97 中铁十四局宁启电化路基施工进展情况统计表Word文件下载.docx
- 文档编号:17068699
- 上传时间:2022-11-28
- 格式:DOCX
- 页数:45
- 大小:22.83KB
97 中铁十四局宁启电化路基施工进展情况统计表Word文件下载.docx
《97 中铁十四局宁启电化路基施工进展情况统计表Word文件下载.docx》由会员分享,可在线阅读,更多相关《97 中铁十四局宁启电化路基施工进展情况统计表Word文件下载.docx(45页珍藏版)》请在冰豆网上搜索。
K9+382.78~K10+053.61
13
K10+053.61~K10+073.61
14
K10+124.17~K10+154.17
15
K10+154.17~K10+875
16
K10+875~K11+280
17
K11+280~K11+400
18
K11+400~K11+605.6
19
K11+605.6~K11+625.6
20
K11+697.51~K11+717.51
21
K11+717.51~K11+900
22
K11+900~K12+030.00
23
K12+030.00~K12+155.00
24
K12+155.00~K12+290.00
25
K12+290.00~K12+345.00
26
K12+345.00~K12+412.76
27
K12+412.76~K12+432.76
28
K12+432.76~K12+473.70
29
K12+473.70~K12+493.70
30
K12+493.70~K13+096.45
31
K13+096.45~K13+116.45
32
K13+116.45~K13+163.45
33
K13+163.45~K13+183.45
34
K13+183.45~K13+210.00
35
K13+210.00~K13+290.00
36
K13+290.00~K13+705.51
37
K13+705.51~K13+725.51
38
K13+763.41~K14+240.00
39
K14+240.00~DK15+580
40
DK15+580~DK15+716
水泥搅拌桩
41
DK15+710.56~DK16+466.405
42
DK16+466.405~DK16+496.405
43
DK17+300.76~DK17+330.76
44
DK17+330.76~DK19+120
45
DK19+120~DK19+720
46
DK19+720~K20+574.95
47
K20+574.95~K20+594.95
48
K20+594.95~K20+639.99
49
K20+639.99~K20+659.99
50
K20+659.99~K21+747.79
51
K21+747.79~K21+767.79
52
K21+767.79~K21+819.11
53
K21+819.11~K21+839.11
54
K21+839.11~K22+189.96
55
K22+189.96~K22+209.96
56
K22+209.96~K22+256.14
57
K22+256.14~K22+276.14
58
K22+276.14~K22+305
59
K22+305~K22+500左侧
60
K22+314.2~K22+500右侧
61
K22+500~K23+100
62
K23+100~DK23+517.55
63
DK23+517.55~DK23+547.55
64
DK23+547.55~DK23+612.45
65
DK23+612.45~DK23+642.45
66
DK23+642.45~DK23+795.3
多向搅拌桩
67
DK23+795.3~DK23+825.3
68
DK23+825.3~DK23+869.42
69
DK23+869.42~DK23+899.42
70
DK23+899.42~DK24+629.61
71
DK24+629.61~DK24+659.61
72
DK24+659.61~DK24+750
73
DK24+750~DK24+780
74
DK26+595.18~DK28+520
75
DK28+520~DK29+116.44(=K29+200)
76
K29+200~K30+596.52
77
K30+596.52~K30+626.52
78
DK33+713.77~DK33+988.2
水泥搅拌桩(已施工)
79
DK33+988.2~K34+158.35
80
K34+158.35~K34+222.42
水泥土挤密桩(已施工)
81
K34+222.42~K34+995
82
K34+995~K35+400
高压旋喷桩(正在施工)
83
K35+400~DK35+575
84
DK35+575~DK35+795
85
K35+796.35~K35+816.35
86
K36+065.37~K36+095.37
87
K36+095.37~K36+314.99
88
K36+314.99~K36+344.99
89
K36+344.99~K36+384.73
90
K36+384.73~K36+414.73
91
K36+414.73~DK36+975
92
DK36+975~K37+035.025
93
K37+015.025~K37+035.025
94
K37+939.95~K38+651.11
95
K37+939.95~K37+959.95
96
K38+631.11~K38+651.11
97
K38+723.01~K38+743.01
98
K38+723.01~K38+753.01
99
K38+753.01~K39+106.37
100
K39+106.37~K39+136.37
101
K39+116.37~K39+136.37
102
K39+225.22~K39+245.22
103
K39+225.22~K39+255.22
104
