PROJECT EXECUTION PLAN PEP项目执行计划英文版Word文档格式.docx
《PROJECT EXECUTION PLAN PEP项目执行计划英文版Word文档格式.docx》由会员分享,可在线阅读,更多相关《PROJECT EXECUTION PLAN PEP项目执行计划英文版Word文档格式.docx(26页珍藏版)》请在冰豆网上搜索。
5.2Consultation
5.3Procurement
5.4Construction
5.5Commissioning,OperationandMaintenance
6.ProjectControls
6.1ChangeControl
6.2Programme
6.3Cost
6.3.1CostPlanning
6.3.2CostReporting
6.3.3InvoicingProcedure
6.3.4Risk
6.4Quality
6.4.1Definitionofstandards
6.4.2SiteControlsandInspection
6.4.3DefectsRectification
6.5OrganisationandAdministration
6.5.1ProjectFilingSystem
6.5.2Meetings
6.5.3ProjectProgressReporting
6.6HealthandSafet
Thepurposeofthisdocumentistodefineallproceduralmattersrelatingtothedesign,procurementandconstructionoftheproject.ThisdocumentshouldbereadinconjunctionwiththeUniversityofLeedsProjectManagerHandbook.
TheProjectExecutionPlan(PEP)ispreparedbytheProjectManagerinconsultationwiththeclientandtheProjectteam.Itdescribesthegeneralprocedurestobeadoptedbytheclientandtheteamfortheproject.
ThePEPisnotastaticdocument.Itshouldberegularlyupdatedbyeachteammember,althoughallrevisionswillbeissuedthroughtheProjectManagertoretainanelementofcontrol.
TheobjectivesofthePEParetoachievetheclient’srequirementsintermsoftime,costandqualityvia:
∙GuidingtheProjectteammembersintheperformanceoftheirduties
∙Monitoringandcontrollingprojectprogrammeanddelivery
∙Maintaininganadequateandtimelyflowofcriticalinformation
Thedocumentissplitintothefollowingsections;
1.TheUniversityofLeedsProjectManagerHandbook
2.Projectobjectivesandpriorities
3.Organisation,rolesandresponsibilities
4.Projectstrategy
5.Projectcontrols
TheUniversityundertakesawiderangeofmaintenanceandnewbuildprojectsandhasdevelopeda
UniversityofLeedsProjectManagerHandbookforuseon
Universityconstruction
projects.Ateachstageoftheprojectthehandbookshouldbereferredtoforguidanceandsupport.Withinthehandbookisaseriesofprocesseswhicharesupportedbyarangeofproceduresandtemplates.Eachprojectalsohasasetofeightgatewayreviewsthatmustbesignedoffbytherelevantpartiesbeforeaprojectcanproceedtothenextstage.
ProjectProcesses
Theprocesseshavebeendevelopedtocoverthetasksthatareundertakenduringeachofthesixprojectlifecyclestages:
FeasibilityOptionAppraisal(RIBAStageA/B)
OutlineProposals(RIBAStagesC)
DetailProposals(RIBAStagesD,E)
Tender(RIBAStagesF,H)
Construction(RIBAStagesJ,K)
PostProject(RIBAStageL)
3.ProjectObjectivesandPriorities
Client’sbriefanddesigncriteria
Summaryofprojectaims
Summaryoflocation,generalarrangementsandanysiteconstraints
ApprovalStage
ApprovalSignoffDate
Gateway1Approval–PrimaFacieBusinesscaseSignoff
Gateway2Approval–FullBusinessCaseSignoff
Gateway3Approval–FundingGranted
Gateway4Approval–StageA/BSignOff
Gateway5Approval–StageCSignOff
Gateway6Approval–StageD/EsignOff
Gateway7Approval–TenderReportApproval
Gateway8Approval-Completion
CurrentApprovedProgramme
Location:
CurrentApprovedBudget
4Organisation,RolesandResponsibilities
Thenames,address,telephonedetailsofalltheorganisationsinvolvedintheprojectareincludedwithintheprojectdirectory.(ReferenceTemplate–ProjectDirectory)
4.2KeyContacts
TheProjectTeam
Theprinciplepartiesinvolvedwiththeprojectare:
