:
锅炉钢架验收合格,扩建端、炉后场地平整、压实后铺好路基板,满足履带吊作业。
7.2吊车准备
CC2500(450t)履带吊SWSL工况,接78m主臂、24m副臂、配重120t、超级配重60t,超起半径15m、超起副臂30m。
履带吊幅度工况性能如下表。
幅度m
18m
20m
22m
24m
起重量t
95
93
90
87
CC2500(450t)履带吊SWSL工况,接78m主臂、42m副臂、配重120t、超级配重60t,超起半径15m、超起副臂30m。
履带吊幅度工况性能如下表.
幅度m
26m
28m
30m
34m
起重量t
61
60
58
55
1380塔式起重机幅度10m-22m,起重量为63t。
7.3现场条件准备
7.3.1环境准备
i灭火器等器材已定址放置。
ii施工电源布置完成。
iii通道畅通,光线充足,安全设施工作状态良好,氧乙炔供应充足。
iv安装区域平台完善,格栅板铺设完毕,预留孔洞装设盖板,无妨碍施工的任何物品。
7.3.2安全条件
i设立临时警戒区域,派专人监护,无关人员不得入内。
ii吊装、托运用具、支座滚柱必须检查应满足安全使用要求。
iii安全防护设施及安全用具(安全带等)必须符合安全使用要求。
iv所有参加作业人员必须经过三级安全教育,高空作业人员必须经过体检合格后方可参加作业。
作业前必须对所有参加人员进行安全、技术和质量交底。
8作业程序
8.1后竖井烟道吊装:
锅炉钢架设施验收合格后竖井烟道分为两半450t履带吊就位使用450t履带吊将烟道转移至炉后吊装位置450t履带吊吊装烟道找正安装就位
8.2储水罐吊装:
锅炉钢架设施验收合格450t履带吊就位使用1380塔吊将储水罐转移至扩建段吊装位置450t履带吊吊装储水罐找正安装就位
9作业方法、工艺要求及质量标准
9.1后竖井烟道吊装;
9.1.1后竖井烟道吊装时一分为二,分解后的烟道总重量为75t,钢丝绳钩头重约5t,吊装总重量为80t,由450t履带吊单机吊装就位。
吊装时,450t履带吊接78m主臂、24m副臂,配重120t,超起半径15m、超起副臂30m,回转半径20m,最大起重量93t,负荷率约86.02%,满足要求。
9.1.2第一步:
按照下图,450t履带吊铺好走道板,放置好超起配重450t履带吊生钩于烟道的吊耳上,检查起重机械及钢丝绳卸扣无误后,缓慢起吊烟道离地面约10cm时应暂停起吊并进行全面检查和试验刹车,确认正常后方可进行下一步。
第二步:
450t履带吊缓慢向右回转,待回转至烟道正对K5轴线时,停止回转。
第三步:
450t履带吊幅度不变,缓慢起吊,待烟道下地面超过G4/K5柱头(柱头标高40m)时,停止起吊。
第四步:
450t履带吊幅度不变,沿走道板方向平行G4轴线缓慢向前移动21.2m,待烟道到达就位位置上方时,停止起吊。
第五步:
找准就位中心后,450t履带吊缓慢松钩,直至烟道就位。
见下图三:
图一:
吊装立面图
图二:
起吊平面图
图三:
起吊平面图
9.2储水罐吊装;
9.2.1储水罐吊装总重量为45t,钢丝绳钩头重约4t,吊装总重量为49t,由450t履带吊单机吊装就位。
吊装时,450t履带吊接78m主臂、42m副臂,配重120t,超起半径15m、超起副臂30m,回转半径29m,最大起重量58t,负荷率约84.5%,满足要求。
9.2.1第一步:
按照下图,1380塔吊10m幅度起重量为63t,将储水罐吊运至1380塔吊以北位置,使得储水罐距离K2/G1柱头400mm,见图四,负荷率为71.4.铺好走道板,第二步:
450t履带吊24m幅度生钩于储水罐顶端,1380塔吊12m幅度生钩于储水罐底,双机抬吊将储水罐吊离地面约10cm时应暂停起吊并进行全面检查和试验刹车,确认正常后方可进行下一步。