K39+255.22~K39+277
105
K39+277~K40+210
106
K40+210~K40+390
107
K40+390~K40+890.7
108
K40+890.7~K41+075
109
K41+075~K41+291.03
110
K40+975~K41+291.03
花管注浆
111
K41+499.895~K41+529.895
112
K41+529.895~K42+520
113
K42+520-K42+665
114
K42+665~K43+100
115
K43+100~K43+233.325
116
K43+318.975~K43+513.31
花管注浆、高压旋喷桩
117
K43+513.31~K44+858.08
118
K44+967.43~K45+700
119
DK45+700-DK45+921.6
120
DK45+934.26-DK45+993.41
121
K46+000-K46+375
122
K46+710-K46+950
123
K46+950~K50+735
124
K50+735~K50+890
多向水泥搅拌桩
125
K50+890~K51+353
126
K52+355.935~K53+362
127
K52+100~K53+415
128
DK53+415~K53+567
压密注浆、高压旋喷桩
129
I标二工区
K53+580-K53+815
三重管高压旋喷桩
130
压密注浆
131
K53+815-K53+835(过渡段)
无
132
K53+850~K54+275
133
K54+275-K54+433
134
K54+433.00-K54+475.00(过渡段)
135
K54+475.00-K54+540.56
136
K54+540.56-K54+572.56(过渡段)
137
K54+572.56-K54+730.66
138
K54+730.66-K54+762.66(过渡段)
139
K54+750~K54+936.3
140
K55+652.80-K55+684.80(过渡段)
141
K55+684.80-K55+971.66
142
K55+971.66-K56+003.66(过渡段)
143
K56+003.66-K56+035
144
K56+035~K56+210
145
K56+210-K56+314.4
146
K56+314.40-K56+346.40(过渡段)
147
K56+346.4-K56+498
148
K56+498~K56+516
149
K56+494.63-K56+526.63(过渡段)
150
K56+623.80-K56+655.80(过渡段)
151
K56+655.8-K56+790
152
K56+790~K57+225
153
K57+225-K58+006
154
K58+006.00-K58+038.00(过渡段)
无
155
K58+038.00-K58+210.39
156
K58+210.39-K58+242.39(过渡段)
157
K58+242.39-K58+407.05
158
K58+407.05-K58+439.05(过渡段)
159
K57+290~K57+950
160
K57+950-K58460
161
K58+460~K58+750
162
K58+750~K58+825
163
K58+825~K58+950
164
K58+950-K58+975
165
K58+975~K59+301.65
166
K59+540.03-K59+572.03(过渡段)
167
K59+665.50-K59+697.50(过渡段)
168
K59+697.5-K59+907
169
K59+907-K60+160
右侧水泥搅拌桩
170
左侧水泥搅拌桩
171
K60+160-K60+005.3
172
K60+005.30-K60+041.30(过渡段)
173
K60+041.30-K60+043.40
174
K60+043.40-K60+075.40(过渡段)
175
K60+075.40-K60+249.00
176
K60+249.00-K60+281.00(过渡段)
177
K60+281.00-K60+275.60
178
K60+275.60-K60+307.60(过渡段)
179
K60+307.60-K60+805.95
180
K60+805.95-K60+837.95(过渡段)
181
K60+837.95-K60+879.00
182
K60+879.00-K60+921.00(过渡段)
183
K60+921.00-K60+997.50
184
K60+997.50-K61+029.50(过渡段)
185
K61+029.50-K61+159.11
186
K61+159.11-K61+191.11(过渡段)
187
K61+191.11-K61+209.89
188
K61+209.89-K61+241.89(过渡段)
189
K61+241.89-K61+225
190
K61+225-K61+480
右侧高压旋喷桩
191
K61+357.21-K61+389.21(过渡段)
192
K61+480-K61+709.1
193
K61+709.01-K61+770.18
194
K61+747-K61+767(过渡段)
195
K61+694.00-K61+726.00(过渡段)
196
K61+901.38-K61+921.38(过渡段)
197
K61+901.38-K62+124.19
198
K62+012.85-K62+044.85(过渡段)
199
K61+104.19-K62+124.19(过渡段)
200
K62+185.55-K62+205.55
201
K62+185.66-K62+377.65
202
K62+385.00-K62+417.00(过渡段)
203
K62+388.35