一、计算式
Cos2=0.999
(3.1/cos2-0.3)/1.001*1.415=3.962
((8.404-0.6)*(5.4-0.3)*0.1+3.962*5.4*0.1*2)*2=16.518
16.518-14.14=2.378m³
建设单位:
签名:
年月日
监理单位:
施工单位:
涵前铺砌M7.5浆砌片石30cm厚
((8.404-0.6)*(5.4-0.3)*0.3+1.5*0.3*(5.4-0.3)*2+(1.2+1.2+0.3)*0.3*5.403+3.962*5.4*0.3*2+8.404*0.3*1.5)*2=75.05
75.05-61.87=13.18m³
涵身入口处50cm厚砂砾垫层
7.3*2.3*0.5*2=16.79
16.79-15.87=0.92m³
涵身下部20cm厚砂砾垫层
7.3*60.04*0.2=87.66
87.66-82.85=4.81m³
涵身下部C20砼垫层10cm厚
(60.04+4.6)*7.3*0.1=47.19
47.19-44.6=2.59m³
C30箱涵底板45cm厚
(60.04+4)*6.9*0.45=198.84
198.84-187.31=11.53m³
C30箱涵侧墙45cm厚
(60.04+4)*(3*0.45+0.5*0.3*0.5)*2=182.51
182.51-172.91=9.6m³
C30箱涵顶板45cm厚
(60.04+4)*6.9*0.45=198.844
198.844-196.92=1.924m³
C30混凝土翼墙50cm厚
((0.75+3.1)*3.9-0.5*3.1*3.1)*0.42*2*2=17.153
17.153-28.13=-10.98m³
涵顶栏杆下部实心砖墙
0.37*(0.363+0.365)*14.6=3.93
3.93-2.73=1.2m³
翼墙上部C30混凝土帽石20cm厚
0.2*0.47*14.6*2=2.745
2.745-1.4=1.345m³
2.5cm厚花岗岩贴面
(0.363+0.365)*14.6+(0.375+2.75-0.125+0.5)*22.5*2=168.129
168.129-172=-3.271㎡
非预应力钢筋
一、计算式
变形缝:
9*377.42/1000=3.3968T
涵身:
12099*64.04/10/1000=77.482T
预埋件:
11.72/1000=0.0234T
栏杆底座:
319.3*2/1000=0.638T
3.3968+77.428+1.697+0.0234+0.638-66.556=16.681T
K3+660箱涵
(3.1/cos4-0.3)/1.002*1.416=3.965
((8.417-0.6)*(5.4-0.3)*0.1+3.965*(5.4-0.3)*0.1*2)*2=16.062
16.062-14.14=1.892m³
涵前铺砌30cm厚M7.5浆砌片石
((8.417-0.6)*(5.413-0.3)*0.3+1.5*0.3*(5.413-0.3)*2+(1.2+1.2+0.3)*0.3*(5.413-0.3)+3.965*(5.413-0.3)0.3*2+(8.417+3.965*2)*0.3*1.5)*2=80.507
80.507-62.06=18.487m³
涵身下部入口处50cm厚砂砾垫层
(2.3*0.5*7.3)*2=16.79
16.79-13.84=2.95m³
71.183*7.3*0.2=103.927
103.927-98.23=5.697m³
涵身下部C20混凝土垫层10cm厚
(71.183+4.6)*7.3*0.1=55.332
55.332-52.29=3.042m³
(71.183+4)*0.45*6.9=233.443
233.443-219.91=13.533m³
(71.183+4)*(3*0.45+0.5*0.3*0.5)*2=214.272
214.272-202.99=11.282m³
233.443-229.52=3.923m³
C30混凝土翼墙
17.153-28.13=-10.977m³
14.6*0.37*(0.646+0.635)=6.92
6.92-2.73=4.19m³
C30翼墙上部帽石
14.6*0.2*0.47*2=2.745
花岗岩贴面
0.375*22.5*2+(0.646+0.635)*14.6+(2.625+0.5)*22.5*2=176.203
176.203-172=4.203㎡
预应力钢筋
11*377.42/1000=4.152
12099*75.183/10/1000=90.964
翼墙:
848.53*2/1000=1.697
11.72*2/1000=0.02344
319.03*2/1000=0.638
4.152+90.964+1.697+0.02344+0.638-67.67=29.804T
C25混凝土端墙
K2+900圆管涵
(1.7*1.94-3.14*0.6*0.6)*0.4*2=1.734
1.734-0.51=1.224m³
K4+025
K3+183.5圆管涵
(44.5-0.24-0.12-0.2)*2*0.2*1.08=18.982
18.982-19.22=-0.238m³
流水槽口10mm钢筋拦污网
(1.2*4+0.3*8)*2*0.617=8.88
8.88-5.69=3.19kg
二、计算式
三、计算式
涵
致:
如皋市2013年度农村桥梁各施工中标单位:
根据省财政厅和如皋市人民政府为民办实事的进度要求及市财政局与各级人民政府签订的农村桥梁实施协议规定:
2013年度农村桥梁必须于2013年10月底前完工。
8月1日至8月6日如皋市人大代表、我局行风监督员对我市今年农村桥梁进行了检查,发现还有部分桥梁还没有进场施工。
现要求未进场施工的中标单位必须于8月20日前进场,逾期未进场的,我局将约谈中标企业负责人。
抄报:
如皋市人民政府
抄送:
各镇(街道)财政所(局)
如皋市财政局
2013年8月7日