深基坑支撑支护作业指导书Word文档下载推荐.docx
- 文档编号:14593972
- 上传时间:2022-10-23
- 格式:DOCX
- 页数:18
- 大小:472.68KB
深基坑支撑支护作业指导书Word文档下载推荐.docx
《深基坑支撑支护作业指导书Word文档下载推荐.docx》由会员分享,可在线阅读,更多相关《深基坑支撑支护作业指导书Word文档下载推荐.docx(18页珍藏版)》请在冰豆网上搜索。
4.
5.
6.
7.
8.
9.
目的.......................................................................................................................................................................................1
编制依据.............................................................................................................................................................................1
适用范围.............................................................................................................................................................................1
施工准备工作...................................................................................................................................................................1
4.1技术准备...................................................................................................................................1
4.2支撑施工材料准备:
...............................................................................................................1
主要机械设备...................................................................................................................................................................2
劳动组织.............................................................................................................................................................................2
施工工艺流程...................................................................................................................................................................2
施工作业方法及要求.....................................................................................................................................................2
8.1混凝土支撑施工方法..............................................................................................................2
8.2钢支撑施工方法.......................................................................................................................4
施工质量控制标准与措施...........................................................................................................................................8
9.1质量标准...................................................................................................................................8
9.2质量控制措施...........................................................................................................................8
10.安全要求和安全措施.....................................................................................................................................................10
10.1现场安全保证措施...............................................................................................................10
10.2.支撑安全措施.......................................................................................................................11
10.3起重机机械安全措施...........................................................................................................11
10.4现场临时用电(焊接)安全措施.......................................................................................11
10.估算指标.............................................................................................................................................................................12
深基坑支撑支护作业指导书
地铁分册
深基坑支撑支护作业指导书
1.目的
明确深基坑支撑、支护作业的组织设计、作业流程、设备选型及材料准备,以达到指导、规范深基坑支撑、支护作业施工的目的。
2.编制依据
2.1本工程施工的设计图纸和设计技术要求;
2.2本工程地质勘察报告;
2.3本工程基坑周边管线图;
2.4本工程施工组织设计;
2.5施工规范及标准
《地下铁道工程施工及验收规范》(GB50299——1999(2003版)
《混凝土结构工程施工质量验收规范》(GB50204-2002)
《建筑基坑支护技术规程》(JGJ120-99)
《建筑与市政降水工程技术规范》(JGJ/T111-98)
《钢筋焊接及验收规范(程)》(JGJ18-2003FF09)
《施工现场临时用电安全技术规范》(JGJ46-2005)
3.适用范围
本作业指导书适用于地铁车站深基坑的支撑与支护工程。
4.施工准备工作
4.1技术准备
在施工前,做好技术交底工作,将砼支撑尺寸、配筋形式、施工要求及各道钢支撑位置和预加轴力等技术指标和质量标准,向全体施工人员详细进行技术交底,使全体施工人员熟悉并掌握本工程所执行的各项技术措施和技术标准。
作好安全交底工作,明确危险源,作好安全预控预案,根据危险源制订安全施工措施。
施工混凝土支撑前,根据混凝土支撑尺寸确定入场模板尺寸,现场安排好模板堆放,保证模板质量;
根据混凝土支撑设计需求进入钢筋,钢筋按照型号不同现场堆放好,并覆盖;
现场布置钢筋焊接、绑扎平台。
根据基坑围护结构图纸尺寸,按照计划用量备足各种长度的Φ609×
16钢支撑管、活络头、钢垫箱;
钢垫块、钢楔块、紧固螺栓、铁板等支撑材料,分类堆放在料场。
各种材料必须经质量检验合格方可按施工进度分批进场,确保进场支撑材料均达到设计要求和施工进度要求。
同时计算好的每道支撑施加预应力值相对应的油泵压力表读数;
根据土方开挖进度提前在拼装场按支撑编号及设计长度进行拼装备用。
按施工人员设备按计划进场,全体人员熟悉场地、图纸,并进行施工技术、安全交底。
施工埋置
式支撑前准备好套筒式组合钢垫箱,同时下料准
备好钢牛腿料,一旦工作面出来能及时投入安装。
1
5.设备机械配置
表1:
设备机械需求计划表
序号
设备名称
数量
小型挖掘机
2台
2
电焊机
8套
3
钢筋加工机械
4套
4
50T履带吊
1台
5
液压千斤顶
2套
6.劳动组织
表2:
人力资源需求计划表
工种
数量(人)
工长
4人
电焊工
15人
电工
2人
机械维修工
挖机司机
6
钢筋工
20人
7
木工
8
普工
10人
9
合计:
74人
7.支撑施工工艺流程
第一道钢筋混凝土支撑—→第二道钢支撑—→第三道钢支撑—→第四道钢支撑—→第五道钢支撑(南北端井)
8.施工作业方法及要求
8.1混凝土支撑施工方法
具备开挖条件后,先开挖至第一道钢筋砼支撑底以下0.35m位置,标高为+2.45m,凿除地下墙顶劣质混凝土,根据支撑和钢筋砼便桥的位置浇筑200mm素砼垫层,养护一定时间后放置横向100x100mm方木,上铺50mm厚钢模板,然后支立侧模,施工圈梁、第一道砼支撑,并达到强度后,进行机械设备行走。
图1:
混凝土支撑模板体系图