ClientLiaisonOfficer:
Mobile
EstatesProjectManager:
Mobile
ExternalProjectManager:
QuantitySurveyor:
Mobile
Tel
Architect:
M&
EServicesEngineer:
StructuralEngineer:
Mobile
CDMConsultant:
MainContractor:
4.3DesignTeamTendersReceivedandAccepted:
Required
Received
Action
ProjectManager
Architect
EEngineer
S&
CEngineer
QuantitySurveyor
CDMCo-ordinator
4.4AgreeDesignTeamFeeScheduleandDrawdown:
4.5ExecuteDesignTeamAppointmentDocumentation:
4.6ExecuteandIssueDesignTeamProfessionalWarranties:
4.7ExecuteandIssueDesignTeamNovationAgreement:
4.8ConstructionContractParticulars
ContractNoticeIssue
PQQ
PQQEvaluation
ITT
ITTEvaluation
TenderReport
Executeandissuemaincontract
5.0ProjectStrategy
TheUniversityhasdeterminedastrategythatwillbeadoptedoneachprojectforthemanagementofdesign,procurement,constructionandcommissioning,OperationandMaintenance.
ThedesignteamwillbemanagedbytheArchitectasleadconsultant.RolesandResponsibilitiesaredetailedwithinthefollowingtemplates;
-ScopeofService–ExternalProjectManager
-ScopeofService–Architect
-ScopeofService–MechanicalandElectrical
-ScopeofService–StructuralandCivil
-ScopeofService–QuantitySurveyor
-ScopeofService–CDMC&
SWMP
-ScopeofService–BREEAMAssessor
-ScopeofService–Acoustics
-ScopeofService–FireEngineer
-ScopeofService–MonitoringArchitect
ConsultantDesignResponsibilityMatrix
Reference:
Date:
1=PRIMARYRESPONSIBILITY
2=SUPPORTINGROLE
IfthereisnoExternalProjectManager,theEstatesProjectManagerwillundertakeallthedetailedresponsibilities.
ExternalProjectManager
Civil/StructuralEng
Mechanical&
ElectricalEng
CDMCoordinator
MainContractor
AppointmentofConsultants
1
2
BriefInformation
Instructchangestobrief
Designteamco-ordination
Co-ordinationofservices
Siteownershipandboundaries
Landand/orbuildingsurvey
Servicessurvey
Adjoiningpremises/department
Airand/orwatercondition
PlanningApplication
BuildingRegsComplianceCertificate
FireCertificateApplication
WaterretainingtankingDPC’sandDPM’s(roof)
Buildingenvelopedesign
Internalwalls,partitions,ceilings
Internalfinishes
Buildingstructureelements
Paintperformancespectoprimarysteel
Galvperfspectoexternalsteel
Subcontractordesigncriteriaforconcealedsteelworkconnections
Architecturalmetalwork
Undergrounddrainage
Roofdrainage
Intdrainage
Intsanitaryinstallation
Sanitaryfittings
Rainwatersystem
Mainwatersupply
Coldwaterdistribution
Hotwatersupply/distribution
Structurefireprotectionperformancespecforintumescentpaint
Firestopping
Firefightinginstallationsandstrategy
Firealarm/detection
Electricalpowerandlighting(InternalandExternal)
Communicationssystems
Securityservices
BMSSystems
Lightningprotection(earthingandbonding)
Heatinginstallation/fuelsupply
Buildersworkholes>
150mmx150sq
Buildersworkholes<
150x150
Mechanicalengineering
Plantroomlayouts
Airconditioningsystems
Maingassupply/distribution
Lifts,conveyorsandhoists
Refrigerationplant/installations
ExternalEnvelopeCleaningandMaintenance
LaboratoryEquipment
SpecialistEquipmentschedule
Labfurniture
Servicessoundcontrolandacoustics
AVSystems
Videoconferencingservices
Fixedfurnitureandfittings(notloose)
Signage
Hardandsoftland