第三步:
450t履带吊和1380塔吊双机抬吊将储水罐树立起来。
第四步:
450t履带吊带60t超起,幅度不变,缓慢起吊,待储水罐下端超过锅炉钢架时,停止起吊。
第五步:
450t履带吊幅度不变,沿走道板方向缓慢向前移动10.7m,停止移动。
第六步:
450t履带吊缓慢变幅至29m,使得储水罐到达就位位置上方,找准就位中心后,缓慢松钩。
见下图五。
图四:
储水罐转移位置平面图
图五:
储水罐起吊平面图
图六:
储水罐吊装图
9.5施工过程要求。
施工作业人员必须按图纸、有关规程规范和作业指导书要求进行施工。
在施工过程中对有疑问不清楚之处及时反馈给施工总指挥,不得盲目施工。
在施工过程中如发现问题需立即向技术人员及现场指挥人员汇报,不得擅自施工。
10相关计算
10.1钢丝绳校核
10.1.1在吊装过程中后竖井烟道净重75t,履带吊选用6×37+FC-1870-φ65mm千斤绳破断拉力T=254t。
千斤绳起吊夹角220(见下图七),则钢丝绳单根受力:
N=75/(4·COS17º)
=75/(4×0.98)=19.2t
吊装钢丝绳的安全系数K,K=T/N=254/19.2=13.2>8满足要求。
10.1.2在吊装过程中后储水罐净重45t,履带吊选用6×37+FC-1870-φ42mm千斤绳破断拉力T=254t。
千斤绳起吊夹角220(见下图七),则钢丝绳单根受力:
N=45/(4·COS4º)
=45(4×0.99)=11.3t
吊装钢丝绳的安全系数K,K=T/N=103/11.3=9.1>8满足要求。
图七:
钢丝绳夹角示意图
10.2吊耳的设计
后竖井烟道采用四只吊耳起吊作业,每只设计负荷40t,吊具布置如图八上部所示。
本章计算使用公式根据《起重机设计手册》第三篇-第四章-第四节所示公式引用。
大板梁吊具应力校核
i、吊耳部分应力校核(按单吊耳40t承载能力计算,吊耳尺寸如下图八)采用钢材Q345,厚度30mm,[σ]=325Mpa
吊耳危险截面A-A拉应力应满足
σ拉A=Qaj/2[(b-d)Σδ]≤[σ]/1.7
=40×104×2.3/2(350-70)×30
=54.8Mpa≤[σ]/1.7=325/1.7=191Mpa
aj=2.3---安全系数
b=350---有效承载宽度
d=70---开孔直径
Σδ=30---有效厚度
上述参数在本节中以下计算同样适用。
图十一:
吊装吊耳设计图
吊耳危险截面B-B拉应力(切向)应满足
σ=Q(h2+0.25d2)/2[d(Σδ)(h2-0.25d2)]≤[σ]/3
=40×104(1352+0.25×702)/2[70×30(1352-0.25×702)]
=95Mpa≤[σ]/3=325/3=108Mpa
吊耳轴孔处平均挤压应力应满足
σ=Q/2d(Σδ)≤[σ]/3
=40×104/2(70×30)=95.2Mpa≤[σ]/3=325/3=108Mpa
ii、焊缝强度校核(焊缝类型为受拉开坡口正面角焊缝,母材为Q345;焊缝截面及要求如下图10表所示)。
1、要求焊缝金属强度极限不低于吊耳母材金属强度极限。
2、所使用焊条要求于母材相匹配。
3、焊后需无损检测(着色),并且检验结果合格。
接头类型
坡口形式
图形
焊接
方法
焊件厚度
a
b
p
要求
T型接
K型
Ds
30
450
0
10
(图表内各项数据依据火力发电厂焊接技术规程DL/T869-2012)
根据以上条件,对焊缝强度计算如下;
由σjb=[(4P2+K2)/3(P2+K2)]1/2·σwb
a——(5+5)sin450,P=K=5mm如下图所示,a=7mm(焊缝高度);
图十二:
焊缝剖面示意图
σjb——接头强度极限,σjb=0.91σwb=295.8Mpa
