Constructionofkeyproblemsofprojectprogresscontrol
Abstract
Constructionprogresswasoneofthethreeobjectivesoftheprojectwhichisanimportantcomponentofprojectmanagement.Reasonable,scientific,efficiencyofprojectconstructionscheduleisthekeytoachievetheprojectobjectivescontrol.Onlyduringthepreparationstage,stageofprogressoftheprogrammerdesignstage,plansandimplementationofconstructionandotherlinks,takingfullaccountofthefavorablefactors,rationalcoordinationoflimitedresources,caneventuallyachievetheprogressrequiredbythetarget,tocreateadvaneed,civilizationandconstructionprocessandlayasolidmaterialfoundation.
Keywords:
Constructionprojects;
Progresscontrol;
Keyissues
Progress,investment,qualityisthethreeobjectivesoftheproject;
thereisarelationshipofmutualdependenceandmutualrestrictionbetweenthem.Projectschedulecontrolisanimportantcomponentofprojectmanagementandistoensurethatprojectobjectivescontroliscompletetheprerequisitefortherealizationof,toensuretheprojectduration,therationaluseofresources,andlowercosts,topreventplanchangestoobigandimportantguaranteeforimprovingtheefficiencyofproject.Managementshouldfocusonthefollowingaspects:
1.Attachesgreatimportancetoprojectconstructionpreparation
Projectpreparationisanimportantcomponentofconstructionproduction,anditisintendedtoprojectgoals,resourcesupplyandselectionofconstructionplan,spatiallayoutandthevariousaspectsoftimeandmanpowerarrangement.Italsoisthefundamentalguaranteeforthesmoothconductofcivilengineeringconstructionandequipmentinstallation.Therefore,preparingcarefullyfortechnicalbeforeconstruction,materials,labororganizationspreparationandover-the-counterpreparationsforconstructionsitepreparation,hasanimportanteffectonrationalsupplyingresourcestospeeduptheconstructionspeed,improvingprojectqualityensuringconstructionsafetyandwinningsocialreputation.To
strengthentheprojectprogresscontrol,youmustattachgreatimportaneetotheprojectpreparation,preparationbeforeconstruction.
2.Deploymentandconstructionofconstructionprogramming
Constructionsofcomprehensivearrangementsforthedeploymentprojectasawholeis,andmakesdecisionsonmajorstrategicissuesinconstruction.Prefectofconstructiondeploymentiseffectivecontrolengineeringprogress,guaranteesengineeringquality,andsavesengineeringinvestmentofprimaryprotection,anditspreparationshouldreflectreasonableoforganizationarrangementsandtaskdivision,andestablishprovenof,andreasonablerunningofProjectManagersector;
personnelofsetandthedivisionshoulddofullmobilizationitsenthusiasm,andmakeofprofessionalplay;
establishedofspecializationconstructionorganizationsystemandforengineeringminpackage;
divisionconstructionstage,determinesstagingbatchconstruction,andcommissioningofarrangementsandmainprojectandinterspersedproject.
Inadditiontothedeploymentconsistsofperfectconstruction,preparationofreasonableconstructionplan,toensuretheeffectiveprogressoftheproject,constructionreadinessplanningshouldalsobeenincludedthedevelopmentspecification.Mainsite-widepreparations,includesmaterialsforideological,organizationalpreparation,technicalpreparation,andsoon.Majoritemsofworksorthemainunitofengineeringandspecialprojectsshouldbedevelopedintheconstructionorganizationtodesignitsconstructionprogrammed.Theaimisthepreparationoftechnicalandalsofortheconstructionofwellunderwayandprovidesabasisforrationalarrangementoftheprojectsite.Therefore,youshouldcalculatethequantitytodeterminetheprocess,selectthecommandmentsandmainconstructionmethodoflargeconstructionmachine.
Engineeringdeterminationoftheorder,needtobeconstructedbystagesandingroups.Itshouldbethefirstundergroundandthentheground,afterthefirstdeep-shallow,afterthefirstline,extension,undergroundpipelineconstruction,withthesupplyofvarioustypesofmaterialandtechnicalconditionsandshouldbebalaneedandrationalutilizationoftheseresourcesbetweencoordinatedconstructionofpromotingbalaneed.
