洞口开挖边坡支护Word文档下载推荐.docx
- 文档编号:14677541
- 上传时间:2022-10-23
- 格式:DOCX
- 页数:16
- 大小:67.40KB
洞口开挖边坡支护Word文档下载推荐.docx
《洞口开挖边坡支护Word文档下载推荐.docx》由会员分享,可在线阅读,更多相关《洞口开挖边坡支护Word文档下载推荐.docx(16页珍藏版)》请在冰豆网上搜索。
2.作业准备......................................................................................................................................1
2.1内业技术准备...................................................................................................................1
2.2外业技术准备...................................................................................................................1
2.技术要求....................................................................................................................................2
3.施工程序及工艺流程................................................................................................................2
4.1施工程序..........................................................................................................................2
4.1.1截水沟施工..........................................................................................................2
4.1.2边仰坡施工..........................................................................................................3
4.1.3进洞超前预支护...................................................................................................3
4.2工艺流程..........................................................................................................................4
5.施工要求......................................................................................................................................4
4.劳动组织....................................................................................................................................5
4.材料要求......................................................................................................................................6
7.1片石..................................................................................................................................6
7.2锚杆..................................................................................................................................6
7.3注浆砂的要求..................................................................................................................6
7.4钢筋网..............................................................................................................................6
7.5水泥..................................................................................................................................7
7.6粗细骨料应符合以下要求...............................................................................................7
7.7外加剂..............................................................................................................................7
7.8速凝剂..............................................................................................................................8
7.9水......................................................................................................................................8
7.10材料称量的允许误差....................................................................................................8
7.机具设备配备............................................................................................................................9
8.质量控制及检验........................................................................................................................9
9.安全及环保要求....................................................................................................................11
10.1洞口土石方施工安全技术措施..................................................................................11
10.2喷锚支护安全措施................................................................................................11
10.3环保要求...................................................................................................................12
i
洞口开挖边坡支护作业指导书1.适用范围
适用于新建铁路沪昆客运专线CKGZTJ-11标段大茶山隧道(出口段)、刘家庄隧道洞口段开挖边仰坡支护施工。
2.作业准备
2.1内业技术准备
2.1.1施工调查前应查阅设计文件和资料,制定调查提纲。
施工调查
内容应包括工程概况、施工条件、地形地质及其他与工程相关内容。
调查结束后应编写施工调查报告。
2.1.2隧道洞口段开挖边仰坡支护施工前,应进行施工技术交底,作
业人员应进行岗前培训和安全教育,特殊工种的作业人员应持证上岗。
2.2外业技术准备
2.2.1导线复测完毕,成果可用。
2.2.2砂、石、料、钢材、水泥等原材料试验完成,混凝土配合比设计完成并经监理审批。
2.2.3分项开工报告已批复。
2.2.4施工机械配备应满足正常施工要求。
实施中,可根据施工进度
1
要求分期、分批组织上场。
隧道施工机械配套应针对隧道大断面的
特点,以实现机械化均衡生产为目标,配套的生产能力应为均衡施工能力的1.2~1.5倍。
3.技术要求
3.1客运专线铁路隧道工程施工技术指南(T2214-2005)
3.2铁路工程施工安全技术规程(TB10401.1-2003)
3.3铁路隧道喷锚构筑法技术规范(TB10108-2002)
3.4铁路隧道工程施工质量验收标准(TB10417—2003)
3.施工程序及工艺流程
4.1施工程序
洞口段开挖边坡支护施工顺序:
施工测量→截水沟→洞口刷坡、挂网锚喷→管棚施作→暗洞开挖、支护→监控量测。
4.1.1截水沟施工
边仰坡开挖前先行截水沟施工,形成地表排水系统,由于地势
陡峭,汇水面积小,水沟采取C25砼、0.4m×
0.6m直角梯形沟,沿开挖线外5米顺山势布置,保证排水通畅及美观。