σwb——焊缝金属强度极限值,取σwb=325Mpa(焊缝金属强度极限不低于吊耳母材金属强度极限)。
又有P/2al≤[σ’l]/ββ0
l—跨距,l=350mm
[σ’l]——焊缝金属材料许用应力,取[σ’l]=σjb;
β——因母材屈服限σs而变的系数,查得β=0.8;
β0——焊缝角度的函数,查得β0=1.58。
综合以上所叙得[σ’l]2al/ββ0=295.8×al/ββ0
[σ’l]=295.8×7×350×2÷(0.8×1.58)
[σ’l]=114.7t>P=40t
以上计算各式依据——《焊接结构》机械工业出版社,第三章3-3。
计算结果说明焊缝连接可靠,可以使用。
11工序交接及成品保护
储水罐吊装过程中,钢丝绳生钩过程等不得对储水罐造成损伤,做好保护,对各施工阶段所需物品应提前准备;各施工阶段结束后应核查是否达到预计效果,判断能否进行下一工序施工。
12安全和文明施工措施
12.1技术人员应在起吊作业前进行安全、技术、质量交底,交底时分公司总工、安全科、工程科、机修工地、机炉工地及甲方、监理有关人员到场,起吊前应开好安全作业票。
12.2划定工作区域,并派专人监护,无关人员不得入内,不得在危险区域内逗留或通过。
现场吊装应由专人指挥,指挥信号应统一,分工明确,信号清楚。
12.3后竖井烟道吊装前,必须先将临时就位的锅炉钢架安装检验合格,保证后竖井烟道顺利就位。
12.4因现场情况复杂,现场施工区域内应清理干净、清理与施工无关的杂物。
12.5起吊用索具必须检查,确保索具合格后再进行作业。
起吊前认真检查吊机,尤其是力矩限制器及各限位等安全装置,以保证机械机况的完好。
12.6起吊、行走回转及脱钩等过程一定要缓慢,特别注意工序步骤的衔接。
12.7施工过程中要有专人监护吊机卷扬机。
12.8高空作业施工人员必须系好安全带,并牢固地挂在施工作业区的上方牢固处。
高处作业的平台、走道、斜道等应装设由上下两道栏杆和栏杆组成的防护栏杆及档脚板,或设防护立网。
12.9高处作业所用工具必须系安全绳,传递物件禁止抛掷,设备、材料及废料临时存放在要有可靠的防止移动和坠落的措施。
12.10严格控制后竖井烟道保持水平,以免载荷分配变化。
12.11履带吊拆钩时作业人员必须挂好安全带防止高空坠落及高空落物。
12.12吊装作业完毕后,把所有工具,器具,材料和一切杂物回收分类存放,严禁污染破坏环境。
12.13发生任何意外情况,按照分公司相应应急预案处置。
12.14作业完毕必须做到“工完料尽,场地清”文明施工。
13、强制性条文:
《电力建设安全工作规程》火力发电厂部分/DL5009.1-2014
4.12.1通用规定:
1作业前应进行安全技术交底,交底人和作业人员签字。
2作业应统一指挥。
指挥人员和操作人员应集中精力、坚守岗位,不得从事与作业无关活动。
3起重机械操作人员、指挥人员(司索信号工)应经专业技术培训并取得操作资格证书。
5起重作业前应对起重机械、工机具、钢丝绳、索具、滑轮、吊钩进行全面检查。
11严禁在恶劣天气或照明不足情况下进行起重作业。
当作业地点的风力达到五级时,不得吊装受风面积大的物件;当风力达到六级及以上时,不得进行起重作业。
4.12.4起重作业应符合以下规定:
2两台及以上起重机械抬吊同一物件。
1)宜选用额定起重量相等和相同性能的起重机械。
严禁超负荷使用。
2)各台起重机械所承受的载荷不得超过本身80%的额定载荷。
抬吊过程中,各台起重机的吊钩钢丝绳应保持垂直,升降、行走应同步进行。
14应急处置方案
14.1应急保护对象:
14.1.1在后竖井烟道和储水罐吊装作业期间,如果发生人员高空坠落、高空落物伤人等人身伤害事故,应沉着冷静及时组织救援,将人身伤害程度降至最低。
