《桩基钢筋笼吊装方案Word格式文档下载.docx》由会员分享,可在线阅读,更多相关《桩基钢筋笼吊装方案Word格式文档下载.docx(16页珍藏版)》请在冰豆网上搜索。
1.1总起重量的确定............................................................................................................2
1.2钢筋笼吊装加固............................................................................................................2
1.3主副吊点的确定............................................................................................................2
1.4起重垂直高度计算........................................................................................................2
1.5起重机选型确定............................................................................................................3
第二章吊装验算........................................................................................................................3
2.1钢丝绳强度验算............................................................................................................3
2.2主、副吊扁担梁............................................................................................................4
2.3吊点加固........................................................................................................................4
2.4卸扣................................................................................................................................4
2.5滑车................................................................................................................................4
第三章吊装工序........................................................................................................................4
第四章安全保证措施................................................................................................................6
4.1做好岗前安全吊装培训................................................................................................6
4.2双机抬吊措施................................................................................................................6
4.3吊车操作安全措施........................................................................................................6
4.4起重工(起重机司机、起重指挥、信号、挂钩工)安全操作规程........................7
4.5吊装..............................................................................................................................10
4.6吊索具..........................................................................................................................10
第五章高空坠落及物体打击、吊车倾覆应急预案..............................................................11
5.1报警和接警处置程序..................................................................................................11
2
5.2现场保护的组织程序..................................................................................................11
5.3应急物资和设备..........................................................................................................11
5.4防护、救援的程序和措施..........................................................................................11
5.5通讯联络、安全防护措施..........................................................................................12
附表一30吨汽车起重机性能表.............................................................................................13
附表二25吨汽车起重机起重性能表.....................................................................................14
附图钢筋笼吊点布置示意图..................................................................................................15
第一章吊装设备选型及方法
1.1总起重量的确定
本工程单节钢筋笼重量最大规格为Ø
1.2m×
31m,最大重量约为3吨。
(含包括扁担梁、吊钩、滑轮组、卸扣、钢丝绳小计0.35T)。
1.2钢筋笼吊装加固
钢筋笼采用8点起吊,钢筋笼吊点处用Ø
16mm圆钢加固。
钢筋笼起吊时,顶部要用两根扁担横梁,其长度为2米。
为了不使钢筋笼在起吊时产生
很大的弯曲变形,采用两台吊车同时操作。
钢筋笼下端可系绳索用人力控制,防止钢筋笼在空中晃动。
起吊时不允许钢筋笼下端在地面上拖引,以防造成下端钢筋弯曲变形。
1.3主副吊点的确定
本工程钢筋笼起吊设备采用一台30吨汽轮吊车和一台25吨汽轮吊车。
起重方式采用8点抬吊,主吊设4个吊点,副吊设4个吊点,其中主吊2点设于笼顶上方距离笼顶距离为1.4米,顺向朝下8米、6米、8米处间距布置(附图钢筋笼吊点布置示意图)。
3
1.4起重垂直高度计算
当钢筋笼完全由主吊吊起时,起重垂直高度由以下几项相加:
钢筋笼长度31米(按最大长度考虑)
扁担梁下钢丝绳到钢筋笼顶1.2米
扁担梁上钢丝绳垂直高度1.3米
扁担梁高度0.25米
吊钩底到吊臂顶距离4米考虑
起吊后钢筋笼垂直离地距离按1.0米考虑
H=31+1.2+1.3+0.25+3+1.0=37.75米
1.5起重机选型确定
1、主吊30吨汽轮吊车(暂按徐工QUY30型考虑),当臂长为40.4米时,回转半径8
米时,起重量为7.5吨;
回转半径10米时,起重量为6.5吨。
(附表一重性能表)
30吨汽车起重机起
2、辅吊25吨汽轮吊车(暂按徐工QUY25型考虑),当臂长长度为27.95米时,回转半径10米时,起重量为5.3吨;
回转半径12米时,起重量为3.9吨;
回转半径14米时,起重量为2.9吨。
副吊按承担钢筋笼最大负荷的50%考虑,即3吨×
50%=15吨<2.9吨,满足要求。
(附表二25吨汽车起重机起重性能表)
3、起吊作业时必须严格按照计算臂长长度进行安装在额定范围的起重角度、回转半径进行操作。
吊机回转时应缓慢,必须在指挥的信号下动作。
4
第二章吊装验算
2.1钢丝绳强度验算
本工程使用的钢丝绳均为17.5mm,钢丝绳破断拉力以15500kg计,安全系数取K=6,换算系数为0.82(见《建筑施工手册大全》)。
主钢丝绳主要数据如下表:
1、若钢筋笼由主、副吊水平吊起时:
扁担梁下由主、副吊共4根钢丝绳同时受力,所以每根钢丝绳承受拉力P=3000/4/cos50°
=1166(KG)<2683(kg),故每根钢丝绳的强度能够满足要求。
2、当钢筋笼完全竖直起来,最终由笼头上2根17.5mm钢丝绳承受拉力时,每根钢丝绳受力情况:
5
P=3000/2=1500(kg)<2683(kg),满足强度要求。
2.2主、副吊扁担梁
扁担梁拟采用I25b工字钢加工定做,工字钢总长2米,截面高度为25cm。
2.3吊点加固
主副吊各吊点拟采用Ø
16mm圆钢加工成