3.Inaccordancewiththecontract'
sdurationrequirements,wellconstructionprogresscontrol
Accordingtothedurationofthecontracttocompleteconstruction,bothcontractrequirementsarealsoobjectstoachievebusinessgoals.Inthisconnection,theconstructionunits(owners)withtheconstructionunitoftheinterestsofbothsidesarefullyconsistent.Therefore,strengtheningconstructionprogresscontrolensuresthatthedurationofthecontractperformaneeisaprojectmanagerandmaincontentofthebasicduties.Planisaprerequisiteforcontrol,ifhasnotitwillbeoutofcontrolwhichistocompareactualandplannedvalues,identifydeviationsduring,andforfeedbackadjustment.Preparationofconstructionprogressplantocontrolthedurationvalueisdetermined,andcomeupwithaguaranteeschemeimplementationofeffectivemeasurestoguaranteethedurationplannedcompletionofthecontractperiod.
Preparationofprogressistodecidewhattowhentodo,orwhentheprogressoftheprojecttodowhatextent.Whateveristheprocessoftheprojectitself,orwithotherconstruction-relatedwork,shouldbeintegratedintothescheduleto,or,whoseprogressyouwanttomakeaschedule.Typesofprojectscheduleclassificationbasedoncontentistargetedschemesandsupportschemes.Schedulefortheprojectitselfisthemostbasicgoalplanthatdeterminesthedurationoftheprojectgoals.Inordertoachievethisgoal,youhavearangeofsupportplans,suchasplanningmaterialusage,workingcapitalplanningmaterialusage,andequipmentuseplans,laboruseplantouseplan,semi-finishedproductsandcomponents,andsoon.Controlthelengthoftimeitcamefromoverallprogressplanandphaseplan.Totalprogressschemecontrolthewholeprocessofprojectconstruction,andphasedplanincludestheprojectconstructionprogressplanandten-years,quarters,months,weeksofjobschedules,andsoon.Ithasatextplan-planwithachartfromtheexpressions.Theformeriswithatextdescriptionofeachstageofconstruction,andtheimageofprogresstoachieverequirements;
thelatteriswithimageandsimplechartstoexpresstheconstructionschedule.AsfarasIknow,baristhemostcommonlyusedscheme,networkplanning,andslash-typescheme.Ithasoverallprogressplanandthepartitionplanfromthescopeofmanagement.Masterplansareproject-orientedglobalstrategyprogressoftheplan,generallycruder.WhiletheplanisforabottlegourdorProject~Professionalprogressoftheworkplan,generallymoredetailed.
4.Preparationofprojectschedule
a.Thisprojectofprojectcontract.Provisionistodeterminethedurationofthecontractdurationinplannedvaluebasis.Projectstartandcompletiondatesstipulatedinthecontract,mustbeimplementedbyschedule.Scheduleoftheultimategoalisthroughreasonableprogressdesign,toguaranteedurationcompletedontime.
b.Constructionofenterpriseproductionandmanagementofreasonableplan.Throughtheconstructionofenterpriseproductionandmanagementofrationalplanning,toensureprojectefficiency,isthemajorcomponentoftheplan.Obeyingthebusinessprincipleofguidaneeandmeetingtherequirementsofenterprisebalaneeachievethebestinterestsoftheenterprise.
c.Drawinginformation.Drawinginformationisthebasisandpremiseofrationaldesignofconstructionschemesforconstruction.Constructionprogressplanmustbelinkedwiththeprogressofthedesignplan,andmustbebasedonthedateofdeliverynumberagreementtoarrangetheappropriatepartoftheconstructiontime,whichisalsoagoodwayofconstructionriskpreventionandguaranteeconstructionquality.
d.Constructionorganizationdesignofthisprojectisoneofthestrongbasisforthepreparationofprojectscheduling.Thisinformationdefinesconstructioncapacitydeploymentandmethodofconstructionandreflectstheconstructioncharacteristicsoftheproject,whichformsthebasisoftargetsatvariousstagesintheprocessofdeterminingconstructionplans.
e.Materialsandequipmentsupplyplan.Ifyoualreadyhaveonthematerialandequipmentandturnovermaterialsupplyplan,theconstructionprogressplanmustbecoordinatedwiththeproject.Inadditiontotheabovefivepointsmakingprogressonaprojectplansasthebasisforthemainconsideration,youshouldbeawareofinformationaboutsiteconstructionconditions,includinghydrological,climateandenvironmentaldatainthefieldofconstructionandtransportationconditions,energysupply,auxiliaryproductioncapacity.Alsopriortothepreparationofprojectconstructionprogressplan,similartoanalreadybuiltoractualconstructionscheduleneedstobecollected,andyoushouldseriousanalysis,organize,listcontrolconstraint,cleartheinflueneeofdurationtoachievemandatorytimelimits,forthepreparationofprojectprogressaswellprepared.
5.Theprojectprogr
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 外文 文献 翻译 施工 项目 进度 控制 关键 问题 Constructionofkeyproblemsofpr
链接地址:https://www.bdocx.com/doc/17472346.html