14.1.2在后竖井烟道和储水罐吊装作业期间,如果发生机械设备事故,及时组织救援,将设备事故损失降至最低程度。
14.2.应急地点:
项目部应急小组办公室
14.3应急指挥机构
序号
姓名
担任职务
备注
1
吕从军
总指挥
组织指挥应急救援
2
邓海雄
副总指挥
协助总指挥负责具体指挥工作
3
黄爱国
指挥组成员
组织救援人员实施事故的应急响应
4
林大亮
指挥组成员
组织救援人员实施事故的应急响应
5
丁庆涛
救援组成员
协调医务、汽车司机等人员为主
6
翁庆松
指挥组成员
组织救援人员实施事故的应急响应
14.4应急处置方案启动
14.4.1应急处置方案启动条件:
1)在作业期间,严重威胁人身安全或已经造成人身伤害的情况下。
2)在作业期间,可能或已经造成机械设备事故的情况下。
14.4.2应急处置方案启动步骤:
1)发生紧急情况时,应立即与应急小组成员取得联系。
2)应急小组成员接到通知后,立即到应急小组办公室集中。
3)应急小组在确认紧急情况后,由应急小组指挥决定是否启动应急预案。
4)应急小组在指挥下组织对人员、机械设备实施救援。
14.5应急响应网络及方法步骤:
14.5.1网络:
突发事件
指挥小组
信息网络开通
判断响应级别
人员救助
应急资源调配
应急启动
火灾
现场指挥
救援行动
现场清理
机械设备
善后处理
应急救援
环境保护
事故调查
14.5.2方法步骤:
1)现有条件组织救援,保护现场。
2)向指挥小组成员报警。
3)人员救护向医疗救护报警,报警时说明地点,伤害程度情况,
14.5.3指挥机构职责:
1)负责应急预案的制定,组建应急救援小组,并组织实施;
2)检查督促做好重大事故的预防措施和应急救援的准备工作;
3)发生重大事故时,由指挥机构发布和解除救援命令,组织救援队实施救援行动;
4)向上级汇报,组织事故调查;
5)总结应急救援经验、教训。
14.7450t履带吊吊装后竖井烟道性能表
14.8450t履带吊吊装储水罐性能表
14.81380塔吊性能表
R(m)
6.5~10
10~22
23
24
25
26
27
28
29
30
Q(t)
30
63
59.6
55.9
52.8
50.3
47.9
45.5
43.4
41.3
R(m)
31
32
33
34
35
36
37
38
39
40
Q(t)
39.5
37.7
36.1
34.5
33.1
31.6
30.4
29.1
28.0
26.8
R(m)
41
42
43
44
45
46
47
48
49
50
Q(t)
25.8
24.7
23.8
22.8
22.0
21.1
20.3
19.5
18.8
17.16
附表1
中国能源建设集团江苏省电力建设第一工程有限公司
大件吊装危险源辨识与风险评价表
工程项目:
内蒙古大唐国际托克托电厂五期扩建工程机组号:
#10作业名称:
#10机组储水罐、后竖井烟道吊装作业
序号
作业活动
危险因素
可能导致的事故
作业条件风险性评价
风险级别
L
E
C
D
1
#10机组储水罐、后竖井烟道吊装作业
吊装高空作业多,可能高空坠落及物体打击事件
人员伤害、钢梁损坏
1
3
3
9
1
2
违章指挥
钢梁坠落、机械损坏
1
3
3
9
1
3
高处行走可能高空坠落
人员伤害
3
3
7
63
2
4
机械误操作
人员伤害、钢梁损坏
1
3
15
45
2
5
吊耳、索具断裂
人员伤害、机械损坏
1
3
3
9
1
6
吊车超载
人员伤害、机械损坏
3
3
15
135
3
附表2
中国能源建设集团江苏省电力建设第一工程有限公司
大件吊装危险源辨识控制措施
工程项目:
内蒙古大唐国际托克托电厂五期扩建工程机组号:
#10作业名称:
#10机组储水罐、后竖井烟道吊装作业
序号
作业活动
危险因素
可能导致的事故
控制措施
责任单位/责任人